Presentation is loading. Please wait.

Presentation is loading. Please wait.

WATER SYSTEM WORKSHOP February 27, 2012

Similar presentations


Presentation on theme: "WATER SYSTEM WORKSHOP February 27, 2012"— Presentation transcript:

1 WATER SYSTEM WORKSHOP February 27, 2012
WATER METER REPLACEMENT PROGRAM EAST AVENUE PUMPING STATION IMPROVEMENTS February 27, 2012

2 WATER METER REPLACEMENT PROGRAM
Background Project Approach / Reasoning Bid Analysis Recommendations Project Schedule

3 Past Meter Programs 1987 Meter Replacement Program
First meters installed 50 – 60 years ago Mechanical registers moved to outside of houses 1987 Meter Replacement Program Positive Displacement Meters Touch Read System Approximately 4 years to complete Work was by done by Public Works staff.

4

5 Water Accountability Water Recorded At East Avenue Pump Station
Water Recorded At Customer Meters Unaccounted For Water / Non-Revenue Water ~ 2011 – Non-Revenue Water = 149 million gallons

6 Takes into account age of mains and other information
No additional mandates to date IDNR – continue to make efforts

7 Different standard than the IDNR, does not estimate losses for water main breaks, gross amount
Auditors have made comments over the last five years Their standard / goal is 80%

8 Major Sources Of Non-Revenue Water
Real Losses Water main breaks Leaky joints in water mains Annual hydrant flushing Apparent Losses Inaccurate metering at the Pump Station Inaccurate metering at customer meters

9 Determining, Quantifying, and Fixing Major Sources of Unaccounted For Water
Water main breaks – Repair immediately, annual leak surveys Leaky joints in water mains – Water Main Replacement Program, Difficult to determine, Expensive Inaccurate metering at the Pump Station – Testing, Replacement Annual hydrant flushing – Accurate Recordings Inaccurate metering at customer meters – Testing, Replacement

10 Water Meter Accuracy Why do meters lose accuracy over time?
Mechanical meters ~ parts wear out Water “slips” by Most evident in low flows How to estimate? Remove and physically test meter Develop in field testing systems Industry standards for meter life and estimating

11 Meter Removal and Testing
Randomly tested 25 meters Meter manufacture year Measured at different flow rates Results …. 14 of the 25 meters (56%) did not meet AWWA accuracy standards Test does not provide total amount of water

12 SUGGESTED ACCURACY TEST FLOW RATES FOR COLD WATER METERS
DISPLACEMENT METERS (AWWA C700) Maximum Rate Intermediate Rate Minimum Rate Minimum (All Meters) (New and Rebuilt) (Repaired) Size In. Flow Rate gpm Accuracy Limits Percent Accuracy Limits Percent (min.) 5/8 15 2 1/4 95-101 90 5/8 x 3/4 3/4 25 3 1/2 1 40 4 1 1/2 50 8 100

13 Field Meter Testing New and Old Displacement Meters Tested
Results – Magnetic Meter recorded on average 3% more water

14 Industry Standards For Meter Replacement
American Water Works Association recommends replacement of water meters every 15 – 20 years Dependent on water quality Benchmark

15 Recommendation to Replace Meters
Village water meters – 22 to 25 years old Testing Results 56% of meters tested did not meet AWWA standards for accuracy Below IDNR’s target of 92% for unaccounted for water Below auditor’s target of 80% for unaccounted for water Equitable distribution of water fund costs Replace meters now will reduce future water losses

16 Water Meter Replacement Program Project Goals
Improve water accountability. Reduce water meter reading expenses through technology. Improve customer service. Reduce environmental impacts Water loss / Conservation Energy consumption for pumping water Energy consumption for meter reading New federal lead requirements Provide a long-term solution Obtain pricing information to accurately state project costs

17 Water Meter Replacement Program Specifications
Objectives Based on Automatic Meter Reading / Automated Metering Infrastructure Improved accuracy, reliability, and customer service Cost effective meter reading Flexibility for future “Turnkey” Project Centralized management and coordination Economies of scale Staff workload management Meter installation - Non-working hours

18 Request for Bids Bids requested based on Project Goals and Objectives in order to receive actual pricing information Bids received from HD Supply Waterworks, Inc. and Mueller Systems HD Supply Waterworks was determined to be the lowest, responsible bidder Bid amount - $1,373,200 Bid is based on FlexNet system and iPerl meter manufactured by Sensus, Inc.

