Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 1 The DECam Project Closeout, Action Items Hexapod Optical Lenses CCD Readout Filters Shutter 2008.

Similar presentations


Presentation on theme: "Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 1 The DECam Project Closeout, Action Items Hexapod Optical Lenses CCD Readout Filters Shutter 2008."— Presentation transcript:

1 Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 1 The DECam Project Closeout, Action Items Hexapod Optical Lenses CCD Readout Filters Shutter 2008 Nov 20

2 Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 2 Action Items 1.CTIO to generate plan for training for CTIO staff – who should be trained, what should they be trained on, and when are they available OPEN –Telescope simulator –Reassembly at CTIO –When stuff is packed in crates at UCL and Fermilab 2.Fermilab: Develop full list of pre-shipping tests and assumptions. OPEN. 3.Fermilab needs drawings of the NW service platform and F/8 handling fixtures. NOT Complete. –Fermilab to request from Tucson again with support from CTIO 2008 Nov 20

3 Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 3 Action Items 4.Decide if extra size of shipping container/rotation box for imager is in fact a problem. OPEN- to be checked again when shipping container are designed 5.Fermilab and CTIO to agree on final specifications for clean room and Coudé room layout, including the cranes/gantries in both areas and the cabling/cooling plan. OPEN – When does CTIO make the decision on cleanroom layout? 6.DECam team to provide a complete list of equipment required in the Coudé room for DECam assembly and testing OPEN 2008 Nov 20

4 Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 4 Action Items 7.CTIO & DECam team to perform ODH analysis & emergency procedures if cryo system fails.. OPEN 8.Specify needs for cube/tee dewars at CTIO; how many, where, funding, maintainer, readout systems, etc. OPEN 9.Determine setup time estimate for SISPI at CTIO. Determine whether shipping + setup for SISPI < shipping + unpacking for imager. If not, consider further doubling of hardware as mitigating schedule risk (currently only enough doubling to check TCS/DTS interfaces). OPEN 2008 Nov 20

5 Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 5 Action Items 7.Send layout of optical tests required at CTIO. DONE 11/18/08, –David and Roberto to stay in contact. 8.Develop the list of different mass configurations for which telescope balance will need to be maintained; use this to plan the various counterweights which will be required. OPEN 9.Make a video of Ken Schultz installing a DECam science package in the MCCDTV, using the proposed DECam installation procedure and provide to CTIO. DONE - will repeat with final design 2008 Nov 20

6 Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 6 Action Items 10.Sign off on conceptual design of F/8 handling CLOSED ANL will proceed with detail design of concept as presented at this meeting –Remaining open issues: a)Interference with existing platform – resolved? b)People access c)How to hold the inner ring at 125 deg. flip position d)Counterweight retraction is horizontal, not along the optical axis (4-7 deg diff), requiring compliance. e)Compliance on engaging kinematic mount. (Horizontal wraps - see cable section). f)CTIO to figure out how to reverse flip direction. 2008 Nov 20

7 Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 7 Action Items 11.Cables: OPEN a)Steve, Dave and Gale to determine if the cables be continuous from the Coude Room control racks and computers to the PF cage or should they have breaks to make installation easier (possible?) If so where? b)CTIO to document how will the cables be handled. Agree with Fermilab on a date for a review to determine the cables will not be damaged during the installation and how they will be tested after installation. c)CTIO to determine which if any can be installed and tested Before the shutdown for DECam installation? 2008 Nov 20

8 Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 8 Action Items 11.Cables continued: OPEN d)CTIO to specify all cables that will go into cage for F/8 and any monitoring that is not part of DECam. Fermilab (Steve) is the keeper of the complete list of all cables going to the PF cage. OPEN e)Fermilab and CTIO to agree on how 3-phase is delivered to cage when in Coudé room and at top end CLOSED some work to be done in April 2009 shutdown, Gale & Steve have it sorted out. Will be discussed at monthly installation meetings. (Gale needs consumption estimates.) f)CTIO to specify all cables that will go into cage for F/8 and any monitoring that is not part of DECam. Fermilab (Steve) is the keeper of the complete list of all cables going to the cage. OPEN 2008 Nov 20

9 Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 9 Action Items 12.Cooling Tubes: Fermilab and CTIO to agree on cooling tube route and where (if anywhere) will be hard pipe. OPEN –Move LN2 path to west side of telescope, design wrap & protection for DEC encoders. 13.Fermilab to design horizontal wrap for partial flip. OPEN 14.CTIO and DECam team to determine full list of what can be installed and tested BEFORE DECam arrives at CTIO in Dec. 2010. OPEN 2008 Nov 20

10 Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 10 Action Items 15.Barrel handling –Fermilab to determine if we need two sets of fixtures: OPEN - One for Fermilab and the Telescope Simulator test, one for UCL 16.Fermilab to determine assembly plan for cage, hexapod and barrel OPEN 17.CTIO to define plan for installation of DECam on the Blanco and keep DECam informed during the generation of the plans – OPEN Set-up regular meetings every four weeks to discuss progress –CTIO to decide what is needed - who will design and build required gear (e.g. handling cart, lifting fixture)? –Agree on a date with Fermilab for a design review –Agree on alignment reference surfaces 2008 Nov 20

11 Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 11 Action Items 18.Scaffolding for work at zenith when the cage is being installed on the spiders. –CTIO to design & build scaffolding –What, if anything, should be replicated at the telescope simulator? OPEN 19.CTIO and Fermilab to agree on conceptual plan for removing and installing the imager at the NW station OPEN 20.CTIO to define measurements required to align cage to telescope and specify (if needed) fiducials to be added to PF cage OPEN – must be complete SOON before completion of cage DESIGN. April 09 cage fabrication begins. 2008 Nov 20

12 Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 12 Action Items 21.Develop a plan for standby mode for DECam when F/8 is being used. Closed 11/18/08: everything should stay on. 22.CTIO to compare PF cage drawings to cage currently on the Blanco and provide information to Fermilab on where attachments to the spiders should be in the DECam Prime Focus cage. OPEN 23.Filter handling – produce a conceptual design for filter changing & operational plan for removal/reinstallation of FCM. OPEN. 2008 Nov 20

13 Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 13 DRAFT Agenda for Dec. 10 Integration meeting Brooke - Clean Room and Coude room Update –Schedule for building it, physical layout, cables, services… Gale and Steve: –update on electrical power distribution for DECam and plans for electrical shutdown during the April 09 shutdown Andy, Steve, Gale: Confirmation of cooling and cable routes CTIO: Status of plans for installation of DECam on the Blanco –Status of plans for alignment of DECam to primary mirror –Update on scaffolding and access ideas at Zenith for DECam installation. –What, if anything, should be replicated at the telescope simulator? –What could be installed before DECam arrives –Fermilab: list of different mass configurations for which telescope balance will need to be maintained. CTIO will use this to plan the various counterweights which will be required. Status of plans for training CTIO staff –when do we need to determine who should be trained on which parts of the project Status of detail drawing collection on the NW station. Topics for future meetings: –Barrel handling and cage assembly in the Coude room –Update on imager installation plans at NW station –Filter changer and filter installation plans 2008 Nov 20

14 Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 14 Extras Sparing and maintenance –Monsoon, RS to analyze failure scenario & sparing needs CTIO must find out what NEWFIRM needs by way of cabling & cryo. Collaborate on cryo feed & cable design & fab Collaborate on alignment mask design 2008 Nov 20

15 Andy says… Aw, Crap…. Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 152008 Nov 20