1 Economic Regeneration Progress Report – September 2011 Achievements and Progress on Regeneration Schemes

2 Achievements – Great North Run 2 million viewers saw South Tyneside on the BBC as 38,000 runners completed the Great North Run

3 Achievements – Economic Growth Recruitment campaign for BT retail jobs going well. 119 of 220 jobs filled to date. 80% of successful candidates are residents of South Tyneside Over 400 people refereed to Call Centre skills training, facilitated by the Council Jobsfair held 28 September

4 Achievements – Regeneration One Harton Quay – Project Completion and handover to BT achieved 29 September 2011

5 Achievements - Regeneration Handover to the Council of 20 bungalows for older persons at Druridge Crescent Key handover ceremony held early September at East Croft sheltered housing, Rackly Way - Whitburn

6 Regeneration Progress Swimming pool at Pier Parade – site photographs September 2011 – Construction project remains on programme, in some cases ahead of schedule

7 Regeneration Progress Green Incubator South Shields – site photographs September 2011, project remains on programme

8 Regeneration Progress Hebburn Town Centre – Site photograph September 2011. Glen and Thistle Courts demolished, site now grass seeded School Street, Hebburn, site photograph, September 2011. Good progress continues in the construction of new housing