Presentation is loading. Please wait.

Presentation is loading. Please wait.

Three Gate objectives are proposed in order to track project progress: –1. To formally approve the completion of a stage: To provide assurance that all.

Similar presentations


Presentation on theme: "Three Gate objectives are proposed in order to track project progress: –1. To formally approve the completion of a stage: To provide assurance that all."— Presentation transcript:

1 Three Gate objectives are proposed in order to track project progress: –1. To formally approve the completion of a stage: To provide assurance that all planned activities for a stage were completed and met the project plan within stated limits. –2. To ensure closure of any variance that required the involvement of management, ( that could not be resolved by the project team ). –3. To make or to formally document a decision about the next stage. Project Control Process - Gate review Objectives

2 Presentation - Approval of next Phase Completion of technical activities Gate N-1 Review Gate N Review Collection of project data Completion of technical products (GPCR) problem resolutions Project Control Process - Gating Overview

3 Project Control Process - Gates by IS Life-Cycle Account Management Account Management Initial Investigation Supplier Evaluation and Selection Installation, Adaptation, Interfacing, Integration, Acceptance & handover Launch & Operation Launch & Operation Initial Investigation and High Level Design Detailed Design, Developpment and Testing Gate 0Gate 1&2 Gate 1Gate 2 Gate 2a Gate 3 SALC RSD : Gates that require a formal gate review by Gate Review Committee : Gates that require an ISPO authorisation Gate 4

4 work completed as planned, with no significant variances, all mandatory products have been completed, and recommendation for next phase is approved. Else Project must stay at the current stage, bridge the gaps and gate again Project Control Process - Gate approved means

5 Project Control Process - IS Variance Policy “Variance Situation” - when the project actual or the projected data, exceeds an approved variance limit. Progress Variance: Is apparent when technical and management products identified on GPCR are: Absent, Of very low quality, Not Reviewed/Signed-off or Late. Quality Variance: Is Apparent when major non-conformance are detected, when IS life-cycle is not followed, Significant I/R are reported by the independent UAT. Effort Variance: Is apparent when either too many/too little effort is reported (TRS). Scope Variance: Is apparent when scope is decreased by the project team to meet a date. Opposite can also appear “ creeping requirements”. Cost Variance: Is apparent when % spent (expense or capital) is approaching limit and no immediate action is foreseen to submit an amendment to CRB

6 Project Control Process - Gate Review Presentation “Standard Presentation” - Gate review presentations must all follow the standard. Slide 1 - Project Name, Number, Title, Current Stage, Gate # review, project manager name, Customer name Slide 2 - HR (IS, Users, External) current, next stage, deviations Slide 3 - Schedule, current, next stage, deviations Slide 4 - Costs (Capital, Expenses), current, next stage, deviations Slide 5 - Architecture & technology diagram Slide 6 - GPCR completed/outstanding items, current, next stage Slide 7 - project Risks and recommendation to proceed


Download ppt "Three Gate objectives are proposed in order to track project progress: –1. To formally approve the completion of a stage: To provide assurance that all."

Similar presentations


Ads by Google