1 (A State Government Company)
INTEGRATED COASTAL ZONE MANAGEMENT PROJECT AT SAGAR ISLAND MONTHLY PROGRESS REPORT AS OF 31st OCTOBER, 2016 HYDEA SpA Del Rosso Fiorentino 2G, 50142 Florence , Italy GHOSH, BOSE & ASSOCIATES ( P) Ltd, 8, HARRINGTON MANSION 8, HO CHI MINH SARANI KOLKATA – SUNDARBAN INFRASTRUCTURE DEVELOPMENT CORPORATION LTD. (A State Government Company)

2 M/S. VIRAJ PROJECTS (I) PVT LTD
ACF With PMC : Hydea SpA - Ghosh Bose & Associates (P) Ltd JV Component Name of Contractors Construction of Public Rain Shelter cum Nat Mandir & Public Rain Shelter cum Dala Arcade M/S. VIRAJ PROJECTS (I) PVT LTD Construction of ECO Camp , Beach Shelters and Drainage Construction of Leach Pit Based Toilets and Solid Waste Management Facility M/S N.K. BASU & COMPANY Construction of Bus Terminus

3 Construction of ECO - , Beach Shelter and Drainage 16.07.2014
Package consisting of Civil, Sanitary & Plumbing, Electrical, and Other Allied Works A. Tendering Stage Sl No. Name of Work Date of IFB Pre bid Meeting Submission of Tender Issuance of LOA 1 Construction of Public Rain Shelter cum Nat Mandir & Public Rain Shelter cum Dala Arcade 2 Construction of ECO - , Beach Shelter and Drainage 3 Construction of Leach Pit Based Toilet and Solid Waste Management Facility 4 Construction of Bus Terminus

4 BRIEF DESCRIPTION AND LOCATION OF THE PROJECT
Sl. No. Name of Work Brief Description and Location of Site Name of the Contractor Value of Work Awarded Some Important Dates 1 Public Rain Shelter Cum Dala Arcade and Public Rain Shelter Cum Nat Mandir Nat Mandir – An Open Pavilion with domed roof having an area of 450 Sq m Location –As on faces the temple, on the right side of the paved approach, right in front of the temple. Dala Arcade – A shopping arcade having 124 Nos. 10’ X 10’ shops to accumulate the dala vendors. Location – On the left side of the paved approach as face towards the temple M/s Viraj Project (P) Ltd Rs Core Letter of Acceptance Issued :- Contract Signed :- Proceed to Work Letter Issued on :- 2 Eco- , Beach Shelters and Drainage Eco-Camp – Consisting of Reception Centre, 20 Nos. small Eco-Huts, 10 Nos. Large tented Huts, Eating House & Toilet Blocks. Location – The Complex is located behind the temple complex between road no. 4 & 5. Beach Shelter – On the Beach overlook from the . Rs 9.11 Core 3 Leach Pit Based Toilet and Permanent & Temporary Composite Solid Waste Management Facilities 20 Nos. leach Pit Based Toilet Blocks comprising of 10 Nos. toilet in each block to be set up at 2 location , one near the exiting toilet right side of Road no. And another at the beach. 4 Nos. solid waste handling facilities shall be located at different locations covering the entire pilgrim area M/s N.K. Basu & Company Rs 2.12 Crore 4 Bus Terminal .Bus Stand shall have Waiting Area , , Toilet Block and Tourist Information Centre & Transport Office Location – In the Road island at the confluence of Road No. 3,4&5 at the start of the Mela Ground Rs 1.85 Crore

5 BRIEF SUMMARY OF THE PROJECT
SL No. Contractor Name of Work Contract Price Date of LOA Date of Work Order Date of commencement as per W.O. Extended Date of Completion 1 M/s Viraj Projects (I) Pvt. Ltd. Construction of Public Rain Shelter cum Nat Mandir 23,828,531.00 2 Construction of Public Rain Shelter cum Dala Arcade 109,010,332.00 3 Construction of ECO Camp, Beach Shelter and Drainage 91,779,042.95 4 M/s N.K. Basu & Company Construction of Bus Terminius 18,517,073.93 5 Construction of Leach Pit Based Toilet and Solid Waste Management Facility 21,224,549.75

