Download presentation
Presentation is loading. Please wait.
Published byAnne Mosley Modified over 8 years ago
1
Milford Haven Bridge Collapse Group 9 Gary Donohoe Joseph Gill Aisling Kearney James Thompson
2
Contents History Construction Collapse Reasons for Collapse Actions Taken Conclusions
3
History The Milford Haven Bridge is now known as The Cleddau Bridge since its collapse during construction in 1970 It spans the River Cleddau between Neyland and Pembroke Dock in Wales Milford Haven in the mid 1960’s had grown to become a major oil port capable of handling some of the worlds largest tankers The bridge was built because only a ferry service existed to travel across the river at the time Construction began in September 1968 The bridge collapsed in 1970 resulting in the loss of four lives Construction recommenced in 1972 The bridge opened to traffic in 1975 and approximately 885,900 vehicles used it in its first year This figure has grown to almost 4 million in 2006 It is still in use as a toll bridge
4
Construction The bridge has 7 spans and rests on 6 piers It is a box girder design The shape of the girder makes its inherently strong The box girders can be bolted or welded together to form a section which behaves like a single beam This presents solutions to designers as when used appropriately it can created a very strong and stiff beam
5
Collapse The collapse of the partially completed bridge happened on Tuesday 2nd June 1970 A 70m cantilever collapsed on the south bank The collapse happened as one of the 150- ton sections was being cantilevered into position to connect the road span of the bridge to the second of the 100-feet-high reinforced concrete pillars, on the Pembroke Dock side During construction the stresses are quite different of what might be expected on completion of the bridge The structure just appeared to fold
6
Reasons for Collapse Improved steel producing techniques meant that designers could be more confident of the strengths of steel being consistent and so section sizes could be reduced At the time the stresses which arise during construction were not fully appreciated There was no substantial stiffening of the box sections other than at the pier support’s of the bridge This meant that during construction the box section developed very large moments causing it to buckle about the pier it was being constructed from
7
Actions Taken as a Result of The Milford Haven Collapse This and two other box girder bridge disasters led to the formation of the Merrison Commission They looked at the adequacy of existing codes in relation to box girders They set down guidelines for stress analysis and the way in which box girders were to be connected These were formalised in BS 5400 and led to the creation of specialised sections dealing with box girders Other recommendations included clarifying the roles of the engineer and contractor, such as vetting of design and construction methods It was recommended that the design rules should be used only by suitably experienced designers
8
Conclusion This failure occurred due to the fact that the engineers were pushing the boundaries of their knowledge at the time of this incident The disaster led to a better understanding of the complexities of steel box girder design Armed with this knowledge, more powerful computers, and the updated codes, we are hopeful that a disaster like this will not happen again
Similar presentations
© 2025 SlidePlayer.com Inc.
All rights reserved.