Download presentation
Presentation is loading. Please wait.
Published byJosephine Lynch Modified over 8 years ago
1
IE 366 Chapter 6, Section 10 Project Planning and Scheduling
2
IE 366 Gantt Charts: Cesarean Section Facilitator Project
3
IE 366 Critical Path Method (CPM) ● Define – Activities/Tasks – Activity precedence relationships – Activity times ● Construct network (graph) – Node = beginning of activity – Arc (line) = activity – Number on arc = duration of activity ● Make forward pass – Find earliest possible start times – Maximum of incoming paths ● Make backward pass – Find latest necessary start times to finish on schedule – Minimum of outgoing paths ● Calculate slack times – Latest – earliest ● Critical path is path with zero slack
4
IE 366 CPM Steps ● Define – Activities/Tasks – Activity precedence relationships – Activity times ● Construct network (graph) – Node = beginning of activity – Arc (line) = activity – Number on arc = duration of activity ● Make forward pass – Find earliest possible start times – Maximum of incoming paths ● Make backward pass – Find latest necessary start times to finish on schedule – Minimum of outgoing paths ● Calculate slack times – Latest – earliest ● Critical path is path with zero slack
5
IE 366 CPM Example: Preparing a Meal 7Begin meal8 584,6Serve meal7 1075Assemble spaghetti6 3062Prepare spaghetti ingredients5 573Assemble salad4 1042Prepare salad ingredients3 53,51Instruct helper on salad preparation2 152 Set up kitchen1 MinutesPrecedesFollowsActivityNumber
6
IE 366 CPM Steps ● Define – Activities/Tasks – Activity precedence relationships – Activity times ● Construct network (graph) – Node = beginning of activity – Arc (line) = activity – Number on arc = duration of activity ● Make forward pass – Find earliest possible start times – Maximum of incoming paths ● Make backward pass – Find latest necessary start times to finish on schedule – Minimum of outgoing paths ● Calculate slack times – Latest – earliest ● Critical path is path with zero slack
7
IE 366 CPM Example: Construct Network 1
8
IE 366 CPM Example: Construct Network 12
9
IE 366 CPM Example: Construct Network 123
10
IE 366 CPM Example: Construct Network 1234
11
IE 366 CPM Example: Construct Network 123 5 4
12
IE 366 CPM Example: Construct Network 123 5 4 6
13
IE 366 CPM Example: Construct Network 123 5 4 6 7
14
IE 366 CPM Example: Construct Network 123 5 4 6 78
15
IE 366 CPM Example: Construct Network (neatly) 12 3 5 4 6 78
16
IE 366 CPM Example: Construct Network 12 3 5 4 6 78 15 5 5 30 10 5 5
17
IE 366 CPM Steps ● Define – Activities/Tasks – Activity precedence relationships – Activity times ● Construct network (graph) – Node = beginning of activity – Arc (line) = activity – Number on arc = duration of activity ● Make forward pass – Find earliest possible start times – Maximum of incoming paths ● Make backward pass – Find latest necessary start times to finish on schedule – Minimum of outgoing paths ● Calculate slack times – Latest – earliest ● Critical path is path with zero slack
18
IE 366 CPM Example: Forward Pass 12 3 5 4 6 78 0 15 5 5 30 10 5 5
19
IE 366 CPM Example: Forward Pass 12 3 5 4 6 78 0 15 5 5 30 10 5 5
20
IE 366 CPM Example: Forward Pass 12 3 5 4 6 78 0 15 5 5 20 30 10 5 5 35 30
21
IE 366 CPM Example: Forward Pass 12 3 5 4 6 78 0 15 5 5 20 50 30 10 5 5 35/60 30
22
IE 366 CPM Example: Forward Pass 12 3 5 4 6 78 0 15 5 5 20 50 30 10 5 5 35/6065 30
23
IE 366 CPM Steps ● Define – Activities/Tasks – Activity precedence relationships – Activity times ● Construct network (graph) – Node = beginning of activity – Arc (line) = activity – Number on arc = duration of activity ● Make forward pass – Find earliest possible start times – Maximum of incoming paths ● Make backward pass – Find latest necessary start times to finish on schedule – Minimum of outgoing paths ● Calculate slack times – Latest – earliest ● Critical path is path with zero slack
24
IE 366 CPM Example: Backward Pass 12 3 5 4 6 78 0 15 5 5 20 50 30 10 5 5 35/6065 30
25
IE 366 CPM Example: Backward Pass 12 3 5 4 6 78 0 15 5 5 20 50 30 10 5 5 35/60 60 65 30
26
IE 366 CPM Example: Backward Pass 12 3 5 4 6 78 0 15 40 5 5 20 45 2050 30 10 5 5 35/60 60 65 30 55
27
IE 366 CPM Example: Backward Pass 12 3 5 4 6 78 0 15 40/15 5 5 20 45 20 50 30 10 5 5 35/60 60 65 30 55
28
IE 366 CPM Example: Backward Pass 12 3 5 4 6 78 0 0 15 40/15 5 5 20 45 20 50 30 10 5 5 35/60 60 65 30 55
29
IE 366 CPM Steps ● Define – Activities/Tasks – Activity precedence relationships – Activity times ● Construct network (graph) – Node = beginning of activity – Arc (line) = activity – Number on arc = duration of activity ● Make forward pass – Find earliest possible start times – Maximum of incoming paths ● Make backward pass – Find latest necessary start times to finish on schedule – Minimum of outgoing paths ● Calculate slack times – Latest – earliest ● Critical path is path with zero slack
30
IE 366 CPM Example: Critical Path 12 3 5 4 6 78 0 0 15 40/15 5 5 20 45 20 50 30 10 5 5 35/60 60 65 30 55
31
IE 366 Project Evaluation and Review Technique (“Enhanced PERT”)
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.