Actions Related to the Proposed Evans Lane Interim Housing Community City Council Meeting August 16, 2016 Item 4.1.

Similar presentations


Presentation on theme: "Actions Related to the Proposed Evans Lane Interim Housing Community City Council Meeting August 16, 2016 Item 4.1."— Presentation transcript:

1 Actions Related to the Proposed Evans Lane Interim Housing Community City Council Meeting August 16, 2016 Item 4.1

2 The Challenge 2 4,063 homeless men and women in San José 307 homeless men and women with housing vouchers in hand who are unable to find a home 157 Veterans 150 Vulnerable Individuals 500 supportive housing apartments will become available starting in 2018

3 Background 2 1998 Site purchased 2005 Unsuccessful RFQ for site development 2011 GP 2040 rezoned parcel to NCC

4 Background 2 1998 Site purchased 2005 Unsuccessful RFQ for site development 2011 GP 2040 rezoned parcel to NCC Sept. 22, 2015 Council direction to work on an interim housing development

5 Background 2 1998 Site purchased 2005 Unsuccessful RFQ for site development 2011 GP 2040 rezoned parcel to NCC Sept. 22, 2015 Council direction to work on an interim housing development Jan. 2016: Initiated GP Change & Released RFP June 28, 2016: GP Amendment Approved Direction to explore permanent, high-density alternative 2018 Site development activities must begin

6 Permanent Housing (Example)

7 Permanent Housing Examples Symphony Student Housing 7 stories (5 residential; 2 non- residential) Donner Lofts 6 stories (5 residential; 1 non- residential)

8 2 Dog Park for Residents & Community Community Gardens Vehicle Circulation Community Center Neighborhood Community Resource Offices Recommendation: Interim Housing Use

9 Shared Supportive Housing

10 Goal: House Individuals with Vouchers 44% of those with vouchers will be housed by summer including men, women, and seniors

11 Goal: House Veterans 21% of those with vouchers will be housed by summer

12 Goal: Transition into Permanent Apartment 2 September 2015 City Council Approves Concept for Interim Housing Community Model July 2017 Issued $40MM NOFA – will identify supportive housing projects likely to be completed in 2020-21

13 Goal: Transition into Permanent Apartment 2 Summer 2017 Evans Lane Opens September 2015 City Council Approves Concept for Interim Housing Community Model July 2017 Issued $40MM NOFA – will identify supportive housing projects likely to be completed in 2020-21

14 Goal: Transition into Permanent Apartment 2 Summer 2017 Evans Lane Opens 2018 Second Street 133 apartments 2019 Renascent Place 160 Studios 2019 St. James Station 55 apartments for Veterans September 2015 City Council Approves Concept for Interim Housing Community Model 2017 Vermont House 16 shared apartments July 2017 Issued $40MM NOFA – will identify supportive housing projects likely to be completed in 2020-21

15 ItemRecommendationAlternative Description Interim Supportive Housing Community Permanent Affordable/ Market-Rate Housing Density 17 units/ 102 residents 446 units/ 990 residents Completion Date Summer 2017 Fall 2022 (affordable) Fall 2021 (market) Community Amenities 9 months42-72 months Total Development Costs $12.8M-$15M$109M Comparison of Options

16 ItemRecommendationAlternative Description Interim Supportive Housing Community Permanent Affordable/ Market-Rate Housing Density 17 units/ 102 residents 446 units/ 990 residents Completion Date Summer 2017 Fall 2022 (affordable) Fall 2021 (market) Community Amenities 9 months42-72 months Total Development Costs $12.8M-$15M$109M Comparison of Options

17 ItemRecommendationAlternative Description Interim Supportive Housing Community Permanent Affordable/ Market-Rate Housing Density 17 units/ 102 residents 446 units/ 990 residents Completion Date Summer 2017 Fall 2022 (affordable) Fall 2021 (market) Community Amenities 9 months42-72 months Total Development Costs $12.8M-$15M$109M Comparison of Options

18 ItemRecommendationAlternative Description Interim Supportive Housing Community Permanent Affordable/ Market-Rate Housing Density 17 units/ 102 residents 446 units/ 990 residents Completion Date Summer 2017 Fall 2022 (affordable) Fall 2021 (market) Community Amenities 9 months42-72 months Total Development Costs $12.8M-$15M$109M Comparison of Options

19 Abode Services Housed 5,074 people in last five years 27 Years of experience in homelessness & housing services

20 Next Steps October – December o Project Entitlements Planning Commission and/or City Council consideration of PD Zoning & Permit o Project Funding City Council consideration of funding for the Project Continue Community Outreach Complete Neighborhood Assessments

21 Recommendations Use of the Property as the site of an interim housing community Selection of Abode as the Developer/ Operator Lease of Property to Abode Predevelopment grant to Abode

22

23 DATEEVENTATTENDEES March 30PBCE Community Meeting200 May 25Monterey Corridor Business Association30 June 1Community Meeting12 June 20Community Meeting40 June 23Willow Glen Neighborhood Association45 July 20Community Meeting45 Aug-Nov Monthly Community Meetings with Neighbors and Stakeholders Pending TBDPBCE Public MeetingPending Community Outreach (to date/future)

24 Bridge vs. Shared Supportive Housing Item Bridge Communities (AB2176) Shared Supportive Housing Number of people served50102 Upfront development costs$500K - $3.7 MM$12.8 - $15 MM Eligible for Housing Authority assistance? NoYes Annual City cost$360K$0 Long-term cost to the City$5.945 MM (5-years)$12.8 - $15 MM (15-years) Project ready for occupancySpring 2017 – Fall 2018Summer 2017 Developer/operator identified? NoYes Neighborhood amenitiesTBDYes Restrooms, kitchen facilities, and laundry access Shared community spacePrivate within each home


Download ppt "Actions Related to the Proposed Evans Lane Interim Housing Community City Council Meeting August 16, 2016 Item 4.1."

Similar presentations


Ads by Google