Download presentation
Presentation is loading. Please wait.
1
PRESENTATION TO PARLIAMENT SELECT COMMITTEE
ON PETITIONS & UNDERTAKINGS Presented by Mbulelo Peterson 3 MAY 2017
2
PRESENTATION OUTLINE SANRAL’s Service Delivery Model
SANRAL Philosophy on asset preservation Budget breakdown Secondary Strategic Network Active Projects Assistance to Province N2 Wild Coast Update
3
SANRAL’S SERVICE DELIVERY MODEL
SANRAL is the implementing arm of the Department of Transport. SANRAL was established in 1998 by an act of parliament. SANRAL’s mandate is to plan, design, construct and maintain the National Road Network. SANRAL opted to carry out this mandate by outsourcing the design, construction and maintenance of the network by making use of private consulting firms and construction companies. SANRAL opted to be an INFORMED CLIENT that retained the planning, management and decision making capacity in-house.
4
SANRAL PHILOSOPHY ON ASSET PRESERVATION
1. Asset Preservation and Management come first! 2. One has to plan and budget for the maintenance and preservation of the road network before thinking of upgrades. 3. Safety on our roads must receive top priority. 4. Law enforcement must be seen to be effected at all times. 5. Overload control centres should be operational 24 hours a day.
5
BUDGET BREAKDOWN 2014/15 2015/16 2016/17 2017/18 Routine Maintenance
2014/15 2015/16 2016/17 2017/18 Routine Maintenance 253,161,101 281,735,381 329,569,905 337,660,964 Periodic Maintenance 577,385,138 1,073,396,998 1,489,591,810 753,906,953 Special Maintenance 183,763,104 416,761,552 423,526,687 1,074,601,406 Strengthening 688,360,522 560,079,264 882,885,142 1,289,439,315 Improvements 1,183,590,366 1,370,210,215 1,363,626,454 1,706,388,631 New Facilities 408,706,366 26,041,935 376,640,000 1,284,027,351 Community Development 179,222,984 125,725,413 243,686,833 Sub-Total 3,294,966,597 3,907,448,329 4,991,565,411 6,689,711,452
6
Investment and forecast from 2009 to 2017
District Municipality Investment to 2017 Alfred Nzo R ,941,000,000 Amathole R ,810,000,000 Buffalo City R ,220,000,000 Chris Hani R ,831,000,000 Joe Gqabi R ,770,000,000 OR Tambo R ,660,000,000 Nelson Mandela R ,317,000,000 Sarah Baartman R ,325,500,000 Projects Across Boundaries R ,000,000 R ,281,500,000
7
SECONDARY STRATEGIC NETWORK
NDoT’s view is that SANRAL should extend its network to include approx. 14,000 km of secondary strategic network (currently provincial roads). In the Eastern Cape this includes the R56, R58, R62, R63, R67, R72 and R75. The Premier formally requested SANRAL to take over these routes in February The routes were then incorporated into the SANRAL network in May 2012. Take over by SANRAL meant funds that were spent on maintenance of these routes could be shifted to other roads in the Province.
8
EXPANSION OF NATIONAL ROAD NETWORK
9
ROUTES TRANSFERRED IN JUNE 2016
Route No FROM - TO Provincial Road No Length (km) R 390 Cradock (N10/4) - Hofmeyer (Van Heerden str) TR07601 63 Hofmeyer (Van Heerden Str) - R56 West of Steynsburg TR07602 34.28 R 391 R56 – Burgersdorp TR05101 36.99 R 392 Queenstown N6 (Grey Str) - R410 Intersection MR00659 8.56 R 396 Tsolo N2 - Maclear R56 MR00721 61.18 R 410 R392 I/S - Lady Frere MR00661 42.79 Lady Frere - Hali No 2 (R392) DR08551 15.38 Hali No 2(R392) – Cala DR08002 31.91 Cala - R58 at Quiba (MR710) TR07401 14.63 R 58 R58 at Quiba (MR710) - R56 East of Elliot 4.88 TOTAL 313.6
10
ROUTES GAZETTED IN JUNE 2016
Route Number FROM - TO PROVINCIAL ROUTE NO LENGTH (KM) R 335 N2 via MOTHERWELL and ADDO - MR473 MR450 54.37 R 342 MR450 - N10 at PATERSON MR473 24.55 R 336 MR450 via KIRKWOOD - R75 MR471 48.11 TOTAL 127.03
11
MAP OF NEW ROUTES
12
R61: Mthatha (Sprigg Street) to Ngqeleni Turnoff (6 km)
Commencement date : November 2013 Completion Date : September 2017 Value : R 350 million Scope New eastbound carriageway; upgrade westbound carriage New bridges over the Mthatha River, Corana River and Sidwadweni River Interchange at Ngqeleni Turnoff Two agricultural underpasses; one pedestrian bridge Relocate households and build new dwellings Apply Cape Seal and asphalt at intersections
13
R61: Ngqeleni Turnoff to Libode (15 km)
Commencement Date : February 2014 Completion Date : September 2016 Value : R265 million Scope Widening of sections of road New cross section (passing lanes where required) Interchange at Libode Walkways and community service roads Construct one vehicular overpass; one vehicular underpass and one pedestrian bridge Construct taxi bays
14
R61: Libode (Mount Nicholas) to Mngazi (28 km)
Commencement Date : September 2016 Completion date : February 2019 Value : R375 million Scope Construction of bridges: Umngazi River Bridge Qiti Overpass Bridge Qhaka Overpass Bridge Construction of underpasses: Gangata Agricultural underpass Kuleka Agricultural underpass
15
R61: Libode (Mount Nicholas) to Mngazi cont….
