Sharing My Story David Arakawa, Federal Project Director SNS Instruments Next-Generation (SING) Project DOE Oak Ridge National Laboratory Site Office 1.

Slides:



Advertisements
Similar presentations
Will Minter Division Director, Asset Management & Small Business Programs Office November 15, 2006 ITER Project.
Advertisements

U.S. Department of Energy’s Office of Science Archived File The file below has been archived for historical reference purposes only. The content and links.
Briefing to the Commission to Review the Effectiveness of the National Energy Laboratories (CRENEL) Joseph McBrearty, Deputy Director for Field Operations.
1 EM Update and Perspective David Huizenga Senior Advisor for Environmental Management 2012 DOE Project Management Workshop April 3, 2012.
Oak Ridge National Laboratory Mentor-Protégé Program Business Success Stories Presented by Cassandra McGee Stuart ORNL Small Business Programs Office May.
Dean Fortin – Massachusetts WIC 23 July System Testing Objectives  Verify hardware  Verify software  Verify hardware/software interaction  Verify.
DOE OFFICE OF INDIAN ENERGY Step 4: Project Implementation 1.
DOING BUSINESS IN THE MIDDLE EAST STRATEGIES, CHALLENGES AND RISKS OPPORTUNITIES.
Contractor Assurance Discussion Forrestal Building Washington, D.C. December 14, 2011.
BERAC Charge A recognized strength of the Office of Science, and BER is no exception, is the development of tools and technologies that enable science.
U.S. Department of Energy’s Office of Science Dr. Raymond Orbach February 25, 2003 Briefing for the Basic Energy Sciences Advisory Committee FY04 Budget.
Month Year Working together to achieve your desired outcomes, by delivering service excellence. Building Engineering Solutions for the optimisation of.
The Systems Engineer’s Role in Project Success J. H Rothenberg May 1, 2006.
TRU Waste Processing Center Culture and Successful Implementation of an ISO Certified Environmental Management System Presented at the DOE ISM Conference.
Energy Champions Training Module 1.5 Energy Champion Program Overview.
ORNL is managed by UT-Battelle for the US Department of Energy ORNL Project Management David Arakawa – DOE FPD Suzanne Herron - CPM Jack Stellern – CPM.
Pre-Project Planning Lessons from the Construction Industry Institute Construction Industry Institute Michael Davis, P. Eng, PMP Ontario Power Generation.
Global Project Management
A New Paradigm for Utility Coordination Kenny Franklin INDOT Director of Utilities and Railroads.
Privileged and Confidential Strategic Approach to Asset Management Presented to October Urban Water Council Regional Seminar.
Managing a Training Program Why train? Who will attend the training? What are the learning objectives? Strategies? Coverage? How will the training program.
ORF 1 Performance Management Presentation Team Members: Division of Policy and Program Assessment Farhad Memarzadeh, Sheri Bernstein, Reza Jafari, Robert.
9 Closing the Project Teaching Strategies
FY2010 PEMP Notable Outcomes October 15, FRA, LLC Board of Directors 10/15-16/2009 Office of Quality and Best Practices Performance Evaluation Management.
Merging university departments, schools and faculties Piers Brissenden School of Health Sciences University of South Australia.
2013 ADC INSTALLATION INNOVATION FORUM | PAGE 2 Asset Management January 15, 2013.
Project Management: York University Computer Science and Technology Dept Date: Nov 1, 2006 By: Steven Gallant, VP, Project Management Date: Nov 8, 2006.
Contacts Enecto - Turning web visits into business InterAction User Group David Botros Senior Account Manager Tel: +44 (0) Mob: +44.
Basic Energy Sciences Advisory Committee Meeting March 3, 2010 Overview of the DOE Office of Science Graduate Fellowship Program Julie Carruthers, Ph.D.
We do...  Project Planning, And develop...  Asset Management strategies bkproject s offers infrastructure planning and asset management consulting services.
Legacy Management Strategic Plan 2010 David Geiser Director, U.S. Department of Energy (DOE or Department) Office of Legacy Management (LM) November 2010.
1 presented to National Governors Association Federal Facilities Task Force National Transportation Program: A Policy Perspective J. Kent Hancock, Director.
© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.
EARTO – working group on quality issues – 2 nd session Anneli Karttunen, Quality Manager VTT Technical Research Centre of Finland This presentation.
A New Paradigm for Utility Coordination Kenny Franklin INDOT Director of Utilities and Railroads.
Fundamentals of Project Management
Your Financial Work Defense Finance and Accounting Service DFAS Transformation Update March 2003.
More Construction for the Money “Back to the Future” Jim Porter 2004 Recipient Carroll H. Dunn Award of Excellence.
Phoenix Convention Center Phoenix, Arizona Mission, Culture, and Sustainable Change Institutional Change Aligning with an Organizational Mission to Drive.
Business Plan.
Acquisition and Contract Management Update Jay Rhoderick Associate Deputy Assistant Secretary for Tank Waste and Nuclear Material AtomEco-2012.
© 2012 Cengage Learning. All Rights Reserved. This edition is intended for use outside of the U.S. only, with content that may be different from the U.S.
School of something FACULTY OF OTHER Consolidation Workshop Roles of University Leaders; opportunities and challenges; support Michael Arthur, Vice Chancellor.
PRESENTED AT THE 30 th NATIONAL ENERGY AND ENVIRONMENTAL CONFERENCE – LAS VEGAS NEVADA SEPT 2003 Robert J Nespeco P.E. Director, Quality Assurance MTA.
Thailand’s Preparation for Starting a Nuclear Power Program Mr. Pricha Karasuddhi Technical Advisor Nuclear Power Program Development Office(NPPDO) Ministry.
ENTERPRISE RESOURCE PLANNING
Carl G. Ray Program Executive Small Business Innovation Research Small Business Technology Transfer SBIRSBIR To increase small business participation.
Company implications of EEOP Verification ASMC Board 2 March 2010.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Procurement David Dale Procurement Manager NSLS-II Project Project Advisory Committee November 20, 2007.
Using an Environmental Management System for Managing DOE’s Legacy DOE Order Workshop 26 February, 2003.
Strength Through Science BESAC Presentation Office of Science Dr. James Decker Acting Director, Office of Science U.S. Department of Energy August 2, 2001.
Pre-Decisional Involvement
1 OFFICE OF ADVANCED SCIENTIFIC COMPUTING RESEARCH The NERSC Center --From A DOE Program Manager’s Perspective-- A Presentation to the NERSC Users Group.
O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY The Spallation Neutron Source Project: Update T. E. Mason Oak Ridge National Laboratory.
Oak Ridge National Laboratory Ted Fox Deputy Associate Laboratory Director Energy and Engineering Directorate March 19, 2009.
Transformation of a National Laboratory: ISMS Component Beth Streeper ISMS Program Manager Integrated Safety Management Workshop 2007 Brookhaven National.
VP Quarterly Report on Strategies Q3– February 2, 2016 Robbie Peters, Vice President, Financial Services & Chief Financial Officer Vision: Healthy people,
Safety Culture Improvement Doug Fleming Update to CAC January 26, 2012.
1 Ventilation Systems Capital Asset Projects Safety Significant Confinement Ventilation System (15-D-411) Exhaust Shaft (15-D-412) Ronald.
Managed by UT-Battelle for the Department of Energy Presented at: The Oak Ridge Regional Emergency Management Forum David Milan Manager, Emergency Management.
Office of Baseline Change Proposal (BCP) Approval or Brief Presented by: Draft version Jun 16, 2015.
Office of Critical Decision-1 Approve Alternative Selection & Cost Range or Brief Presented by:
Redmond Police Functional Plan Update Council Study Session January 14, 2014.
National Institutes of Health U.S. Department of Health and Human Services Planning for a Team Science Evaluation ∞ NIEHS: Children’s Health Exposure Analysis.
1 Getting to Green at the Department of Energy Progress on OMB’s Environmental Sustainability Scorecard Andy Lawrence Director, Office of Nuclear Safety,
NNSA Project Reviews NNSA Office of Project Analysis, Oversight, and Review (NA-APM-1.1) June 7, 2017 Dwight Henderson, Director
The Federal Oversight and Contractor Assurance System Directives Safety Culture Improvement Panel Meeting September 7, 2016 Patricia.
Contractor Assurance Systems (CAS) Summit August 23, 2016
2018 EFCOG Safeguards & Security Working Group Annual Meeting
Preliminary Project Execution Plan
Presentation transcript:

