Presentation is loading. Please wait.

Presentation is loading. Please wait.

Status of ITER Cryo-distribution and Cryoline project

Similar presentations


Presentation on theme: "Status of ITER Cryo-distribution and Cryoline project"— Presentation transcript:

1 Status of ITER Cryo-distribution and Cryoline project
Oral Id - 9-O-4B-IT-16 Status of ITER Cryo-distribution and Cryoline project B Sarkar1, H Vaghela1, N Shah1, R Bhattacharya1, K Choukekar1, P Patel1, H Kapoor1, M Srinivasa1, H S Chang2, S Badgujar2 and E Monneret2 1ITER-India, Institute for Plasma Research, Bhat, Gandhinagar , India 2ITER Organization, Route de Vinon-sur-Verdon, CS , St. Paul Lez Durance Cedex, France B. Sarkar ITER-India, Institute for Plasma Research, Gandhinagar India

2 Organization Introduction to ITER and Cryo-distribution & Cryoline system Scope Project Requirements Risk analysis, Mitigation and Interface Management - Roadmap - Present Status Conclusions

3 Key word- ITER project (D-T Fusion)
D + T = He + n + energy Q = 10 50 MW MW Frencch Nuclear authority Fulfillment of Regulatory Obligation Stringent Requirements Establishment of Reliability ITER Project – Nuclear Establishment

4 Layout at ITER site – Specific to Cryogenic System

5 3-D Layout – Cryogenic System
Cryolines and warmlines located in Building 11, 52, 53 Area 53 Plant bridge

6 ITER Cryogenic System - Overview

7 Process Flow Diagram of ITER Cryoline and Cryo-distribution
11 CTBs of PF & CC coils 9 CTBs of TF coils 6 CTBs of CS coils 14 CVBs of Cryopumps (NB & Torus) 3 CVBs of magnet structures 1 CVBs of Thermal Shield CCB ACB-ST ACB-PF ACB-TF ACB-CS ACB-CP LHe Plant (3 Units) CTCB 80K He Loop (2 Units) Legends A: LHe Header C: SHe Supply Header D: 4.8 K Return Header E: 80 K Supply Header F: 100 K Return Header H: 50 K Supply Header Storage (4.5K LHe, 80K GHe 80K GN2, 300K GN2, 80K Quench Tank) LN2 Plant (2 Units) Process Flow Diagram of ITER Cryogenic System Indian Scope of Supply (Red Dotted line in the Figure)

8 ITER-Cryoline System Group X (Process Pipe: > 3) Group Y (Process Pipe: 1,2 or max. 3) Total length is ~ 5 km Sizes: DN 100 to DN1000 37 types of VJ lines Spread in Tokamak building, plant bridge, and cryoplant area Tight positional tolerances for installation ITER Cryolines

9 ITER-Cryo-distribution system
11/30/2011 5 ACBs, 1 CTCB, and 1 TCVBs Dynamic heat load Steady state heat load State of the art system ITER CD system = Nuclear heat load A Critical Component In Radiation Environment ITER (First of a kind development) JT-60SA Auxiliary Cold box CS model coil Existing m/c ATLAS SST-1 Internal Piping

10 Specific Layout of Cryoline inside Tokamak Building
[With only B1 and B2 level ] [With only B2 level ] Level L3 L3 Radiation Environment

11 Scope and Deliverables

12 Scope Functional scope
To distribute cold power to the clients (namely, magnets and cryo-pump) through supply of cryogens at proper temperature, pressure and flow To perform the safety functions in case of failure Project Life Cycle

13 Scope Preliminary Engineering Design Final Engineering Design
Manufacturing Factory Acceptance test Site installation Conducting site acceptance test and Integrated cold test

14 Scope (Physical Deliverables)
Sl. No. System Supplies Details 1. Cryo-distribution System (i) Auxiliary Cold Box (ACB) (ii) Thermal shield cooling system (iii) Cryo Terminal cold box (i) Five numbers ACB TF ACB PF & CC ACB CS ACB Structure ACB Cryopump (ii) One number (iii) One number 2. System of Cryolines (i) Helium at 4 K level – approximately 2 km (ii) Helium at 80 K level – approximately 2.5 km (iii) Nitrogen at 80 K level – approximately 0.6 km (i) cryolines from Helium plant to CTCB (ii) Cryolines (magnet and ryopump) from CTCB to ACBs (iii) TF, PF, CC, CS, STR cryolines from respective ACBs to CTBs (iv) CP Cryoline from ACB to CVB (v) Quench and relief line (vi) liquid nitrogen lines 3. Warm line Approximately 6 km All warm lines