Commencement Date : September 2016 Completion : August 2019 Value : R375 million Scope Construction of underpasses: Tutor Ndamase Agricultural underpass 1 Tutor Ndamase Agricultural underpass 2 Tutor Ndamase Agricultural underpass 3 Tutor Ndamase Agricultural underpass 4 Mnxabakazi Agricultural underpass Umngazi Agricultural underpass
16
R61: Libode (Mount Nicholas) to Mngazi cont….
Commencement Date : September 2016 Completion : August 2019 Value : R375 million Scope Widening of Intersections: 8x Intersections will be widened 6x Dangerous intersections will be closed Community Development project: Local SMME will be used to construct community access roads which will be used to channel traffic towards the new formalised intersections. Relocation of services – ESKOM, Telkom, houses, etc
17
R61: Upgrade from Majola Tea – Tombo (15.5 km)
Commencement date: January 2015 Completion : March 2018 Value R535 million Scope New vertical alignment at sharp curves Widening of road with passing lanes where required Reinforced Earth Walls at high fills Upgrade or relocate intersections and accesses Construct 3x agricultural underpasses; one pedestrian bridge and taxi rank -Majola Tea Junction Relocate 7 dwellings
18
R61: Mthatha Airport to Mthatha CBD (Sprigg Street) (12km)
Commencement date: November 2018 Duration: 36 months Estimated Value : R550 million Scope Dual carriageway - vertical and horizontal alignment Construct major culverts and cattle/agricultural underpasses Construct service roads, walkways, traffic circles and calming measures Formalize accesses and intersections
19
R61: Baziya to Mthatha Airport (28km)
Commencement date: November 2014 Duration: 30 months Value : R397 million Scope New vertical alignment Widening of road with passing lanes where required Construct river bridges, major culverts and cattle/agricultural underpasses Construct service roads and walkways Formalize accesses and intersections
20
R61: All Saints to Baziya Phase 1 (17km)
Commencement date: October 2014 Duration 30 months Value R400 million Scope New vertical alignment Widening of road with passing lanes where required Construct river bridges, major culverts and cattle/agricultural underpasses Construct service roads and walkways Formalize accesses and intersections
21
R61: All Saints to Baziya Phase 2 (18km)
Commencement date: SEPTEMBER 2017 Duration : 30 months Estimated Value : R350 million Scope New vertical alignment Widening of road with passing lanes where required Construct river bridges, major culverts and cattle/agricultural underpasses Construct service roads and walkways Formalize accesses and intersections
22
R61: Upgrade between Qumanco River and All Saints Ph 1 (16km)
Commencement date : February 2013 Duration : 18 months Value : R209 million Scope Upgrading of vertical alignment and widening of road Construct 2x bridges and major culverts Improve intersections where necessary Construct service road inside township to facilitate closure of unsafe accesses
23
R61: Upgrade between Qumanco River and All Saints Ph 2 (17km)
Commencement date : SEPTEMBER 2017 Duration : 24 months Estimated Value : R250 million Scope Upgrading of vertical alignment and widening of road Construct 2 x bridge and major culverts Improve intersections where necessary Dualing of road inside Engcobo and upgrade Stanford Street Construct service roads to facilitate closure of unsafe accesses Construct underpasses where required
24
R61: Upgrade from Upper Tsojana to Qumanco River (25km)
Commencement date :SEPTEMBER 2017 Duration : 32 months Estimated Value : R450 million Scope Upgrading of vertical and horizontal alignment and widening of road Construct 1x bridge and major culverts Improve intersections where necessary Construct service/access roads to facilitate closure of unsafe accesses Construct underpasses where required
25
R61: Reseal N6/R61 to Upper Tsojana (60km)
Commencement date : October 2015 Duration: 10 months Value : R60 million Scope Repair sections in distress Crack sealing and selected texture treatment Reseal with 13mm + 6.7mm stone
26
R61: Rehabilitate road between Cradock and Tarkastad Phase 1 (16km)
Commencement date : April 2015 Duration : 15 months Value : R130 million Scope Upgrading and widening of road Lengthen culverts Improve intersections where necessary Resurface road
27
R61: Rehabilitation from Cradock and Tarkastad Ph 2 (25km)
Commencement date : APRIL 2017 Completion : September 2018 Value : R127 million Scope Upgrading and widening of road Lengthen culverts Improve intersections where necessary Resurface road Asphalt through Tarkastad town
28
R61: Rehabilitate road between Elinus and N10/R61 Intersection (18km)
Commencement date : February 2015 Duration : 24 months Value : R201 million Scope Upgrading and widening of road Lengthen culverts and bridges Improve intersections where necessary Resurface road Road marking and erection of road signs
29
R61: Rehabilitate road between Draai River and Elinus (14km)
Commencement date : January 2015 Duration : 14 months Value : R80 million Scope Upgrading and widening of road Lengthen culverts Improve intersections where necessary Resurface road
30
N2: Upgrade from Mount Frere to Ngcweleni River (30km)
