Chairman of Road Infrastructure Agency Management board

Similar presentations


Presentation on theme: "Chairman of Road Infrastructure Agency Management board"— Presentation transcript:

1 Chairman of Road Infrastructure Agency Management board
   Projects under Operational programme “Transport and transport infrastructure” Eng. Lazar Lazarov Chairman of Road Infrastructure Agency Management board November 2016 Sofia

2 “Kalotina – Sofia” MW Lot 1 Western Arc of Sofia Ring Road, Phase 2
Activity Contractor Contract Value VAT included Construction “European roads“ ASD 101 999 866,65 BGN OVERPASS BLVD. “LOMSKO SHOSE"

3 Motorway “Struma” Lot 3.1 from Blagoevgrad to Krupnik
   Motorway “Struma” Lot 3.1 from Blagoevgrad to Krupnik from km to km and from km to km Activity Contractor Contract Value VAT excluded Design and Construction „АМ Струма 3.1“ ASD ,92 BGN Supervision „SN АМ „Струма Лот 3.1“ ASD ,00 BGN

4 Motorway “Struma” Lot 3.1 - “Jeleznitsa” tunnel
   Motorway “Struma” Lot “Jeleznitsa” tunnel Procedures are carried out under the PPA with the subject: - Design and construction of the motorway "Struma“ Lot 3.1 Jeleznitsa tunnel - Supervision of the design and construction of the motorway "Struma" Lot 3.1 Jeleznitsa tunnel

5 Motorway “Struma” Lot 3.3 from Kresna to Sandanski
from km to km = km Overall length: 23.6 km Activity Contractor Contract Value VAT excluded Design and Construction Consortium “Struma” - Lot 3.3 ,00 BGN Supervision "Patinvest-engineering" JSC ,28 BGN

6 Motorway “Struma” Lot 3.3

7 An archaeological site 16 km 419 + 670 to km 420 + 384
village Damyanitsa, municipality of Sandanski, Blagoevgrad

8 Finds of the preliminary exploring
archaeological site 16 km to km VI – V century BC III-IV century

9    Application Form for Struma Motorway Project – Lot 3.1, Lot 3.3 and Zheleznitsa Tunnel Received comments and remarks from Jaspers - May 2016 Agreed with Jaspers updated traffic model and CBA Submission for Jaspers’ review of the updated Application form and supporting documents – 19 December 2016

10 Struma Motorway Lot 3.2 from Krupnik to Kresna
   Struma Motorway Lot 3.2 from Krupnik to Kresna Lot 3.2 falls in the environmentally sensitive and technically difficult construction area The intensive traffic on the road through the Kresna Gorge increases the risk of traffic accidents involving casualties. For Struma Motorway Lot 3.2 passage through the Kresna Gorge various technical alternatives were developed. Four alternatives (objects of the new EIA) had been currently prepared: 15.4 km long tunnel ( ) Dual Carriageway (2014) Dual Carriageway (2015) Eastern Bypass (2016)

11 Long Tunnel Alternative (2008-2014)
   Long Tunnel Alternative ( )

12 Dual Carriageway Alternatives (2014-2015)
   Dual Carriageway Alternatives ( )

13 Eastern Bypass Alternative (2016)
   Eastern Bypass Alternative (2016) 2 lanes and with a total width of 10.5 m The new carriageway bypasses the Kresna Gorge from the east and the other carriageway uses the existing road E-79 (I-1). The existing road will be rehabilitate and mitigating measures to limit the risk of mortality of wild animals and fragmentation of their habitats will be implement

14    EIA Procedure Developed updated Terms of Reference for the scope and content of the environmental impact assessment (EIA) of the investment proposal - "Improved layout of Lot 3.2 of Struma Motorway“ will be issued. Consultations with the specialized administrations, stakeholders and public were performed The statements had been received and processed. The reference for consultations is under preparation as the ToR for EIA have been precised and supplemented The submission of the ToR for the EIA for consultation with the competent authorities (MoEW and Ministry of Health) will occur in December 2016 Expected preparation of the first draft of the EIA /AA Report - March 2017 Submission of the EIA/AA Report in the MoEW for assessment of their quality Public consultation on the EIA/AA Report after positive assessment of their quality by the MoEW.

15 Contract Value VAT included
Preparation of project: Road I-1 (E-79) Vidin-Montana-Vratsa, approximate length: 126 km Activity Contractor Contract Value VAT included DESIGN І-st section – Vidin- Dimovo, from km to km ІІ-nd section – Dimovo-Bela-Ruzhintsi, from km to km „VIA PLAN–BURDA” ASD ,28 BGN ІІІ-rd section – Ruzhintsi-Montana, from km to km ІV-th section – Montana-Vratsa, from km to km "Inzhkonsultproekt" Ltd. ,16 BGN

16 Preparation of project: Road I-1 (E-79) Vidin-Montana-Vratsa, approximate length: 126 km
Activity Contractor Contract Value VAT included Environmental Impact Assessment "Dango Project Consult" Ltd. 60 372,00 BGN Auditing road safety on phase preliminary project and technical project І-st section – Vidin- Dimovo, from km to km ІІ-nd section – Dimovo-Bela-Ruzhintsi, from km to km „Safe roads ” ASD 10 000,00 BGN ІІІ-rd section – Ruzhintsi-Montana, from km to km ІV-th section – Montana-Vratsa, from km to km „Road safety ” ASD 14 400,00 BGN Start of design activity – July 2013 Deadline for preparation of technical projects – July 2018

17 THANK YOU FOR YOUR ATTENTION!