ASEM MINISTERIAL CONFERENCE on Energy Security Tensions and Opportunities of Energy Security in the Baltics Vytautas Naudužas 18 th of June, 2009 Brussels.

Similar presentations


Presentation on theme: "ASEM MINISTERIAL CONFERENCE on Energy Security Tensions and Opportunities of Energy Security in the Baltics Vytautas Naudužas 18 th of June, 2009 Brussels."— Presentation transcript:

1 ASEM MINISTERIAL CONFERENCE on Energy Security Tensions and Opportunities of Energy Security in the Baltics Vytautas Naudužas 18 th of June, 2009 Brussels

2 2009.06.182 POWER SYSTEMS IN EUROPE

3 2009.06.183 PLANNED PROJECTS NPP LNG terminals UGS Coal fired power plant Electricity lines & cables Gas pipelines

4 2009.06.184 MAJOR GENERATION FACILITIES IN BALTICS TPP – Thermal Power Plant CHP – Combined Heat and Power Station HPP – Hydro Power Plant HPSP – Hydro Pumped Storage Plant

5 2009.06.185 Krievija Ukraina Baltkrievija Polija Lietuva Latvija Igaunija Somija Zviedrija NORDEL Russia Ukraine Belorus Poland Czech Germany Lithuania Latvia Estonia Finland Norway Denmark Sweden Integrated Baltic and CIS energy system NORDEL ESTLINK 350 MW 12.2006 Total produc- tion Total consumption (+) Exp. (-) Imp. LT14,0112,641,37 LV4,126,57-2,45 EE8,447,121,32 ∑26,5726,330,24 2007 (in TWh) UCTE/ CENTRAL Europe

6 2009.06.186 Krievija Ukraina Baltkrievija Polija Čehija Vācija Lietuva Latvija Igaunija Somija Norvēģija Dānija Zviedrija NORDEL Russia Ukraine Belorus Poland Czech Germany Lithuania Latvia Estonia Finland Norway Dānija Sweden Integrated Baltic and CIS energy system NORDEL ESTLINK 350 MW 12.2006 Lithuania – Sweden 1000 MW Lithuania – Poland 1000 MW Produc- tion Consumption (+) Exp. (-) Imp. LT10,9911,50-0,51 LV4,677,47-2,80 EE8,488,030,45 ∑24,1427 2010 UCTE/ CENTRAL Europe -2.60 Import in 2015 → New NPP Capacity 1500 MW (3000 MW) Annual production 11 TWh (22 TWh) 5 TWh (in TWh) Capacity 400 MW Coal-fired power plant Capacity 400 MW CCGT unit

7 2009.06.187 PRIORITY PROJECTS - LITHUANIA (1) Electricity Networks ∑ (1)1764 M€  Lithuania – Poland electricity interconnection (1000 MW)237 M€ Additional network strengthening466 M€  Lithuania – Sweden electricity interconnection (1000 MW)700 M€  Reconstruction of internal electricity grid361 M€

8 2009.06.188 PRIORITY PROJECTS - LITHUANIA (2) Electricity Generation ∑ (1 +2)10 734 M€  New CCGT (400 MW)360 M€  New gas-fired co-generation power plants (total 250 MW)360 M€  Modernization of Kruonis HPSP (2 units)250 M€  New Nuclear Power Plant (3400MW)8000 M€

9 2009.06.189 PRIORITY PROJECTS - LITHUANIA (3) Natural Gas ∑ (1+2+3)11524 M€  Liquefied Natural Gas Terminal, Klaipeda (2 Bill. m 3 / year) 340 M€  Underground Natural Gas Storage Syderiai, Lithuania (0.5 Bill. m 3 )150 M€  Gas pipeline to Poland Amber pipeline (5.5 Bill. m3/ year)300 M€

10 2009.06.1810 PRIORITY PROJECTS - LITHUANIA (4) Renewables and Energy Efficiency ∑ (1+2+3+4)27524 M€  New Renewable capacities for Electricity and Heat (to reach 23% target)1000 M€  Renovation of public buildings3000 M€  Housing modernization programme12000 M€

11 2009.06.1811 Does nuclear energy belong to a museum? Can we meet all our electricity needs with renewables?

12 2009.06.1812 No chance without Nuclear !

13 2009.06.1813 ASIA-EUROPE TRANSPORT DEVELOPMENT FORUM The First ASEM Transport Ministers’ Meeting 19-20 October 2009, Vilnius Ministry of Transport and Communications of the Republic of Lithuania

14 Thank You for your kind attention! www.urm.lt Vytautas Naudužas Tel.: +370 5 236 2961 Fax: +370 5 236 2984 E-mail: vytautas.nauduzas@urm.lt