Commencement date : SEPTEMBER 2017 Duration : 30 months Estimated Value : R500 million Scope Full upgrade of road Widening road Community access roads Pedestrian and agricultural underpasses
31
N2: Community Development Project - Mount Frere (10km)
Commencement date : October 2016 Completion : September 2018 Value : R40 million Scope Learnership training to local SMME’s of CIDB Grades 1- 3 Community service road and walkways The approximate length of the road to be block paved is 10 km
32
N2: Reseal from Qumbu (Mzeke River) to Mount Frere (37 km)
Commencement date : February 2015 Completion Date : March 2016 Value : R55 million Scope Repair sections in distress Crack sealing and selected texture treatment Construct pedestrian walkways Reseal with 19mm stone
33
N2: Community Development Project – Qumbu (10km)
Commencement date : October 2016 Completion : March 2018 Value : R23 million Scope Learnership training to local SMME’s of CIDB Grades 1- 3 Construction of walkways The approximate length of the walkways is 10 km
34
N2: NQADU FOREST TO QUMBU (MZEKE RIVER) (28km)
Commencement date : SEPTEMBER 2017 Duration : 24 months Estimated Value : R 350 million Scope Reconstruct pavement layers Passing lanes where required) Pedestrian walkways where necessary Formalize dangerous intersections Underpasses where required
35
N2: MTHATHA SOUTHERN BYPASS
Commencement date: October 2019 Duration: 30 months Estimated Value : R500 million Scope Dual carriageway - vertical and horizontal alignment Construct major culverts and cattle/agricultural underpasses Construct service roads and pedestrian walkways Formalize accesses and intersections
36
N2: VIEGESVILLE TO MTHATHA (20km)
Commencement date: June 2018 Duration: 36 months Estimated Value : R500 million Scope Dual carriageway - vertical and horizontal alignment Construct major culverts and cattle/agricultural underpasses Construct service roads, walkways, traffic circles and calming measures Formalize accesses and intersections
37
N2: TETYANA TO SITEBE KOMKHULU (17km)
Commencement date : November 2016 Completion Date : March 2019 Value : R 487 million Scope New vertical and horizontal alignment New cross section (passing lanes where required) Straighten out Mtentu Cuttings Straighten out cuttings on either side of Mbashe River
38
N2: IDUTWA BYPASS Commencement date : September 2018
Duration : 24 months Estimated Value : R 350 million Scope New vertical and horizontal alignment New cross section (passing lanes where required) Interchange at R408 intersection Underpasses where required Community link/service roads
39
N2: IDUTWA BYPASS cont… Submission of EIA done Studies undertaken:
Air Quality Impact Assessment Socio-economic Impact Assessment Noise Impact Assessment Heritage Impact Assessment Town Planning, Land Use & Land Rights Impact Assessment Aquatic Impact Assessment Vegetation and Biodiversity Assessments Submission of EIA done
40
N2: IBIKA TO TETYANA (26km)
Commencement date : September 2018 Duration : 24 months Estimated Value : R 250 million Scope Strengthening of base layers Formalize dangerous intersections Apply necessary seal
41
N2: BUTTERWORTH BYPASS Commencement date : September 2018
Duration : 24 months Estimated Value : R 450 million Scope New vertical and horizontal alignment New cross section (passing lanes where required) Underpasses where required Community link/service roads
42
N2: BUTTERWORTH BYPASS cont…
Studies undertaken: Air Quality Impact Assessment Socio-economic Impact Assessment Noise Impact Assessment Heritage Impact Assessment Town Planning, Land Use & Land Rights Impact Assessment Aquatic Impact Assessment Vegetation and Biodiversity Assessments Submission of EIA done
43
N2: Reseal from Toleni to Ibika (29km)
Commencement date : September 2017 Duration : 26 months Value : R344 million Scope Repair sections in distress Crack sealing and selected texture treatment Construct pedestrian walkways Reseal with 20/7 mm double seal Asphalt in Butterworth town
44
N2: Reseal from Komga Turn Off to Kei River (10km)
Commencement date : September 2016 Completion Date : June 2017 Estimated Value : R90 million Scope Repair sections in distress Crack sealing and selected texture treatment Construct turning lane at N2/R63 Intersection Resurface with 20/7/7mm split seal
45
N2: Reseal Wilsonia to N6/N2 Intersection (12km)
Commencement date : February 2016 Completion Date : December 2016 Value : R58 million Scope Remove UTFC and repair sections in distress Reseal with 19mm mm stone
46
N2: Resurfacing from King Williams Town to Bhisho & Breidbach (15km)
Commencement date :April 2016 Duration: 18 months Value : R186 million Scope Mill out sections in distress in Cathcart Street, Buffalo Road, Grey Street & Alexandra Road Traffic calming measures on R63 between traffic lights; Roundabout at Zwelitsha Turn Off on N2 Reseal with 13mm + 6.7mm stone or Asphalt
47
Commencement date :October 2017 Duration: 24 months
N2: Upgrade : Bulembu Airport to King Williamstown & Interchange at Breidbach (10km) Commencement date :October 2017 Duration: 24 months Estimated Value : R300 million Scope New vertical and horizontal alignment New cross section (passing lanes where required) Reseal with 13mm + 6.7mm stone or Asphalt Construct quarter links at Breidbach Intersection Construct Interchange at Belton Bridge