15 Project Requirements

16 Acceptable heat load System of cryolines is 2.6 kW at 4.5 K, 6.2 kW at 80 K Cryo-distribution: 3 kW at 4.5 K and 3.9 kW at 80 K. Codes and standards ASME and EN/ISO - Project imposed system classifications Safety Importance Classification (SIC): Non Safety important, Safety relevant, SIC-2 Quality Classification (QC): QC 1, QC 2, QC 3 and QC 4 Seismic Classification (SC): Non-Seismic, SC2, SC1 (SF) Vacuum Quality Classification (VQC): VQC 4A/B Two events of seismic level (SL) spectrum: Cadarache site specific, SL1 and SL2.

17 - Site specific requirements:
(i) French Decree dated December 13, 199, amendments and (ii) French order of December 21, 1999 (iii) INB order of February 07, 2012 [3]. These regulatory requirements ensure proper classification, identification of category and evaluation of conformity of the pressure equipment in a nuclear establishment. SC1(SF): damage limit ‘normal’ as per code for Seismic Level-2, SC1(S) and SC(2): damage limit ‘faulted’ as per code for Seismic Level-2, SIC-II: Safety Important Class component which is part of secondary confinement boundary for nuclear establishment – stringent quality control and inspection by nuclear authority, QC1: 100% volumetric inspection, QC2: typically 20% volumetric inspection

18 Major codes and standards
Sl. No. Purpose Code 1. Construction EN 13480 2. Pipes ISO 1127 3. Welding ISO 5817, ISO 14731, ISO 14343, ISO 14344 4. Safety Devices EN 764, ISO 4126, EN 13648 5. Cryogenic valves EN 1626, EN , AD 2000, PED 97/23/EC 6. Non Destructive Testing ISO 17636, EN 12517, EN 473, ISO 17636

19 Loads & constraints considered for design of ITER cryolines
Cryoline Design Pressure (internal, external) Temperature (minimum, maximum) Seismic load Loads due to transportation and material handling Layout constraints (routing, location of supports, interfaces) External fields (magnetic, nuclear radiation) Flow induced vibrations, vibrations from interface equipment Self weight, supported weight Loss of Insulation Vacuum Snow load, wind load

20 Risk analysis and Mitigation

21 Risk Management Process
The risk management process followed the specific path Identification, Assessment, Impact Determination, Monitoring Reporting and Risk Closure

22 Reliability (Risk Assessment)
Likelihood of Occurrence (O) Impact or Consequence Negligible (1) Marginal (2) Significant (3) Critical (4) Crisis (5) Very Likely (5) Low (5) Medium (20) High (45) Very High (80) Very High (125) Likely (4) Low (4) Medium (16) High (36) High (64) Very High (100) Unlikely (3) Low (3) Medium (12) Medium (27) High (48) High (75) Very Unlikely (2) Low (2) Low (8) Medium (18) Medium (32) High (50) Not Credible (1) Low (1) Low (9) Medium (25) Correlation 𝑹= 𝑰 𝟐  𝑶 with four rank zones as low, medium, high and very high.

23 Risk Drivers First of its kind Design Management of establishing too many interfaces, Interface Load, Compatibility of material, Compliance with French nuclear safety, Space constraints and layout, Stringent Quality Requirements Regulatory requirement.

24 Prototyping – Mitigation by Design & Test
Two Prototype test Two Designs Design-2 OVJ: DN600 Q 0.98 W/m Q 3.73 W/m Process pipes CC, CD, C, CR ~ 4.5 K Process Pipe E, F ~ 80K Cold Circulator -2 Cold Circulator -1 PTCL-1 Design-1 OVJ: DN600 Q 0.88 W/m Q 4.33 W/m PTCL-2 Process pipes CC, CD, C, CR ~ 4.5 K Process Pipe E, F ~ 80K Design-1 OVJ: DN600 Q 0.88 W/m Q 4.33 W/m Design-2 Q 0.98 W/m Q 3.73 W/m

25 Result of risk assessment
CL – Cryoline CD – Cryo-distribution Risk Category – Technology, Interface, Safety, Site, Quality, Regulatory, Contamination