19 Sensus FlexNet System Two-way communication
FCC licensing – 57 repeators

20 Sensus FlexNet Propagation Analysis
1. One antenna can cover the entire Village

21 Sensus iPerl Meter Magnetic Meter Reading Technology
Low flows – 0.03 gallons per minute ~ Leaking toilet No moving parts Alarms – Empty pipe condition, cut wire, leak detection

22 Sensus iPerl Meter

23 Total Estimated Project Cost with HD Supply Waterworks
Item Cost Base Bid- Includes all costs for supply and installation of meters (1” and smaller), meter interface units, and fixed base system components $1,373,200 Electrical Ground Straps $4,500 Large Meter Installations $48,768 Private Service Valve Repair / Installation (Reimbursable) $17,750 Total $1,444,218

24 Schedule Anticipated schedule
Install Fixed Base Equipment and Test – 3 months Install all water meters – 4,600 – 1 year

25 East Avenue Pumping Station Improvements

26 East Avenue Pumping Station Improvements
Background Summary of Report Findings Recommendations

27 Background 1983-84 - East Avenue Pump Station constructed
Pump station consists of Incoming water feed from McCook Five pumps - 2,000 gallons per minute, 2.8 million gallons per day 1.75 million gallon reservoir Re-chlorination Back-up generator Many components are nearing end of useful life ~ 30 years Study initiated to determine recommend repairs

28 Summary of Report Findings
Upgrade electronic control system (SCADA)[$120,000] Replace Automatic Transfer Switch and Motor Control Center [$75,000] Convert To A Liquid Chlorine System [$41,000] Valve Replacement and Installation [$58,000] Total of all recommend repairs [$500,000] Upgrade electronic control system (SCADA) – The technology that operates the station is from based on the technology at the time of the improvements in While the existing system is still functioning, replacement parts are becoming more difficult to find. Additionally a newer SCADA system will provide more information, require less operator attention and potentially reduce overtime. A new SCADA system would have the ability to automatically generate reports and log operational information. The estimated cost to upgrade the SCADA system is $120,000. Replace Automatic Transfer Switch and Motor Control Center – The existing electrical equipment used to power the building is obsolete, difficult to service and approaching the end of their service life. Baxter & Woodman recommends that these pieces of equipment be replaced in the next five years. The estimated cost to replace these pieces of equipment is $75,000. Convert To A Liquid Chlorine System – The conversion from gas to liquid chlorine would improve safety at the station as liquid chlorine is easier and safer to transport. Additionally replacing the existing gas chlorination system with liquid chlorine is anticipated to increase the life of the pumps. The estimated cost for this conversion is $41,000. Valve Replacement and Installation– Several valves are recommended for replacement or installation as part of the project. The first valve that is recommended to be installed is external to the station on East Avenue. Its purpose would be to isolate the existing water main on East Avenue to facilitate the continued operation of the pumping station in an emergency such as a main break on East Avenue. The second set of valves that are recommended to be replaced are the pump control valves. The replacement of these valves would improve the operation of the existing pumps by providing better control than the existing valves. Lastly, Baxter & Woodman recommends that a study be undertaken to assess the construction of a series of valves to bypass the East Avenue

29 Next Steps Recommend implementing identified improvements
Hire engineering firm Complete plans and specifications Develop detailed cost estimates Upgrade electronic control system (SCADA) – The technology that operates the station is from based on the technology at the time of the improvements in While the existing system is still functioning, replacement parts are becoming more difficult to find. Additionally a newer SCADA system will provide more information, require less operator attention and potentially reduce overtime. A new SCADA system would have the ability to automatically generate reports and log operational information. The estimated cost to upgrade the SCADA system is $120,000. Replace Automatic Transfer Switch and Motor Control Center – The existing electrical equipment used to power the building is obsolete, difficult to service and approaching the end of their service life. Baxter & Woodman recommends that these pieces of equipment be replaced in the next five years. The estimated cost to replace these pieces of equipment is $75,000. Convert To A Liquid Chlorine System – The conversion from gas to liquid chlorine would improve safety at the station as liquid chlorine is easier and safer to transport. Additionally replacing the existing gas chlorination system with liquid chlorine is anticipated to increase the life of the pumps. The estimated cost for this conversion is $41,000. Valve Replacement and Installation– Several valves are recommended for replacement or installation as part of the project. The first valve that is recommended to be installed is external to the station on East Avenue. Its purpose would be to isolate the existing water main on East Avenue to facilitate the continued operation of the pumping station in an emergency such as a main break on East Avenue. The second set of valves that are recommended to be replaced are the pump control valves. The replacement of these valves would improve the operation of the existing pumps by providing better control than the existing valves. Lastly, Baxter & Woodman recommends that a study be undertaken to assess the construction of a series of valves to bypass the East Avenue

30 Section 3 Water Financial Analysis

31 Section 4 Summary of Recommendations

32 Summary of Recommendations
Water Meter Replacement Program Replace water meters based on: Age of meters Testing and Analysis IDNR and Auditor Requirements Best practices Recommend HD Supply Waterworks as lowest responsible bidder using the Sensus, Inc. FlexNet and iPerl meter systems East Avenue Pump Station Improvements Hire engineering firm to complete detailed plans, specifications and cost estimates

33 Summary of Recommendations
Financing Issue $2.0 million alternate revenue bond Implement water rate increases as proposed in FY budget


Download ppt "WATER SYSTEM WORKSHOP February 27, 2012"

Similar presentations


Ads by Google