48
N2: Reseal Keiskamma Pass (5km)
Commencement date : April 2016 Completion Date : May 2017 Estimated Value : R10 million Scope Repair sections in distress Crack sealing and selected texture treatment Resurface with Cape Seal
49
N2: Widening of Fish River
Commencement date : February 2016 Completion Date : June 2017 Value : R48 million Scope Widen Fish River Bridge to 13.4 m cross section Construct balustrades
50
N2: Upgrading from Grahamstown to Fish River Pass Ph 1 (17km)
Commencement date : April 2015 Completion : June 2017 Value : R308 million Scope Improve vertical and horizontal alignment Widening of road with climbing lanes Construct bypass at Fish River – Labour Intensive Methods Environmental study of Oldenburgia Grandis by Rhodes University
51
N2: Upgrading from Grahamstown to Fish River Pass Ph 2 (14km)
Commencement date : APRIL 2017 Completion : March 2019 Value : R297 million Scope Improve vertical and horizontal alignment Widening of road to13.4m cross section with climbing lanes Construct three agricultural underpasses Repair work on R67 through Grahamstown Apply Cape Seal with 20mm stone
52
N2: Reseal from Komga River to Grahamstown (41km)
Commencement date : April 2016 Completion Date : May 2017 Value : R80 million Scope Repair sections in distress; Repair sagging sections; Crack sealing and selected texture treatment; Reseal with 19mm Cape Seal
53
N2: Construction of Cholchester Interchange
Commencement date : October 2017 Duration: 18 months Estimated Value : R100 million Scope Construct Interchange bridge Construct approaches to bridge Construct pedestrian walkways
54
N2: Special Maintenance between Bramlin I/C and Coega Bridge (25km)
Commencement date : June 2015 Completion Date : December 2016 Value : R200 million Scope Repair sections in distress Crack sealing and selected texture treatment Reseal with 19mm stone
55
N2: Asphalt Overlay from Krom River to Jeffreys Bay (32 km)
Commencement date : November 2016 Completion Date : November 2017 Value : R116 million Scope Repair sections in distress Crack sealing and selected texture treatment Resurface with Asphalt
56
N2: Resurfacing from Gamtoos to van Staadens (33km)
Commencement date : October 2019 Duration: 10 months Estimated Value : R80 million Scope Repair sections in distress Crack sealing and selected texture treatment Resurface
57
N2: Resurfacing from Kareedouw to Humansdorp (40km)
Commencement date : November 2018 Duration: 12 months Estimated Value : R100 million Scope Repair sections in distress Crack sealing and selected texture treatment Resurface
58
N6: Reseal from Stutterheim to Cathcarth (40km)
Commencement date : May 2017 Duration: 12 months Estimated Value : R90 million Scope Repair sections in distress Crack sealing and selected texture treatment Reseal with double seal 20mm + 7mm stone
59
N9 : Reseal from Aberdeen to Graaff Reinet (54km)
Commencement date : October 2016 Completion Date : August 2017 Value : R80 million Scope Repair sections in distress Crack sealing and selected texture treatment Reseal with double seal 20mm + 7mm stone
60
N9: Upgrade from Middelburg to Carlton Heights (25km)
Commencement date : April 2015 Duration : 40 months Value : R412 million Scope Upgrading and widening of road with climbing lanes Upgrade two intersections and farm accesses Construct major culverts and cattle underpasses Construct river bridges Rehabilitate Meintjies Street after the construction of major bridge near town.
61
N10: Upgrading of road from Riet River - Tarka Bridge (23km)
Commencement date : January 2015 Duration : 32 months Value : R401 million Scope Improve vertical and horizontal alignment Widening of road with climbing lanes Drainage structures and installation of prefabricated culverts, in-situ culverts and in-situ irrigation canal
62
R62:Special Maintenance between Kareedouw - N2/R62 I/S(33km)
Commencement date : April 2017 Completion : June 2018 Value : R90 million Scope Improve shoulders of road Mill out and replace bad sections Improve drainage where required Improve safety aspects Reseal with 14/7 double seal and Asphalt in town Erect new signs, road marking and studs
63
R62: Special Maintenance from Boundary WC - Kareedouw (40km)
Commencement date : October 2018 Duration: 10 months Estimated Value : R110 million Scope Repair sections in distress Texture treatment and Crack sealing Guardrails and shoulder improvements Resurface with double seal 20/7 mm
64
R63: Reseal from Graaff Reinet to Pearston (70km)
Commencement date :February 2016 Construction Duration: 15 months Value : R143 million Scope Repair sections; Apply geotextile where required; Pavement resurfacing; Improve bellmouths of intersections Ancillary Works – fencing, guardrails, etc
65
R63: Reseal from Pearston to Bruintjies Hoogte (35)
Commencement date :January 2016 Construction Duration: 11 months Value : R59 million Scope Repair sections; Apply geotextile where required; Pavement resurfacing; Improve bellmouths of intersections Ancillary Works – fencing, guardrails, etc
66
R63: Upgrade from N10 to Bedford (15km)
Commencement date :February 2018 Construction Duration: 15 months Estimated Value : R150 million Scope New vertical and horizontal alignment; New pavement layers; Improve drainage; Improve intersections and accesses; Ancillary Works – fencing, guardrails, signs, etc
