Construction Methodology for Suramadu Approach Bridge

Similar presentations


Presentation on theme: "Construction Methodology for Suramadu Approach Bridge"— Presentation transcript:

1 CONSORTIUM OF INDONESIAN CONTRACTOR (CIC) SURAMADU BRIDGE PROJECT ADHI – HUTAMA – WASKITA - WIJAYA DESCRIPTION OPERATIONAL CONSTRUCTION OF SURAMADU BRIDGE

2 PLAN LAY OUT AWARE TO COMM. LINE SHIPMENT AWARE TO FERRY CROSSING LINE ATTEND TO WINDOWS TIME BRIDGE SITE PLAN SURABAYA MADURA APPROACH BRIDGE MADURA APPROACH BRIDGE SURABAYA

3 APPROACH BRIDGE 672 M 818 M APPROACH BRIDGE 672 M CABLE STAY BRIDGE BRIDGE ELEVATION TO SURABAYA TO MADURA BRIDGE DETAILS 36 37 38 39 40 41 42 43 44 45 48 49 50 51 52 53 54 55 56 57 SURAMADU BRIDGE EAST JAVA - INDONESIA

4 LAY OUT OF MAP PROJECT LOCATION STOCKYARD AND SITE OFFICE CIC AND CCC

5 STOCK YARD AND SITE OFFICE MAP STOCK YARD AND SITE OFFICE WARF

6 SCOPE OF WORKS

7 Sub Structure of Works Bored Pile Pile Cap Super Structure of Works Pier Works Pier Table Concrete Box Girder STRUCTURE : ENGINEERING FOM AND TECHNICAL STUDY : Soil Investigation

8 LOCATION OF WORK

9 LOCATION OF SOIL INVESTIGATION Pier 56 s/d Pier 48 Pier 56 = S 07’10’32,45” E 112’46’48,15” Pier 55 = S 07’10’35,04” E 112’46’47,97” Pier 54 = S 07’10’37,64” E 112’46’47,80” Pier 53 = S 07’10’40,24” E 112’46’47,63” Pier 52 = S 07’10’42,84” E 112’46’47’46” Pier 51 = S 07’10’45,44” E 112’46’47,29” Pier 50 = S 07’11’48,04” E 112’46’47,12” Pier 49 = S 07’10’50,63” E 112’46’46,94” Pier 48 = S 07’10’50,63” E 112’46’46,79” Pier 45 = S 07’11’19,54” E 112’46’45,04” Pier 44 = S 07’11’21,88” E 112’46’44,88” Pier 43 = S 07’11’24,48” E 112’46’44,71” Pier 42 = S 07’11’27,08” E 112’46’44,54” Pier 41 = S 07’11’29,67” E 112’46’44,37” Pier 40 = S 07’11’32,27” E 112’46’44’20” Pier 39 = S 07’11’34,87” E 112’46’44,02” Pier 38 = S 07’11’37,47” E 112’46’43,85” Pier 37 = S 07’11’40,07” E 112’46’43,68” Pier 45 s/d Pier 37

10 P 37P 45 P 48 P 56 500 M CLEREANCE AREA FOR CONSTRUCTION OF BRIDGE SURABAYA MADURA PIER LAYOUT OF SITE WORK EQUIPMENT AND MOBILIZATION SEA

11 ServiceBarge BoredBarge MuddyBarge PIER Anchorage Line app. 200 m Batching Barge Feeder Barge CONFIGURATION EQUIPMENT FOR STRUCTURE Center Line of Bridge

12 PIER Anchorage Line app. 200 m Batching Barge Feeder Barge CONFIGURATION EQUIPMENT FOR SUPER STRUCTURE Center Line of Bridge PIER Formwork and Rebar Feeder Lifting Barge

13 LIST OF EQUIPMENT

14 TRAFFIC MANAGEMENT AT LAND

15 Traffic management at land consist of: 1. 1. Trailer truck with load go to location of stock yard areaTrailer truck with load go to location of stock yard area 2. Trailer truck with load from stock yard location go to wharf 3. Dump truck with raw material from out site go to wharf 4. Trailer truck whithout load from wharf to stock yard area Trailer truck whithout load from wharf to stock yard area Trailer truck whithout load from wharf to stock yard area next TRAFFIC MANAGEMENT SYSTEM AT LAND

16 1. Concrete rebar= ± 15 ton 2. Casing Pipe = ± 15 ton 3. Aggregat= ± 16 ton 4. Others= ± 10 ton 5. Trailer / Dump Truck= ± 20 ton Loading and Unloading activity at wharf consist of :

17 TRUCK BARGE LOADING AND UNLOADING ACTIVITY CONSORTIUM OF INDONESIAN CONTRACTOR SURAMADU BRIDGE PROJECT MATERIAL WILL BE DELIVERED: Casing Pipa Reinforcement Bar Aggregate Formwork