6 LIST OF PLANT & MACHINERIES AT SITE
Name of Contractor :- M/s Viraj Project (I) Pvt. Ltd. For Construction of Nat Mandir , Dala Arcade , Eco Camp Complex , Beach Shelter & Drainage Sl. No. Description As Per Contract Available at site Remarks 1 M/Machine With Hopper 2 Nos. 2 Nos 2 M/Machine without Hopper 0 Nos. 3 Electric Vibrator 9 Nos. 3 Nos. 4 Petrol Vibrator 4 Nos. 5 3.5 HP Pump 6 1.5 HP Pump 1 No. 7 5 HP Pump 8 Tulu Pump 9 Needle Shaft Pump 6 Nos. 10 R/F Cutting Machine

7 On Hire Basis when required
Sl. No. Description As Per Contract Available at site Remarks 11 Grinding Cutting Machine 3 Nos. 12 Compressive Testing Machine 1 No. 13 D.G. Set 2 Nos. 14 Sieve Analysis Set (For Fine Aggregate) 1 Set 15 Sieve Analysis Set (For Course Aggregate) 16 Auto Level 17 Excavator /Back Loader On Hire Basis when required 18 Truck/Tripper 5 Nos. 19 Theodolite 20 Polishing Machine 1 No

8 On Hire Basis when required On Hire Basis when required
Name of Contractor :- M/s N.K. Basu & Company For Construction of Bus Terminal , Leach Pit Based Toilet & Solid Waste Management Facility Sl. No. Description As Per Contract Available at site Remarks 1 M/Machine without Hopper 2 Nos. 1 No. 2 Weight Batcher 3 Tully Pump 4 3.5 H.P. Pump 5 Vibrator 10 Nos. 6 Earth Compacting Machine 7 Rod Cutting Machine 8 Excavator /Back Loader On Hire Basis when required 9 Truck/Tripper Nil On Hire Basis when required 

9 SKILLED MAN POWER DEPLOYED AT SITE
Name of Contractor: - M/s Viraj Project (I) Pvt. Ltd. Sl. No. Designation No. of Heads at Site 1 Project Manager 2 Engineer (Degree) 3 Engineer (Diploma) 4 Supervisor 5 Electrician 6 Mechanic 7 Stores Name of Contractor :- M/s N.K. Basu & Associates Sl. No. Designation No. of Heads at Site 1 Project Manager 2 Engineer (Degree) 3 Engineer (Diploma) 4 Supervisor 5 Electrician 6 Mechanic  7 Stores

10 STATUS OF PHYSICAL PROGRESS AT SITE
Name of Contractor: - M/s Viraj Project (I) pvt. Ltd. Name of Structure :- Public Rain Shelter Cum Nat Mandir Brief Description of Project as of 31st October 2016 Foundation : - Completed. Filling below foundation (Yellow Sand) :- Completed. Back Filling by Excavated Earth :- Completed. Tie Beam :- Completed. Column up to Roof Beam Bottom :- Completed. Silver Sand Filling below Plinth :- Completed. Plain Cement Concrete below Floor :- Completed. Grade Slab :- Completed. Dome Shuttering (As Per Revised Drg.) : - Completed Reinforcement Work (As Per Revised Drg.) :- Completed. Casting of Dome :-Completed. Plastering Work (Top of Dome) :- Completed. Ceiling Plastering :- Completed. Outside Plastering :- Completed. Crown of Dome Casting :- Completed. Flooring Work :- Kota Stone Flooring Laying Complete. Polishing is on progress. Electrical Work :- Work is on Progress. Mosaic Tiles Work in Column :- Work is on Progress. Note: - The Work Stopped due to alteration of the shape of dome from 20th November Revised drawing had been issued and the work started from 17/3/2016.