67
R63: Reseal from Adelaide to Fort Beaufort (35km)
Commencement date :October 2015 Construction Duration: 14 months Value : R90 million Scope Repair sections; Pavement resurfacing; Improve bellmouths of intersections Ancillary Works – fencing, guardrails, etc
68
R63: Upgrade – Fort Beaufort to Alice (20km)
Commencement date :October 2017 Construction Duration: 30 months Estimated Value : R450 million Scope New vertical and horizontal alignment; Improve intersections and accesses; Increase capacity of bridges and major culverts; Ancillary Works – fencing, guardrails, signs, etc Community Development Projects
69
R63: Reseal from Alice to King Williamstown (60km)
Commencement date :October 2014 Construction Duration: 16 months Value : R98 million Scope Repair sections; Pavement resurfacing; Improve bellmouths of intersections Ancillary Works – fencing, guardrails, etc
70
R63: Upgrade from Bhisho to the R63/N6 intersection (33km)
Commencement date :Oct 2018 Construction Duration: 24 months Estimated Value : R400 million Scope Horizontal and vertical geometric improvements and T-junction improvements; Pavement strengthening and resurfacing; Bridge and culvert structural works; and Ancillary Works – fencing, guardrails, etc
71
R63: Upgrade: R63/N6 Intersection to R63/N2 Intersection (Komga) (33km)
Commencement date :Oct 2018 Construction Duration: 24 months Estimated Value : R380 million Scope Horizontal and vertical geometric improvements and T-junction improvements; Pavement strengthening and resurfacing; Bridge and culvert structural works; and Ancillary Works – fencing, guardrails, etc
72
R72: Reseal from Nanaga to Fonteinskloof (20km)
Commencement date : November 2016 Completion : April 2017 Value : R27 million Scope Repair base failures; Resurface with double seal 20/7mm; Install guardrails, road signs, road markings and road studs
73
R72: Reseal from Fonteinskloof to Alexandria (30km)
Commencement date : November 2015 Duration : 5 months Value : R47 million Scope Repair base failures; Resurface with double seal 13/6; Install guardrails, road signs, road markings and road studs
74
R72: Upgrade Between Port Alfred and Fish River (30km)
Commencement date : February 2015 Duration : 36 months Value : R502 million Scope Improve vertical and horizontal alignment Widening of road with 3m shoulders Widening of Riet River Improve drainage where required In Port Alfred climbing lanes will be added on the steep uphills both sides of the town
75
R72: Upgrade Between Fish River and Birah River (20km)
Commencement date : November 2018 Duration : 36 months Estimated Value : R450 million Scope Improve vertical and horizontal alignment Widening of road with 3m shoulders Widening of Bira River Improve drainage where required Improve intersections
76
R72: Upgrade Birah River and Open Shaw (35km)
Commencement date : November 2016 Completion : March 2020 Value : R630 million Scope Improve vertical and horizontal alignment Widening of road with 3m shoulders Widening of Birah River and reconstruct 4xculverts Improve drainage where required and agricultural passes Improve intersections Pedestrian walkways near Birah, Wesley and Loverstwist
77
R75: Rehabilitation of Route 75 - Port Elizabeth - Despatch (15 km)
Commencement date : February 2017 Completion : January 2019 Value : R360 million Scope Rehabilitate the existing pavement Improve safety of intersections Improve drainage where required Pedestrian walkways, crossings and barriers Resurface with Asphalt Erect new signs
78
R75: Resurfacing of Route 75 - Despatch to Uitenhage (17 km)
Commencement date : November 2016 Completion : December 2017 Value : R100 million Scope Rehabilitate the existing pavement Improve safety of intersections Improve drainage where required Pedestrian walkways and crossings Resurface with Asphalt Erect new signs
79
R75: Special Maintenance from Kirkwood I/S to Wolwefontein (30km)
Commencement date : October 2018 Duration : 24 months Estimated Value : R200 million Scope Repair and mill out bad sections; Improve intersections, shoulders and edges; Improve safety aspects near intersections; Resurface , road markings and erect new signs. Fencing
80
R75: Special Maintenance from Wolwefontein to Jansenville (40km)
Commencement date : October 2017 Duration : 18 months Estimated Value : R180 million Scope Repair and mill out bad sections; Improve intersections, shoulders and edges; Improve safety aspects near intersections; Resurface , road markings and erect new signs. Fencing
81
R75: Special Maintenance from Jansenville to R75/R63 I/S (50km)
Commencement date : October 2017 Duration : 18 months Estimated Value : R200 million Scope Repair and mill out bad sections; Improve intersections, shoulders and edges; Improve safety aspects near intersections; Resurface , road markings and erect new signs. Fencing
82
R56: Rehabilitation of section from Steynsberg to Molteno (58km)
Commencement date : September 2017 Duration : 20 months Estimated Value : R160 million Scope Rehabilitation of road Place new base course Improve drainage Erect new guardrails and road signs Improve intersections where necessary
83
R56: Rehabilitation of section from N6 to Dordrecht (35km)