26 ZONE NO. OF RISKS 1 10 2 9 3 5 Xfmea®, ReliaSoft INITIAL SYSTEM CRITICALITY ZONE NO. OF RISKS 1 4 2 11 3 9 COLD Circulating Pumps (i) step-1: component level test (ii) step-2: prototype test of CCP in operating conditions, considering the overall cost factors. ZONE NO. OF RISKS 1 - 2 15 3 9

27 Roadmap Cryodistribution system: Highly process oriented (Industrial cold box approach) Cryolines & Warmlines: Mechanical integrity (Supply Chain management)

28 Include feedback in respective design Two Prototype test
Roadmap (Cryoline) Include feedback in respective design Two Prototype test Pre-Qualification Manufacturing of Prototype cryolines Award of contract Issue of tender to successful bidders Design of prototype cryolines (Two) by pre-qualified bidders and acceptance Warmlines – Public Tender Process pipes CC, CD, C, CR ~ 4.5 K Process Pipe E, F ~ 80K Design-1 OVJ: DN600 Q 0.88 W/m Q 4.33 W/m Design-2 Q 0.98 W/m Q 3.73 W/m

29 Roadmap (Cryo-distribution)
Include feedback in respective design Two Prototype test Award of contract Pre-Qualification Two Prototype design Issue of tender to successful bidders Award of contract to two industries Issue of tender to internationally well known bidders Cold Circulators Process pipes CC, CD, C, CR ~ 4.5 K Process Pipe E, F ~ 80K Design-1 OVJ: DN600 Q 0.88 W/m Q 4.33 W/m Design-2 Q 0.98 W/m Q 3.73 W/m

30 Present Status

31 Cryolines

32 Prototype Cryoline (Consortium of INOX India Limited & A S Scientific)
“Straight” section “T” section “Z” section Elbow section

33 Three sections of PTCL

34 Vacuum 4 X 10-7 without active pumping
Prototype cryolines made by M/s INOX India Limited & A S Scientific has been cold tested at 4.5 K /7-8 K The thermal stresses are with in limits The PTCL withstood the Break of Insulation Vacuum (No damage occurred – Safety test) Vacuum maintained within specified limit (order of 10-7 mbar) without active pumping The Plan Experimental Results Vacuum 4 X 10-7 without active pumping Vacuum 4 X 10-7 without active pumping Measurement of steady state heat load Time

35 Prototype Cryoline (ALAT)
Manufacturing is near completion

36 Cryo-distribution

37 CTCB – Preliminary design completed
Magnet and Cryo-pump Cryoline CL 1, 2, 3 Total Weight is approximately 20 Tons

38 Cold Circulating Pumps: Test ACB Highlights
TACB as manufactured 3D Model

39 Installation at JAEA

40 Qualification and Performance test for TWO cold circulators completed
Simulation of ITER magnet (TF, PF & CC, CS) and Cryo-pump scenarios 9-O-4B-4 - All operating parameters of ITER are satisfied - The performance test has been conclusive - The qualified circulator will be used for the cryo-distribution system

41 Cumulative Progress – Cryodistribution system
February

42 Cumulative progress – Group X Cryoline

43 Cumulative Progress- Group Y

44 Conclusions

45 The ITER Cryodistribution and Cryoline project of INDA is dynamically progressing to satisfy the overall ITER project objectives. After overcoming the initial teething problems both at technical and project management, the project took off, on the pathway of the strategy decided after the risk analysis. Interfaces remain as an issue for specific cases; however, it is being addressed on case to case basis, when the need arises. The project has completed an overall cumulative progress of approximately 29 % for Y-group of cryolines, 22 % for X-group of cryolines 14 % for Cryodistribution system in February 2016 as per INDA contractual schedule

46 Acknowledgements ITER-India, especially colleagues from the procurement and finance departments with specific gratitude to the Project Director, ITER-India and Director, IPR. Industrial partners, Consortium of M/s INOX India Limited & A. S. Scientific, M/s Air Liquide Advanced Technologies, M/s Linde Kryotechnik, M/s DeMaCo, M/s Barber Nichols Inc., M/s IHI, M/s Taiyo Nippon Sanso and JAEA

47 Welcome to the world of Fusion
Thanks & Welcome to the world of Fusion


Download ppt "Status of ITER Cryo-distribution and Cryoline project"

Similar presentations


Ads by Google