11 Sno. Description Unit Tender Quantity Tentative Revised Qty Executed Qty. Physical Progress Up to September In October Cumulative 1 Earth Work in Excavation Cum 575 955 893.59 0.00 82.28% 8.76% 91.04% 2 Silver Sand Filling/ yellow sand filling 460 410 407.78 3 Plain Cement Concrete 181 73.5 60.49 4 Reinforced Cement Concrete 255.3 290 277.95 1.06 279.00 5 Brick Work 175 153.75 128.09 6 Reinforcement Mt 33.6 16.4 15.66 0.13 15.79 7 Back Filling 280 780 775.14 8 Plaster 3365 2075 133.43 9 Shuttering Sqm 1195.4 1965 21.12 10 Kota Flooring 1380 805 400.71 19.30 420.02 11 Staging Work 1782 1470

12 Completion Status Major Mile Stone Basis up to 31st October 2016
Description of work Weight age % on the basis of Man Power Required Completion % as per weight age Excavation 15 Sand filling 4 Foundation Column + Masonary upto FFL 5 Floor At GRL 10 Column upto Bottom of Roof Roof Casting 24 Tiling work 6 5.1 Plaster 2 1.94 Electrical 1 Painting  0 Landscaping TOTAL 100 91.04

13

14 PHYSICAL PROGRESS EXECUTED ITEM WISE

15

16

17 Name of Contractor M/s Viraj Projects (I) Pvt. Ltd. Name of Structure Public Rain Shelter Cum Dala Arcade Brief Description of the Project as of 31st October, 2016 Excavation : 98% Completed Filling Below Foundation ( Yellow Sand) 100% Completed. Column Foundation (Base Raft) 100% Completed Column Casting Toilet Block Slab at (+)3.45 m Level Lintel Casting 100% Complete Damp Proof Course Work 100 % Completed Base Raft for Brick Work Brick Work in Sub- Structure Brick Work in Super Structure 97% Complete Inside Shop Brick Work & Parapet Wall 78% Completed Silver Sand Filling (Below Floor) Grade Slab Inside Plastering 62% Completed. Roof Slab Casting & Dome Casting 86% Completed Kota Stone Flooring 18% Completed Vitrified Tiles Fixing in Floor & Walls 20% Completed

18 Earth Work in Excavation 6.23% 83.54% 2
Sl.No. Description Unit Tender Quantity Tentative Revised Qty Executed Qty. Physical Progress Up to September In October Cumulative 1 Earth Work in Excavation Cum 2050 4900 0.00 77.31% 6.23% 83.54% 2 Silver Sand Filling/ yellow sand filling 1267 6195 3 Plain Cement Concrete 900 430 4 Reinforced Cement Concrete 1100 1570 58.04 5 Brick Work 1485 6 Reinforcement Mt 150 108 90.000 5.06 95.061 7 Back Filling 750 2000 8 Anti Termite (Base & Wall) Sqm 3850 5500 9 Anti Termite (Below Floor) 3300 3000 10 Damp Proof Course 115.5 98.5 98.341 11 Earth Disposal 530 12 Plaster 12650 15300 480.00 13 Shuttering 7450 7675 391.75 14 Staging Work 550 4000 225.77 15 Flooring 5240 5695

19 Completion Status Major Mile Stone Basis Up to 30th September 2016
Description of work Weight age % on the basis of Man Power Required Completion % as per weight age Excavation 15 14.7 Sand Filling in foundation 2 Foundation Concrete 5 Brick Work UPTO FFL 10 Brick Wall from FFL to Bottom of Roof 9.7 Floor Filling 6 Floor Concreting Roof Concreting 25 22 Partition Wall 3 2.34 Inside Plaster 1.24 Outside Plaster 0  Finish Flooring 0.36 Electrical 0.2 Painting 1 Sanitory  0 Land Scaping Door Windows MISC WORK TOTAL 100 83.54