Commencement date : September 2017 Duration : 20 months Estimated Value : R150 million Scope Rehabilitation of road Place new base course Improve drainage Erect new guardrails and road signs Improve intersections where necessary
84
R56: Rehabilitation of section from Dordrecht to Indwe (39km)
Commencement date : April 2018 Duration : 24 months Estimated Value : R200 million Scope Rehabilitation of road Place new base course Improve drainage Erect new guardrails and road signs Improve intersections where necessary
85
R56: Rehabilitation of section from Indwe – MaClear (124km)
Commencement date : January 2016 Duration : 42 months Value : R635 million Scope Rehabilitation of road Place new base course Improve drainage Erect new guardrails and road signs Improve intersections where necessary Engage SMMEs from Grade 1 to Grade 6 or Grade 7
86
R56:Reseal between MaClear to Mount Fletcher (60km)
Commencement date : October 2015 Duration : 14 months Value : R95 million Scope Base patch repairs and crack sealing Apply slurry texture treatment to Cape Seal Construct concrete edge beams at gravel intersection Mill of 40mm of disintegrating asphalt layer in urban area of Matatiele and resurface with 40mm asphalt wearing course Resurface with a 19mm + 9.5mm rubber bitumen binder
87
R56:Upgrade between Matatiele and Cedarville (30km)
Commencement date : October 2017 Duration : 28 months Estimated Value : R300 million Scope Upgrading and widening of road with climbing lanes Upgrade two intersections and farm accesses Construct major culverts and cattle underpasses Construct river bridges
88
R58:Special Maintenance from Norvalspont to Venterstad (43km)
Commencement date : June 2015 Duration : 12 months Value : R70 million Scope Mill out and replace bad sections Add gravel layer and shape gravel shoulders Improve drainage where required Apply different surfacing types
89
R58:Special Maintenance from Venterstad to Burgersdorp (62km)
Commencement date : February 2016 Duration : 11 months Value : R45million Scope Mill out and replace bad sections Add gravel layer and shape gravel shoulders Improve drainage where required Apply different surfacing types Double seal 13/6 Asphalt in Burgersdorp town
90
R58: Community walkways Commencement date : October 2016
Duration : 12 months Value : R13 million Scope Construct walkways Improve safety aspect near Dukathole township
91
R58:Special Maintenance from Aliwal North to Lady Grey (49km)
Commencement date : October 2017 Duration : 18 months Estimated Value : R150 million Scope Mill out and replace bad sections Add gravel layer and shape gravel shoulders Improve drainage where required Apply 20/7mm double seal
92
R58:Special Maintenance from Lady Grey to Barkley East (45km)
Commencement date : September 2017 Duration : 18 months Estimated Value : R130 million Scope Mill out and replace bad sections Add gravel layer and shape gravel shoulders Improve drainage where required Apply 20/7mm double seal
93
R58:Slope Stabilization - Lady Grey and Barkley East
Commencement date : August 2017 Duration : 12 months Estimated Value : R60 million Scope Remove unstable material from cuts Drill into cut face Anchor tendons into cut face Apply gunite to rock face
94
R58: Resurfacing of section from Barkley East to Elliot (31km)
Commencement date : October 2015 Duration : 16 months Value : R115 million Scope Rehabilitation of road Place new base course Improve drainage Erect new guardrails and road signs Improve intersections where necessary
95
R67:Special Maintenance between Grahamstown-Fort Beaufort (70km)
Commencement date : November 2016 Completion Date : August 2018 Value : R230 million Scope Improve shoulders of road Mill out and replace bad sections Improve drainage where required Improve safety aspects near Fort Beaufort Reseal surface Erect new signs
96
R67:Special Maintenance between Fort Beaufort and Seymour (34km)
Commencement date : June 2017 Duration : 15 months Estimated Value : R80 million Scope Improve shoulders of road Mill out and replace bad sections Improve drainage where required Improve safety aspects near Fort Beaufort Reseal surface Erect new signs
97
R67:Special Maintenance between Seymour and Whittlesea (57km)
Commencement date : October 2015 Duration : 14 months Value : R180 million Scope Mill out and replace bad sections Improve drainage where required Reseal surface Erect new signs
98
R67: Whittlesea Community Service roads Project
Commencement date : November 2016 Duration : 24 months Value : R48 million Scope Learnership training programme Construct community service roads Improve safety aspects of project Use block paving Erect new signs
99
R67:Special Maintenance Whittlesea - Black Kei Riv (25km)
Commencement date : November 2016 Completion : October 2018 Value : R357 million Scope Widening of road Mill out and replace bad sections Improve drainage where required Improve safety aspects near Whittlesea Reseal surface with Cape Seal Erect new signs
100
R67:Upgrade between Swart Kei River and Queenstown (16km)
Commencement date : September 2017 Duration : 30 months Estimated Value : R350 million Scope Widening of road towards Queenstown; New vertical alignment; New pavement layers; Improve safety aspects near Queenstown; Reseal surface and erect new signs.
