Residential demand charges

Similar presentations


Presentation on theme: "Residential demand charges"— Presentation transcript:

1 Residential demand charges
Commissioner Mike Karia Delaware Public Service Commission June 27, 2017

2 Rate Design Mismatch The utility incurs fixed costs and variable costs to serve customers. Today, the majority of costs are recovered through variable charges. Costs should align with the reason the utility incurs costs Cost Causation Principle- “…costs are to be allocated to those who cause the costs to be incurred and reap the resulting benefits.” NARUC v. FERC, 475 F. 3d 1285.

3 Arizona Dockets Salt River Project (“SRP”), in AZ, implemented a Non Coincident Peak (NCP) demand charge in 2014 for solar customers. The rate was approved by their independent board, not the Arizona Corporation Commission. UniSource Energy Services proposed a demand charge, mandatory for solar customers, that was rejected by an Administrative Law Judge on July 22, 2016 pending the outcome of a proceeding that is meant to determine a value that solar production brings to the grid. Arizona Public Service proposed a mandatory residential demand charge but in a settlement agreed to optional time of use and demand rates for residential customers.

4 The Problem Most utility investments are made to serve ratepayers reliably at the system peak. What is the proper method to calculate and bill for each ratepayer’s contribution to “peak,” taking into account the fact that different components of the distribution system may peak on different days throughout the year? How can rates send proper and timely price signals? How can we allow Net Energy Metering customers to avoid costs that they allow the utility to avoid?

5 The Solutions Time of Use Rates Demand Rates Status Quo

6 Time of Use Rates Time-Of-Use Rates
Charges different rates for usage during different times of the day. Can be used for entire bill or just generation. Costs recovered based on energy use (volumetric). Meant to correlate use with system peaks

7 Demand Charges The Solutions Different types
Non-Coincident Demand Charge: Highest peak hour of the month regardless of system peak Typical “Demand Charge” Coincident Peak Demand Charge Charge during certain pre-determined system peak hours. Custom Design With Advanced Metering Infrastructure, more granular rates can be designed to accurately capture contribution to system peak Portion of costs recovered with demand charge recovered based on demand value (neither fixed nor volumetric). Meant to correlate use with system peaks.

8 The Solutions Status-Quo
Charge one rate regardless of time of day or year Costs recovered based on energy use (volumetric) The compromise: Voluntary Time of Use and Voluntary Demand Rates

9 Pro/Con: Time-of-Use Rates
Pros: Depending on design, may align more expensive periods of wholesale energy with higher retail charges. May reduce use at peak. Particularly applicable for vertically-integrated utilities where T, D, & G peaks are all similar. Cons: Not reflective of costs incurred to serve load. Not in accordance with cost-causation principle. No incentive for end-users to shift their use away from system peaks.

10 Pro/Con: Demand Charges
Pros: With AMI Deployed, Demand Charges can be tailored to send granular price signals. If non-coincident demand charge used, allows utilities to recover significant portion of fixed costs in a (proxy) fixed-costed fashion. Cons: Non-coincident peak demand charges Difficult to understand Difficult for customers to control Likely not granting any credit for any aid to distribution grid that Distributed Energy Resources do provide. Need AMI metering to implement more granular demand charge options that would be in accordance with the cost-causation principle.

11 Pro/Con: Status-Quo Pros: Cons:
Simple for Customers/Easy to understand. Customers like flat rate service Won’t feel as if they’re getting “punished” for using during certain times of the day. Cons: Not reflective of costs incurred to serve load. Not in accordance with cost-causation principle. No incentive for end- users to shift their use away from system peaks.

12 Delaware’s Attempts In Delaware, there have been multiple attempts to develop new rate designs None of the proposals survived the discovery and working group phase So none of the proposals were presented to the Commissioners

13 Delaware’s Attempts 2007 Regulation Docket 59: Investigation into the revenue decoupling mechanisms for electric and gas utilities. Media coverage focused on “Use Less Pay More” The Legislature changed its mind and withdrew the regulation 2009 Docket T and : The Application of Delmarva Power for approval of a Modified Fixed Variable Rate Working groups never reached a consensus and the new rate design was never brought before the commission for a vote

14 Delaware’s Attempts 2009 Docket 09-414 Decoupling
Decoupling was not included in the issues brought before the Commission 2013 Docket : The Application of Delmarva Power for approval of forward looking rate plan (FLRP) Working groups never reached a consensus and the rate design was never brought before the commission for a vote