HQ02 TEST STATUS April 4, 2013 FERMILAB. Test status  Magnet delivery to FermilabApr. 02  SG checkoutApr. 04  LE & RE interface plate mounting Apr.

Similar presentations


Presentation on theme: "HQ02 TEST STATUS April 4, 2013 FERMILAB. Test status  Magnet delivery to FermilabApr. 02  SG checkoutApr. 04  LE & RE interface plate mounting Apr."— Presentation transcript:

1 HQ02 TEST STATUS April 4, 2013 FERMILAB

2 Test status  Magnet delivery to FermilabApr. 02  SG checkoutApr. 04  LE & RE interface plate mounting Apr. 04-05  Magnet delivery to MTFApr. 09 Test plan:  Still open for changes  Add the quench protection test plan  Add the magnetic measurement plan Work on detailed test plan and the magnet description document in progress Electrical data and SG data received 2

3 Test status: SG data checkout 3

4 Test status 4

5 5

6 6

7 Test Plan status  Strain Gauge readings with LBNL system – confirm no changes Apr. 04  Any seq R, hipots, impulse tests etc? Seq. R and Hipot will be done at VMTF  1.2..1.Did we confirm the protection heater circuits? Will be specified in the magnet description document  1.2..2.Are we going to connect the acoustic sensors? Yes if 10 kHz sampling rate is OK  60 mΩ dump resistor Symmetric grounding at Fermilab, 450 V max at 15 kA 7

8 Test Plan status (cont’d)  Any plans for cool-down rates? At CERN we put 50K max top to bottom, maybe it can be relaxed a little bit 100 K in LQS magnets  Which readings during cool-down (SG was set at 5 min) At Fermilab at 3 min  Magnetic measurements – again reference appropriate section  manual trips and heater provoked quenches at Imax ≤ 5 kA 8