Presentation is loading. Please wait.

Presentation is loading. Please wait.

Upper Middle Road Grade Separation Construction Project Status Update February 2009.

Similar presentations


Presentation on theme: "Upper Middle Road Grade Separation Construction Project Status Update February 2009."— Presentation transcript:

1

2 Upper Middle Road Grade Separation Construction Project Status Update February 2009

3 The way it was.

4 The plan. The construction of the Upper Middle Road (UMR) Grade Separation, located at the Canadian National Railway crossing west of Appleby Line, is proceeding on schedule. The initial phase which included the road and rail detour construction opened October 6, 2008. The contractor is now working on the rail bridge foundations and piers as well as beginning the excavation for Upper Middle Road to pass under the bridge.

5 Where we are today!

6 North abutment. Note the texture on the form panel, this is what will be the impression left on the concrete when complete.

7 Centre piers. Each of two piers will support the two tracks when the bridge is complete.

8 South abutment footing. Heat being pumped to underside of footing to prevent frost.

9 Rock Excavation

10 Future Upper Middle Road Road profile, see also next slide.

11 Final Underpass Design Road profile, see also previous slide.

12 PhaseDescription of WorkTentative Timeline Construction Stage 2Bridge constructionSeptember 2008 to June 2009 Construction Stage 3Bridge Completion - Transfer CN tracks from temporary alignment to new bridge Early June 2009 5-day road closure required * Road works Transfer UMR from the detour to under bridge June to October 2009 Two 3-day road closures required * Construction Stage 4Road works, grading and landscapingOctober to November 2009 Construction Stage 5Project Completion Top layer of asphalt and project wrap up Spring 2010 * The exact dates and times will be confirmed as the work on the site progresses. Project Schedule:

13 Project Contact Bob Jurk Phone 905-335-7600 ext’n 7682 Email: jurkr@burlingotn.cajurkr@burlingotn.ca We would like to thank you for your co-operation throughout this project.


Download ppt "Upper Middle Road Grade Separation Construction Project Status Update February 2009."

Similar presentations


Ads by Google