Sharing My Story David Arakawa, Federal Project Director SNS Instruments Next-Generation (SING) Project DOE Oak Ridge National Laboratory Site Office 1

Outline My Experience Office of Science’s (SC) Expectations Mentoring SING Project – Overview – “Opportunities” – Outcomes – Key Lessons Final Thoughts 2

Broad-based Experiences in DOE Programs and Projects Uranium Enrichment Science Programs Commercial Science Projects – Basic Energy Sciences – Nuclear Physics – Biological and Environmental Research – Laboratory Infrastructure 3

Meeting SC’s Expectations Owner’s Representative Leadership (Accountability) Proactive Trust (but verify) Communicate (Keep Programs and AE Informed – No Surprises!) Mentoring 4

Mentored by SC and NE Program and Project Directors and Contractor Project Managers 5 – Interacting with the SNS FPD and project team – Observing and participating in Lehman reviews – Benefitted from opportunities provided by co-workers and managers

SNS Instruments Next Generation (SING) 1 Project 5 Best-in-Class Neutron Instruments $68.5M TPC 8 Years – Concept to Commissioning 6

SING “Opportunities” Contingency Management Integration with Operating Facility Tailoring Strategy Unique Risks (e.g. foreign procurements) 7

SING Outcomes Completed ahead of schedule (2 months) and under budget ($263K) Exceeded KPPs for all 5 instruments Worked safely Delivered capital asset 8

Key Lessons Established Project Management Process Effective Project Team Thorough Pre-Project Planning and Communication Excellent Project Team Effective Tailoring Strategy Useful Long Lead Procurements 9

Final Thoughts Seek Opportunities to Expand Your Experience Continue to Learn and Mentor Others Share Lessons to Accomplish Mission 10