1 Problems Contractors Face in Regards to Tack. David Branscome Jr. Operations Branscome Paving Company 1

2 Effects on Tack Due to Short Time Frame Reduced hours of actual paving lay down time Reduced hours of actual paving lay down time Keeping quality while trying to get the most done Keeping quality while trying to get the most done 2

3 Reduced Hours Reduced Hours Primary Routes 4 hours of actual lay down time Secondary Routes 5 hours of actual lay down time 3

4 Trying to get the most done Gathered together at the joint Minimizing traffic by a short work zone Multitude of equipment and vehicles - Contractor/Inspect or 4

5 Trying to get the most done Mill and Fill Project Two Operations in same Short Time Frame Added Congestion in Work Zone 5

6 Trying to get the most done Tack Truck/Vacuum Truck are having to maneuver resulting in inconsistencies “Clean Surfaces” Consistent Application Rate 6

7 Trying to Get the Most Done Milled Surfaces Performance Milling Peeling and Scabbing Could be reduced by going deeper when caught early enough Going 1/4” Deeper would give you that bond of a milled surface in all areas 7

8 Night Time High Profile Work Being Completed at Night 8

9 Night Time Paving Low Visibility Tacking in the dark Making sure the surface is clean at night 9

10 Comments Other Problems Contractors FaceOther Problems Contractors Face Questions?Questions? 10

11 Thank You David Branscome Jr Operations Branscome Paving Company 11