18 BARGE CONSORTIUM OF INDONESIAN CONTRACTOR SURAMADU BRIDGE PROJECT MATERIAL WILL BE DELIVERED: Casing Pipa Reinforcement Bar Aggregate Formwork LOADING AND UNLOADING ACTIVITY

19 TRUCK BARGE CONSORTIUM OF INDONESIAN CONTRACTOR SURAMADU BRIDGE PROJECT MATERIAL WILL BE DELIVERED: Casing Pipa Reinforcement Bar Aggregate Formwork LOADING AND UNLOADING ACTIVITY

20 TRUCK BARGE CONSORTIUM OF INDONESIAN CONTRACTOR SURAMADU BRIDGE PROJECT MATERIAL WILL BE DELIVERED: Casing Pipa Reinforcement Bar Aggregate Formwork LOADING AND UNLOADING ACTIVITY

21 CONSORTIUM OF INDONESIAN CONTRACTOR SURAMADU BRIDGE PROJECT

22 CONSORTIUM OF INDONESIAN CONTRACTOR SURAMADU BRIDGE PROJECT LOADING AND UNLOADING ACTIVITY

23 CONSORTIUM OF INDONESIAN CONTRACTOR SURAMADU APPROACH BRIDGE PROJECT Raw Materials LOADING AND UNLOADING ACTIVITY

24 CONSORTIUM OF INDONESIAN CONTRACTOR SURAMADU APPROACH BRIDGE PROJECT Raw Materials LOADING AND UNLOADING ACTIVITY

25 CONSORTIUM OF INDONESIAN CONTRACTOR SURAMADU APPROACH BRIDGE PROJECT Raw Materials LOADING AND UNLOADING ACTIVITY

26 CONSORTIUM OF INDONESIAN CONTRACTOR SURAMADU APPROACH BRIDGE PROJECT Raw Materials LOADING AND UNLOADING ACTIVITY

27 TRAFFIC MANAGEMENT AT SEA

28 BARGE BARGE 1 AWARE TO COMM. LINE SHIPMENT AWARE TO FERRY CROSSING LINE ATTEND TO WINDOWS TIME MATERIALS BARGE 2 LIGHT BUOY MADURASITE SURABAYASITE BRIDGE SITE PLAN TRAFFIC MANAGEMENT AT SEA MATERIAL WILL BE DELIVERED: Casing Pipa Reinforcement Bar Aggregate Formwork

29 HEALTH,SAFETY AND ENVIRONMENT (HSE) PROGRAM

30 MANPOWER Safety training for workers for example : Safety Basic Training for special worker and Safety Induction for all worker at the first time to do work. Safety training for workers for example : Safety Basic Training for special worker and Safety Induction for all worker at the first time to do work. Used appropriate APD (Safety Tools). Used appropriate APD (Safety Tools). Safety Inspection by HSE officer, implementation of K3 in site. Safety Inspection by HSE officer, implementation of K3 in site. Identification Card, to enter site area of Suramadu Project. Identification Card, to enter site area of Suramadu Project. First Aid Clinic, to give help of P3K and inspection of worker health  worker has to be in good health. First Aid Clinic, to give help of P3K and inspection of worker health  worker has to be in good health.

31 EQUIPMENT PROTEC SELF

32 ENVIRONMENT ( CLEAN AND HEALTH ENVIRONMENTAL) Clearing of land material transportation line, from ground mud, and concrete material continuously. Clearing of land material transportation line, from ground mud, and concrete material continuously. Water tanker for splash water in the material transportation road, to reduce dust risk as consequence of vehicle transportation. Water tanker for splash water in the material transportation road, to reduce dust risk as consequence of vehicle transportation. Basin in front off outside door in stock yard area, to minimize mud from vehicle tire. Basin in front off outside door in stock yard area, to minimize mud from vehicle tire. The place for relocation of garbage must be prepare in stock yard area, before brought to final places. The place for relocation of garbage must be prepare in stock yard area, before brought to final places. Preparation for drainage system and adequate utilities in stockyard location. Preparation for drainage system and adequate utilities in stockyard location.

33 SAFETY SIGNS & PROMOTION K3 Safety sign, to set in strategic area. K3 Safety sign, to set in strategic area. The target is : to giving understanding concerning K3, we hope safety work will be created. The target is : to giving understanding concerning K3, we hope safety work will be created. Warning sign, warning, announcement and guide of direction. Warning sign, warning, announcement and guide of direction.

34 DESIGN OF SAFETY SIGN

35

36

37 SCHEDULE OF WORK

38 GENERAL SCHEDULE