20

21 PHYSICAL PROGRESS EXECUTED ITEM WISE

22 PHYSICAL PROGRESS EXECUTED ITEM WISE

23 PHYSICAL PROGRESS EXECUTED ITEM WISE

24 Name of Contractor :- M/s Viraj Project (I) Pvt. Ltd.
Name of Project :- Eco-Camp Complex Brief Description of the Project as of 31st October 2016 Large Hut (10 Nos) Excavation :- 8 Out of 10 Nos Hut Completed. Foundation :- 8 Out of 10 Nos Hut Completed. Column upto Plinth Level Slab :- 8 Out of 10 Nos Hut Complete. Casting of Plinth Slab :- 7 Out of 10 Nos Hut Completed. Column up to Eaves Beam Bottom :- 7 Out of 10 Nos Hut Completed. Casting of Eaves Beam :- 7 Out of 10 Nos Hut Completed. Brick work Above Plinth :- 6 Out of 10 Nos Hut Completed. Small Hut (20 Nos) Excavation :- 14 Out of 20 Nos Hut Completed. Foundation :- 13 Out of 20 Nos Hut Completed. Column upto Plinth Level Slab :- 11 Out of 20 Nos Hut Completed. Casting of Plinth Slab :- 9 Out of 20 Nos Hut Completed. Column up to Eaves Beam Bottom :- 9 Out of 20 Nos Hut Completed. Casting of Eaves Beam :- 7 Out of 20 Nos Hut Completed. Brick work Above Plinth :- 2 Out of 20 Nos Completed.

25 Eating House (1 No.) Excavation :- Completed. Foundation :- Completed. Column up to Plinth Level Slab :- Completed. Casting of Plinth Slab :- Completed. Column up to Eaves Beam Bottom :- Completed. Casting of Eaves Beam :- Completed. Brick Work Above Plinth :- Completed. Toilet Block (2 Nos)  Excavation :- 2 Out of 2 Nos Block Completed. Foundation :- 2 Out of 2 Nos Block Completed. Column up to Plinth Level Beam :- 2 Out of 2 Nos Block Completed. Plinth Level Beam :- 2 Out of 2 Nos Block Completed. Plinth Level Slab :- 2 Out of 2 Nos Completed. Brick Work above Plinth :- 1 Out of 2 Nos Completed up to Lintel Level. Lintel & Chajjah :- 1 Out of 2 Nos Completed.  Reception Block (1 No.)  Excavation :- Completed. Foundation :- Complete. Pedestal upto Plinth Level Slab :- Complete. Plinth Level Slab :- Complete.

26 Sl.No. Description Unit Tender Quantity Tentative Revised Qty Executed Qty. Physical Progress Up to September In October Cumulative 1 Earth Work in Excavation Cum 600 8000 0.00 36.45%  0.00%  2 Silver Sand Filling / Yellow Sand Filling 263 2000 3 Plain Cement Concrete 111 89.142 4 Reinforced Cement Concrete 344 700 591.43 5 Brick Work 480.5 204.61 6 Reinforcement Mt 40 60 53.59 7 Shuttering Sqm 2678 4300 8 Back Filling 513 7200 9 Flooring 1033

27 Completion Status Major Mile Stone Basis Up to 31st October 2016
Description of work Weightage % on the basis of Man Power Required Completion % as per weightage Excavation 15 11.25 Sand Filling in foundation 2 1.5 Foundation 10 7.2 Upto Floor Slab 6 Upto Eaves Beam 6.5 Masonary upto Eaves Beam 4 Roof  0 Plastering 5 Door Windows Flooring 3 Electrical Sanitary Painting Land Scaping MISC WORK TOTAL 100 36.45

28

29 PHYSICAL PROGRESS EXECUTED ITEM WISE

30

31 Name of Project :- Drainage
Name of Contractor :- M/s Viraj Project (I) Pvt. Ltd. Name of Project :- Drainage Brief Description of the Project as of 31st October,2016 WORK NOT YET STARTED. Sl. No. Description of Items Unit Tender Qty. Executed Quantity % Physical Progress Up to September In October Cumulative 1 Earth Work in Excavation Cum 9818 0.00% 2 Silver Sand / Yellow Sand Filling 2380 3 Plain Cement Concrete 4 Reinforced Cement Concrete 22.4 5 Brick Work 1806 6 Reinforcement Mt 2.24 7 Plastering Sq m 10413

32 Name of Contractor :- M/s Viraj Project (I) Pvt. Ltd.
Name of Project :- Beach Shelter Brief Description of the Project as of 31st October, 2016 WORK NOT YET STARTED. Sl. No. Description of Items Unit Tender Qty. Executed Quantity % Physical Progress Up to September In October Cumulative 1 Earth Work in Excavation Cum 250 0.00% 2 Silver Sand / Yellow Sand Filling 180 3 Plain Cement Concrete 62 4 Reinforced Cement Concrete 150 5 Brick Work 10 6 Plastering Sq m 7 Reinforcement Mt 23 8 Flooring 285

