Design of Beam-Column Connections in Steel Moment Frames
2
Observed Damage to Steel Moment Frames in the 1994 Northridge Earthquake
3
Observed Damage to Steel Moment Frames in the 1994 Northridge Earthquake
4
Typical Moment Frame Connection Detail Prior to 1994
5
The SAC Steel Project www.sacsteel.org
Funded by FEMA Over 6 years to 2000 $12m research funding Participated by 100s of practicing engineers, university researchers, contractors, materials suppliers, inspectors and building officials
6
Output of the SAC Steel Project
7
Prequalified Connection Detail by FEMA 350
8
Welded Unreinforced Flanges, Welded Web Connection (WUF-W)
9
Welded Unreinforced Flanges, Bolted Web Connection (WUF-B)
10
Recommended Weld Access Hole Detail
11
Typical Details of the Joint Panel Zone - Continuity Plate and Column Web Doubler Plate
12
Design Procedure of the WUF-B Connections
13
Beam-Colum Connection Recommended in GB50011-2001: WUF-B Connection – Beam Parallel to Column Web
Column through, joint panel zone in the column The 2 welds between the beam flanges and the columns flange must be CJP groove welds The beam web to column flange connection by high strength friction grip bolts via a column connection plate The weld between the column flange and the column connection plate shall be fillet weld both sides, >=5mm, and to develop the full shear strength of the connection plate. If the plate exceeds 16mm in thickness, use double bevel CJP groove welds Continuity plates and beam flanges equal thickness and equal strength
14
Beam-Colum Connection Recommended in GB : WUF-B Connection – Beam Perpendicular to Column Web
15
Design Process – Step 1 Design Connection for Bending
Mu >= 1.3Mp Mp = full plastic moment capacity of the plastic hinge of the beam (column through), or of the column (beam through) Mu = Bending moment resistance capacity of the joint connection provided by the flange connections and based on the design strength of connection If column through and if CJP groove welds are used to connect the beam flanges to the column, this overtrength requirement is considered met
16
Eurocode 8 Provisions
17
Design Process – Step 2 Design Connection for Shear
Vu >= 1.2(2Mp/ln)+VGb Mp = full plastic moment capacity of the plastic hinge of the beam (column through), or of the column (beam through) ln = clear span of beam VGb=(seismic weight UDL)ln/2, shear force at beam ends, determined by considering static equilibrium of the isolated beam under the seismic weight UDL Vu = Shear resistance capacity of the joint connection provided by the web connection and based on the design strength of connection
18
Design Process – Step 3 Calculate the Required Panel Zone Thickness and Determine if a Doubler Plate is Needed The shear stress in the panel zone bounded by the flanges of the column and the continuity plates shall meet t = y(Mpb1 + Mpb2)/Vp<=4fyv/3, as well as t = (Mb1 + Mb2)/Vp<=(4/3)fv/gRE Vp = hbhctp is the volume of the panel zone, tp is the panel zone thickness >=(hb + hc)/90 y = 0.6 for Seismic Resistance Class 3 and 4, 0.7 for Seismic Resistance Class 1 and 2 Mb1 and Mb2 = the factored bending moments of beams at the two sides of the joint panel gRE=0.75 fv = design shear strength of steel fyv = 0.58fy, is the yielding stress in shear of steel material Beam-Column Joint Panel Zone Doubler Plate if Required
19
Design Process – Step 4 Design the Shear Tab and the HSFG Bolts
To resist the connection shear force demand 1.3(2Mp/l) FEMA 350 recommends that the bolts should be designed for bearing Chinese code recommends the following for checking the shear resistance of HSFG bolts: Nvb = 0.75nAnbfub Nvb = shear resistance provided by one HSFG bolt n = number of cross sections resisting shear in the bolt Anb= net cross section area of bolt fub = tensile strength of bolt material