SPP.org 1. ICT Construction Plan Evaluation and Reliability Assessment Part 2 Entergy ICT Transmission Planning Summit July 29, 2008 Astor Crown Plaza.

Similar presentations


Presentation on theme: "SPP.org 1. ICT Construction Plan Evaluation and Reliability Assessment Part 2 Entergy ICT Transmission Planning Summit July 29, 2008 Astor Crown Plaza."— Presentation transcript:

1 SPP.org 1

2 ICT Construction Plan Evaluation and Reliability Assessment Part 2 Entergy ICT Transmission Planning Summit July 29, 2008 Astor Crown Plaza New Orleans, Louisiana

3 SPP.org 3 Project is not included in model Code for Base Plan and Construction Plan Projects Indicated on Maps BP08-036 = Project Number from 2008 Base Plan CP(2011) = 2008 Construction Plan and Expected In-Service Year DCP(2011) = 2009 Draft Construction Plan and In-Service Year Map Legend BP08-036 CP(2011) DCP(2011) Background Color Indicates Projects’ Inclusion In Case Project is in 2017 model

4 SPP.org 4

5 5

6 6

7 7 NA DCP(2013)

8 SPP.org 8

9 9

10 10

11 SPP.org 11

12 SPP.org 12

13 SPP.org 13

14 SPP.org 14

15 SPP.org 15

16 SPP.org 16

17 SPP.org 17

18 SPP.org 18

19 SPP.org 19

20 SPP.org 20 NA DCP(2013)

21 SPP.org 21

22 SPP.org 22 Other Areas These concerns seen in real-time may be relieved by projects in the Base Plan, Construction Plan or Draft Construction Plan. Hot Springs-Bismark 115kV FTLO El Dorado- Longwood 345kV (Base Plan Project) Liberty-Gillsberg 115kV FTLO Franklin-Bogalusa 500kV (Construction Plan Project with ISD 2009) Hartburg-Inland Orange 230kV FLTO Hartburg- Cypress 500kV (Draft Construction Plan Project with ISD 2010)

23 SPP.org 23 Base Plan Development Next Steps Stakeholder Comments Discuss Stakeholder Comments at September LTTIWG Present Draft Base Plan at October LTTIWG Finalize Base Plan and Post January 2009

24 SPP.org 24 Steve Purdy Lead Engineer, ICT Planning 501-614-3371 SPurdy@SPP.org SPurdy@SPP.org Jason Russell Engineer II, ICT Planning 501-614-3354 JRussell@SPP.org JRussell@SPP.org