33 Name of Contractor :- M/s N.K. Basu & Company.
Name of Project :- Bus Terminal Brief Description of the Project as of 31st October 2016 Waiting Area. Foundation :- Completed . Column :- Completed . Tie Beam :- Completed. Eaves Beam :- Completed. Brick Work :- Stair Brick Work Completed. Back Filling :- Completed. Plastering work :- Completed up to Eaves Beam Grade Slab :- Completed. Food & Drink Facility. Foundation :- Completed. Column :- Completed. Tie Beam :- Completed. Eaves Beam :- Completed. Back Filing :- Completed. Brick Work :- Completed. Roof Beam :- Shuttering Work is on Progress

34 Toilet Block. Foundation :- Completed. Column :- Completed.
Tie Beam :- Completed. Back Filing :- Completed. Lintel & Chajjah Casting :- Completed. Eaves Beam :- Completed. Brick Work :- Completed. Plastering :- Completed up to Eaves Beam Grade Slab :- Completed. Roof Beam Casting :- Completed. Tourist & Information Office.  Excavation :- Completed. Pedestal :- Completed . Back Filling :- Completed. Tie-Beam :- Completed. Column :- Completed up to Eaves Beam Bottom Brick Work (Above Plinth) :- Completed up to Eaves Beam Bottom Plastering :- Completed up to Eaves Beam. Sanitary Works:- Septic Tank & Soak Pit Work :- Completed. S.W. Pipe Line Work :- Is on Progress. Bus Bay Excavation :- Is on Progress

35 Area Lightening Work. a) Foundation Work
Excavation :- Out of 29 Nos 23 Nos Complete. Raft Casting :- Out of 29 Nos 23 Nos Complete.

36 Sl.No. Description Unit Tender Quantity Tentative Revised Qty Executed Qty. Physical Progress Up to September In October Cumulative 1 Earth Work in Excavation Cum 180 29.917 53.62% 4.48% 58.10% 2 Yellow Sand Filling 420.00 0.000 3 Silver Sand Filling 335 950.00 4 Plain Cement Concrete 110 205.00 97.602 1.557 99.159 5 Reinforced Cement Concrete 191 945.00 6.794 6 Brick Work 170.75 185.00 7 Reinforcement Mt 29 20.00 14.550 0.789 15.339 8 Shuttering Sqm 1815 63.310 9 Back Filling 125 10 Septic Tank & Soak Pit Nos  2 2  0.00 11 Plaster 935

37 Completion Status Major Mile Stone Basis up to 31st October 2016
Description of work Weightage % on the basis of Man Power Required Completion % as per weightage Excavation 20 17 Sand filling 3 2.55 Foundation 23 20.7 Massonary Above Plinth 5 4.9 Floor At GRL 4 Column upto Bottom of Roof 7 6.65 Roof Casting 8 2 Sheeting Work / Oloo Thatching Work 0  Tiling work  0 Plaster Electrical Painting 1 Brick Pavement 6 Plumbing & Sanitary 0.45  Door & Window Mislenious TOTAL 100 58.10

38

39 PHYSICAL PROGRESS EXECUTED ITEM WISE

40

41

42 Name of Project :- Leach Pit Based Toilet
Name of Contractor :- M/s N.K. Basu & Company. Name of Project :- Leach Pit Based Toilet Brief Description of the Project as of 31st October ,2016 Out of 20 Nos Unit – Work is on Progress in 19 Nos Unit 5 Nos Block Completed up to Super Structure. 4 Nos Block Completed up to Sub Structure (Pit). 10 Nos Block Sub Structure Work is on Progress. Note :- 4 Nos Block which are located near Road No. 1 is temporary stoped due to errosion of Sand Sl.No. Description Unit Tender Quantity Tentative Revised Qty Executed Qty. Physical Progress Up to September In October Cumulative 1. Construction of temporary toilet blocks with Leach Pit based onsite treatment system toilet per unit Nos 20 14 5 19 45% 10% 55%