101
R390: Special Maintenance from Hofmeyer to R56 (34km)
Commencement date : February 2017 Completion : January 2018 Value : R81 million Scope Repair base failures; Resurface with double seal 13/7 mm; Asphalt on section 1 and in Hofmeyer town Upgrade rest areas Install guardrails, road signs, road markings and road studs
102
R391: Special Maintenance - R56 to Burgersdorp(36km)
Commencement date : August 2017 Duration : 6 months Estimated Value : R80 million Scope Repair base failures; Resurface with double seal 20/7 mm; Install guardrails, road signs, road markings and road studs
103
R392: Special Maintenance – Queenstown to R410 (10km)
Commencement date : February 2017 Completion : January 2018 Value : R72 million Scope Repair base failures and mill out bad sections; Resurface Griffith, Peacock and Livingstone streets Resurface with double seal 20/7 mm; Pedestrian walkways and taxi bay Fogspray from Stutterheim to cathcart Install guardrails, road signs, road markings and road studs
104
R335:Upgrade From Motherwell to Addo (35km)
Commencement date : October 2017 Duration : 34 months Estimated Value : R500 million Scope Widening of road; New vertical and horizontal alignment; New pavement layers; Upgrade Sundays River Improve safety aspects near intersections; Reseal surface and erect new signs.
105
R336:Upgrade From Kirkwood to Addo (33km)
Commencement date : October 2017 Duration : 24 months Estimated Value : R300 million Scope Widening of road; Upgrade two bridges; New pavement layers; Improve safety aspects near intersections; Reseal surface and erect new signs. Fencing
106
R336: Reseal from R75 to Kirkwood (15km)
Commencement date : October 2016 Duration : 6 months Value : R30 million Scope Repair and mill out bad sections; Improve safety aspects near intersections; Resurface , road markings and erect new signs. Fencing
107
R342: Special Maintenance from Addo to Paterson (25km)
Commencement date : October 2017 Duration : 24 months Estimated Value : R200 million Scope Repair and mill out bad sections; Improve intersections; Improve safety aspects near intersections; Resurface , road markings and erect new signs. Fencing
108
R396: Construction of Pedestrian Facilities along R396 (10km)
Commencement date : May 2017 Duration : 12 months Estimated Value : R25 million Scope Learnership training programme Construct pedestrian facilities Improve safety aspects of project Erect new signs
109
R410: Reseal from Khiba to Lady Frere via Cala (67km)
Commencement date : October 2016 Completion : May 2017 Value : R68 million Scope Repair base failures; Resurface with double seal 20/7 mm; Install guardrails, road signs, road markings and road studs Fencing
110
Southern Region Rejuvenation Programme (600 km)
Commencement date : April 2017 Completion : September 2018 Value : R108 million Scope Identify routes that that are due for rejuvenation; Categorise type of rejuvenation required; Apply bitumen emulsion (fog spray); Apply polymer bitumen with mineral filler; Apply 20 mm Cape Seal, road marking and studs Engage SMMEs for slurry application
111
N2 WILD COAST TOLL ROAD MSIKABA BRIDGE
Tender Closing Date : January 2017 Commencement date : May 2017 Duration : 36 months Estimated Value : R1.5 billion Scope Construct abutments Stayed deck Dual carriage way Road markings, studs, signs and guardrails Fencing
112
N2 WILD COAST TOLL ROAD MTENTU RIDGE
Tender Closing Date : January 2017 Commencement date : May 2017 Duration : 36 months Estimated Value : R1.5 billion Scope Construct abutments and piers Launch deck Dual carriage way Road markings, studs, signs and guardrails Fencing
113
N2 WILD COAST TOLL ROAD MSIKABA SOUTH HAUL ROADS
Commencement date : October 2016 Completion date : June 2017 Value : R31 million Scope Construct gravel haul road to north abutment (4.2 km) Concrete roads where gradient greater 10% (1.5 km) Haul road to link communities as far as is possible Relocate graves and dwellings
114
N2 WILD COAST TOLL ROAD MSIKABA NORTH HAUL ROADS
Commencement date : October 2016 Completion date : June 2017 Value : R32 million Scope Construct gravel haul road to north abutment (4.2 km) Concrete roads where gradient greater 10% (960m) Haul road to link communities as far as is possible Relocate graves and dwellings
115
N2 WILD COAST TOLL ROAD MTENTU SOUTH HAUL ROADS
Commencement date : October 2016 Completion date : June 2017 Value : R35 million Scope Construct gravel haul road to north abutment (6.8 km) Concrete roads where gradient greater 10% (530m) Haul road to link communities as far as is possible Relocate graves and dwellings
116
N2 WILD COAST TOLL ROAD MTENTU NORTH HAUL ROADS
Commencement date : October 2016 Completion : June 2017 Value : R28 million Scope Construct gravel haul road to north abutment (2.7 km) Concrete roads where gradient greater 10% (720m) Haul road to link communities as far as is possible Relocate graves and dwellings
117
N2 WILD COAST TOLL ROAD COMMUNITY ACCESS ROAD NEAR LUSIKISIKI
Commencement date : July 2016 Completion date : June 2018 Value : R28 million Scope Construct access road Learnership Programme SAQA Accredited training NQF 2 NQF 4
118
N2 WILD COAST TOLL ROAD COMMUNITY ACCESS ROAD NEAR NDWALANE
Commencement date : July 2016 Completion date : June 2018 Value : R28 million Scope Construct access road Learnership Programme SAQA Accredited training NQF 2 NQF 4
119
N2 WILD COAST TOLL ROAD COMMUNITY ACCESS ROAD NEAR MZAMBA
Commencement date : July 2016 Completion date : June 2018 Value : R28 million Scope Construct access road Learnership Programme SAQA Accredited training NQF 2 NQF 4
120
N2 WILD COAST TOLL ROAD COMMUNITY ACCESS ROAD NEAR MDATYA
