June 2016. 4 Skywalk M/s mayaPRAXIS have submitted the draft report - Preliminary Feasibility Study on Skywalk system for Electronics city phase 1. E.

Similar presentations


Presentation on theme: "June 2016. 4 Skywalk M/s mayaPRAXIS have submitted the draft report - Preliminary Feasibility Study on Skywalk system for Electronics city phase 1. E."— Presentation transcript:

1 June 2016

2 4 Skywalk M/s mayaPRAXIS have submitted the draft report - Preliminary Feasibility Study on Skywalk system for Electronics city phase 1. E – Toilets 16 e-toilets operational. Estate survey Roads & common area survey completed for Phase 1& 2. Plot Inventory of the Industries 98 % completed. GIS Web Application Software work in progress.

3 3

4 4

5 5

6 6

7 7 Kerbstone Painting along Wipro/Shikaripalaya Road

8 8

9 9

10 10

11 11

12 12

13 13

14 14

15 15 WMM Road From MSME Building to Exit Gate

16 16

17 17

18 18 Installation of Automated Toilets

19 19

20 20

21 21

22 22

23 23 RWH works – Under Progress SI.NODESCRIPTIONNO OF PITSSTATUS 1RAIN WATER HATVESTING PIT 38COMPLETED 2RAIN WATER HATVESTING PIT 12TO BE AWARDED

24 24 20 feet deep well Rainwater Harvesting Pit at Various locations

25 25

26 26 Contract Awarded Providing and laying of Asphalting using 60/70 grade bitumen along Café Corner & JP IT Park Road

27 27 Contracts on Anvil Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs along TCS Road Providing UGD to connect industries in cluster 2 & 3 to the 300 KLD STP. Construction of 500 KLD STP in KIADB Land, Electronics City Phase 2