43 Name of Contractor: - M/s N.K. Basu & Company
Name of Structure: - Temporary & Permanent Composite Plant Brief Description of Status as of 31st October 2016 Not Yet Started. Sl. No. Description of Items Unit Tender Qty. Executed Quantity % Physical Progress Up to September In October Cumulative 1 Earth Work in Excavation Cum 253 0.00 % 2 Silver Sand / Yellow Sand Filling 115 3 Plain Cement Concrete 473 4 Reinforced Cement Concrete 181 5 Brick Work 20 6 Plastering Sqm 243

44 FINANCIAL PROGRESS AS OF 31st October , 2016
Sl. no. Name of Contractor Name of Job Contact Value Financial Progress Up to September In October Cumulative 1 M/s Viraj Project (P) Ltd. Construction of Rain Shelter cum Nat Mandir 23,828,531.00 47.132% 0.689% 47.821% 2 Construction of Rain Shelter cum Dala Arcade 109,010,332.00 53.026% 5.057% 58.084% 3 Construction of Eco- Camp Complex , 51,294,983.95 46.12% 0.00% 4 Construction of Beach Shelter & Drainage 40,484,059.00 5 M/s N.K. Basu & Company Construction of Bus Terminal 18,517,073.93 47.83% 1.06% 48.90% 6 Construction of Leach Pit Based Toilet 9,860,000.00 26.75% 5.55% 32.30% 7 Construction of Temporary and permanent composite solid waste facility 11,364,549.76

45 RA Bill reference & Date
PAYMENT DETAILS Package -1: Construction of Public Rain Shelter cum Nat Mandir & Public Rain Shelter cum Dala Arcade Sl. No. RA Bill reference & Date Date of Certification Amount (Rs) Remarks 1. Mobilisation Advance 6.642 million 2. 1st RA Bill 25/8/2015 91.94 Lac 3. 2nd RA Bill 18/09/2015 22.63 Lac 4. 3rd RA Bill 01/10/2015 44.93 Lac 5. 4th RA Bill 18/12/2015 43.06 Lac 6. 5th RA Bill 28/12/2015 33.09 Lac 7. 6th RA Bill 13/01/2016 48.47 Lac 8. 7th RA Bill 22/03/2016 25.12 Lac 9 8th RA Bill 27/04/2016 64.71 Lac 10 9th RA Bill 23/5/2016 62.69 Lac 11 10th RA Bill 04/7/2016 60.75 Lac 12 11th RA Bill 30/7/2016 37.97 Lac 13 12th RA Bill 31/8/2016 66.84 Lac 14 13th RA Bill 19/9/2016 64.76 Lac 15 14th RA Bill 3/10/2016 Lac 16 15th RA Bill 26/10/2016 33.83 Lac

46 RA Bill reference & Date
Package -2: Construction of ECO - Camp Complex , Beach Shelter and Drainage Sl. No. RA Bill reference & Date Date of Certification Amount ( Rs) Remarks 1. Mobilisation Advance 4.589 million 2. 1st RA Bill 25/8/2015 23.75 Lac 3. 2nd RA Bill 18/09/2015 18.53 Lac 4. 3rd RA Bill 01/10/2015 5.68 Lac 5. 4th RA Bill 18/12/2015 25.32 Lac 6. 5th RA Bill 28/12/2015 25.62 Lac 7. 6th RA Bill 13/01/2016 26.34 Lac 8. 7th RA Bill 01/02/2016 30.42 Lac 9. 8th RA Bill 08/03/2016 22.19 Lac 10 9th RA Bill 27/04/2016 28.36 Lac 11 10th RA Bill 23/5/2016 21.16 Lac 12 11th RA Bill 18/7/2016 5.53 Lac

