Presentation is loading. Please wait.

Presentation is loading. Please wait.

SC Activities at IAP Frankfurt

Similar presentations


Presentation on theme: "SC Activities at IAP Frankfurt"— Presentation transcript:

1 SC Activities at IAP Frankfurt
M. Busch March 1st, 2011 Institute for Applied Physics, Frankfurt TTC Meeting

2 Outline Measurements of the CH-Prototype
Status of the 325 MHz CH-Cavity Development of a sc cw linac demonstrator Myrrha update Upcoming Investments Outlook

3 Cryogenic RF Laboratory in Frankfurt
Infra-structure for vertical tests at IAP Control & Diagnosis lead shielding super insulation radiation shield He recovery 200 bar compressor 2kW heating getter-ion pump Linde L140 liquifier, 90 l 4K He transfer line sc filling level sensor piezo excitation temperature measurement magnetic shielding heating

4 The CH-Prototype Number of Gaps 19 Length (mm) 1048 Frequency (MHz)
360 b 0.1 Ep/Ea (bl-definition) 5.2 Bp/Ea [mT/(MV/m)] 5.7 G=RsQ0 (W) 56 Ra/Q (W) (T incl.) 3180 (Ra/Q)G (W2) 178000 Q0 (BCS, 4.2K, 360 MHz) 1.5x109 Q0 (total Rs=150 nW) 3.7x108 W [mJ/(MV/m)2] 92

5

6

7 Test in the old horizontal cryo module (1. prototype)
 Test of the piezo tuner system

8

9 Pick-up Forwarded Piezo signal

10 feasible design, showed quite promising results
Lessons learned from the CH-prototype: feasible design, showed quite promising results since next gen CH-cavities will be operated with beam, some aspects will be very crucial: thermal shrinkage (well appraisable, but tuning necessary) pressure sensitivity (intermediate measurements before final assembly are imperative) field emission (ominpresent -> thorough cleaning (additional flanges)) Fast tuning (elastic deformation of the cavity works (prototype), but consumes longit. Space -> tuning system inside cavity) drift spaces have to be further minimized (different stem geometry)

11 Status of the 325 MHz CH-cavity
b 0.1545 Frequency (MHz) Cells 7 Length bl-def (mm) 505 Diameter (mm) 352 Ea (MV/m) 5 Ep/Ea 5.1 Bp/Ea [mT/(MV/m)] 13 G (W) 64 Ra/Q0 (W) 1248 RaRs (kW2) 80 test Beam test at GSI 11.4 AMeV

12 under construction at RI

13 sc cw Heavy Ion Linac for Super Heavy Elements at GSI
f = 217 MHz A / q < 6.5 9 sc CH-cavities Ea = 5 MV/m Utot = 35 MV Sc Solenoids (8 T)

14 cw Linac Demonstrator Cryo module sc solenoids CH-cavity
First sc CH-cavity will be tested with beam at GSI b=0.065, f=217 MHz, 15 cells RF power 5 kW Cavity: call for tender finished Cryo module sc solenoids CH-cavity

15 Myrrha Beam: 600-1000 MeV Protons Beam current: 4-25 mA (Myrrha, EFIT)
Power: MW (Reactor MWth) Duty cycle: 100% Frequency: MHz Beam stability: 2% power Maximum 3-10 beam trips per year >1 s Transmission: % Losses: 1 W/m Lay-out for a 175MHz RFQ (4-Rod) / r.t. CH/ s.c. CH section is currently investigated. Tests for a r.t. & s.c. CH-Cavity are planned. Design of a RFQ prototype module for high power tests has started

16 Upcoming Investments until Mid of 2012
Amplifier 50 kW (pulsed) 325 MHZ Amplifier 6 kW (cw) 217 MHz Concrete bunker 6x4 m (shielding) New horizontal cryo module 3000 l Helium storage 325 MHz CH-cavity 217 MHz CH-cavity 9T Solenoids (2x) Total investment: 2200 k€

17 Outlook Most parts of the 325 MHz CH-cavity are fabricated, assembly and first tests within the next months 217 MHz cavity (cw linac demonstrator) is in final design phase, production starts in approx. 3 months Lay-out for all 9 cavities for the cw linac is in progress Myrrha design phase has started

18 Thank you for your attention


Download ppt "SC Activities at IAP Frankfurt"

Similar presentations


Ads by Google