Commencement date : May 2017 Completion date : April 2019 Estimated Value : R45 million Scope Construct access road Learnership Programme SAQA Accredited training NQF 2 NQF 4
121
N2 WILD COAST TOLL ROAD COMMUNITY ACCESS ROAD NEAR SIGIDI
Commencement date : May 2017 Completion date : April 2019 Estimated Value : R45 million Scope Construct access road Learnership Programme SAQA Accredited training NQF 2 NQF 4
122
TRAINING OF ENGINEERS Commencement date : October 2014
Duration : Ongoing Scope Gain Design Experience. Construction/Implementation Experience Contractual Issues Professional Registration
123
ASSISTANCE TO PROVINCE
SANRAL is always willing to render assistance to the Province in as far as implementation of projects are concerned as well as training of young engineers, technologists and technicians. SANRAL is implementing the following projects/programmes on behalf of the Province: Sabalele Upgrade Rejuvenation of Selected Roads Mthatha Ring Road Mbashe Selected Rural Roads Rural Roads – Various Municipalities
124
ASSISTANCE TO PROVINCE: SABALELE UPGRADE
Commencement date : April 2015 Duration : 18 months Value : R170 million Scope Improve vertical and horizontal alignment Construct a 6.8 m single carriageway Provide calming measures at identified spots turning lanes at intersection with R61 at St Marks Apply 19 mm Cape Seal
125
ASSISTANCE TO PROVINCE: REJUVENATION PROGRAMME
Commencement date : April 2015 Duration : 24 months Value : R100 million Scope Identify routes that that are due for rejuvenation; Categorise type of rejuvenation required; Apply bitumen emulsion (fog spray); Apply polymer bitumen with mineral filler; Apply 19 mm Cape Seal Engage SMMEs for slurry application
126
ASSISTANCE TO PROVINCE: MTHATHA RING ROAD
Commencement date : August 2015 Duration : 18 months Value : R175 million Scope Construct 6.8m single carriageway on the northern side of R61 Construct new bridge across Mthatha River Make use of DRPW borrowpits Apply 19 mm Cape Seal and Asphalt Engage SMMEs
127
ASSISTANCE TO PROVINCE: MBASHE RURAL ROADS
Commencement date : December 2015 Duration : 15 months Value : R70 million Scope Projects were identified by municipality; Wards were clustered around projects; Construction commenced in December making use of DRPW contractor to the tune R20 million SMMEs will be engaged on the remaining R40 million
128
ASSISTANCE TO PROVINCE: RURAL ROADS PROGRAMME cont...
Commencement date : March 2016 Duration : 15 months Value : R456 million Scope Project budgets given to SANRAL will be converted into project estimates and project costs on 24 February 2016. The project estimates will be presented to the Project Steering Committee on 26 February 2016. Construction works to commence from 1 March 2016 SMMEs will carry out at least 30% of the works
129
RURAL ROADS
130
Bypasses Some of the towns in the Eastern Cape experience traffic congestion, particularly the smaller towns. The reason, more often than not, is a result of poor or nonexistent traffic management and control. This is compounded by a lack of adequate public transport facilities like taxi ranks and bus/taxi bays. Failure to provide these facilities has resulted in motorists – both private and public – parking and stopping anywhere and everywhere thus blocking thoroughfares. The specific issues related to each town are given below:
131
Mount Frere Bypasses Possible routes have been identified
There are six options to be considered Public Participation is planned to commence in 2017 Trade offs may be considered if the Public Participation process drags on for too long.
132
King William’s Town Bypasses
Consulting Firm will be appointed in July 2013 for a Route Location. This will be linked to the upgrade of the road between Bulembu Airport and Breidbach and it includes the Breidbach Interchange as well as the Reseal of R63 between King William’s Town and Bhisho Department of Roads and Public Works needs to take a decision as to whether the link road between Breidbach and Bhisho / Zwelitsha should form part of this project.
133
Butterworth and Idutywa Bypasses
Butterworth and Idutywa Bypasses– Public Participation: Provincial EXCO & Infrastructure Cluster already informed Process continues with the Municipalities and communities – newspaper adverts Public Participation meetings held in both towns on 23 and 24 October 2012 Scoping Report is now being considered by SANRAL
134
Qumbu Bypasses There is no need for a bypass for this town.
The road (N2) through the centre of town is wide enough to allow unrestricted flow of traffic. However, the failure of the municipality to provide public transport facilities ( like taxi ranks) has resulted in all modes of transport stopping and parking in the thoroughfare – thus restricting the flow of traffic. If the municipality provides the necessary taxi/bus ranks, then SANRAL will consider providing a dual carriageway (two lane in as well as two lanes out of town) for Qumbu.
135
Engcobo Bypasses The constraints at Engcobo are possibly more due to poor traffic management within the town. Provision of the necessary facilities coupled to sound traffic management and control will alleviate the congestion. However, additional capacity in the form of additional lanes will be provided through town SANRAL will also be upgrading a street within the town to link up with the R58 ( road towards Cala/Elliot). There is no consideration of a bypass for this town at the moment.
136
Thank You Website: www. sanral. co. za Fraud Hotline:
Thank You Website: Fraud Hotline: Toll-Free Phone No: Toll-Free Fax No:
Similar presentations
© 2025 SlidePlayer.com Inc.
All rights reserved.