47 RA Bill reference & Date RA Bill reference & Date
Package -3: Construction of Leach Pit Based Toilet and Solid Waste Management Facility Sl. No. RA Bill reference & Date Date of Certification Amount (Rs.) Remarks 1. Mobilisation Advance 1.061 million 2. 1st RA Bill 23/01/2016 21.19 Lacs 3. 2nd RA Bill 03/10/2016 5.17 Lacs Package -4: Construction of Bus Terminus Sl. No. RA Bill reference & Date Date of Certification Amount (Rs.) Remarks 1. Mobilisation Advance 0.925 million 2. 1st RA Bill 25/8/2015 23.90 Lac 3. 2nd RA Bill 31/10/2015 15.77 Lac 4. 3rd RA Bill 7/12/2015 31.29 Lac 5. 4th RA Bill 22/03/2016 10.19 Lac 6 5th RA Bill 18/7/2016 7.29 Lac

48 SITE PROGRESS PHOTOGRAPH
AS OF 31st October, 2016

49 BUS TERMINAL – TOURIST & INFORMATION CENTRE –PLASTERING COMPLETE
BUS TERMINAL – TOILET BLOCK – ROOF BEAM CASTING COMPLETE. BUS TERMINAL – WAITING AREA – PLASTERING COMPLETE BUS TERMINAL – FOOD & DRINK FACILITY – ROOF BEAM SHUTTERING IS ON PROGRESS

50 ECO- CAMP – LARGE HUT (BRICK WORK ABOVE PLINTH)
ECO- CAMP – LARGE HUT– STRUCTURAL WORK IN PROGRESS ECO-CAMP – EATING HOUSE-BRICK WORK COMPLETED ECO-CAMP – TOILET BLOCK-I (UP TO LINTEL LEVEL)

51 ECO-CAMP TOILET BLOCK II– (COLUMN COMPLETED UPTO LINTEL LEVEL)
ECO-CAMP – RECEPTION CENTRE– PLINTH SLAB COMPLETE ECO-CAMP – SMALL HUT – EAVES BEAM WORK IS IN PROGRESS ECO-CAMP – SMALL HUT (BRICK WORK)

52 ECO-CAMP – SMALL HUT (EXCAVATION & FOUNDATION WORK IS IN PROGRESS)
PUBLIC RAIN SHELTER CUM DALA ARCADE (KOTA FLOORING WORK IS ON PROGRESS) PUBLIC RAIN SHELTER CUM DALA ARCADE (VETRIFIED TILES FIXING WORK IS ON PROGRESS – INSIDE SHOP) PUBLIC RAIN SHELTER CUM DALA ARCADE ( DOME WORK IS IN PROGRESS)

53 PUBLIC RAIN SHELTER CUM DALA ARCADE – PRE-CAST JALLI FIXING WORK IS ON PROGRESS
PUBLIC RAIN SHELTER CUM DALA ARCADE – ROLLING SHUTTER FIXING WORK IS ON PROGRESS PUBLIC RAIN SHELTER CUM DALA ARCADE – OUTSIDE ELEVATION WORK IS ON PROGRESS PUBLIC RAIN SHELTER CUM DALA ARCADE – TOTAL ROOF CASTING COMPLETE.

54 PUBLIC RAIN SHELTER CUM DALA ARCADE (OUTSIDE PLASTERING WORK IS ON PROGRESS)
PUBLIC RAIN SHELTER CUM DALA ARCADE ( INTERNAL PLASYTERING WORK IS ON PROGRESS) LEACH PIT BASED TOILET (IN ROAD NO. 5) :- TANK BRICK WORK IS IN PROGRESS LEACH PIT BASED TOILET (IN ROAD NO. 5) :- TOILET BRICK WORK IS IN PROGRESS

55 PUBLIC RAIN SHELTER CUM NAT MANDIR – DOME COMPLETED.
PUBLIC RAIN SHELTER CUM DALA ARCADE INSIDE PLASTERING WORK IS ON PROGRESS PUBLIC RAIN SHELTER CUM NAT MANDIR – KOTA STONE FLOORING WORK IS ON PROGRESS PUBLIC RAIN SHELTER CUM NAT MANDIR – COLUMN TILES WORK IS ON PROGRESS

56 ENVIRONMENT & SAFETY

57 Temporary Toilet for Worker at Dala Arcade
Temporary Toilet for Worker at Bus Terminal PROPER STACKING OF MATERIALS AT SITE AFTER WORK HARD BARICATION ALL AROUND IN THE HEIGHT STRUCTURE

58