ATF2 Software Review LAL 18-20 June 2008 Philip Bambade & Glen White ATF2 weekly meeting June 3 2008.

Slides:



Advertisements
Similar presentations
Brett Parker* BNL-SMD *For the ATF2 Superconducting Magnet Upgrade Collaboration Update on SC Magnets and Schedule.
Advertisements

ILCDR/CesrTA meeting Low Emittance Tuning 報告 K.Kubo.
Sha Bai, Philip Bambade, Glen White FJPPL – FKPPL ATF2 workshop LAL, 11~13 February, 2013 Orthogonality of beam waist corrections in the presence of IPBSM.
Tests of DFS and WFS at ATF2 Andrea Latina (CERN), Jochem Snuverink (RHUL), Nuria Fuster (IFIC) 18 th ATF2 Project Meeting – Feb – LAPP, Annecy.
Coupling Correction in ATF2 EXT 7 th ATF2 Project Meeting, december 2008 C.Rimbault, LAL Orsay.
Emittance Measurement Simulations in the ATF Extraction Line Anthony Scarfe The Cockcroft Institute.
Optics for Skew Correction and Emittance Measurement Leo Jenner This talk is going to look familiar if you were at the recent LC-ABD meeting in Manchester…
Status of ATF2 final focus prototype ( emphasizing French involvement ) Collaboration with China : Jie GAO, Sha BAI (IHEP, Beijing) Philip Bambade LAL-Orsay.
1 ATF2 Tuning and its application to ILC and CLIC FFS/IR region ASTeC and MAN : working together on tuning methods for the ATF2 and ILC IR/extraction design.
Status of very high priority beam tuning software Special ATF2 project meeting, Korea, 1 st October 2008 Cécile Rimbault, on behalf of High Priority task.
1 Proposal for a Multi-Optical Transition Radiation System in ATF2 A. Faus-Golfe, D. McCormick IFIC – SLAC 11 June th TB/SGC Meeting.
ATF2 Javier Resta Lopez (JAI, Oxford University) for the FONT project group 5th ATF2 project meeting, KEK December 19-21, 2007.
12/12/04 1 Stewart Boogert (UCL) Second Mini-workshop Nano project at ATF UK plans for Energy spectrometer studies University College London Stewart Boogert.
Trajectory Correction and Tuning James Jones Anthony Scarfe.
ATF2 commissioning in Autumn 2009 for discussion Philip Bambade LAL & KEK LCWS09 BDS session Albuquerque, New Mexico October 1, 2009 on behalf of the commissioning.
Relative Error on Parameter Pessimistic Estimate Optimistic Estimate β function at the LW 3% 1% LW readout error 2% 1% Laser spot waist 10% Laser Pointing.
ATF2 optics … 1 3 rd Mini-Workshop on Nano Project at ATF ATF2 optics, tuning method and tolerances of initial alignment, magnets, power supplies etc.
March 7, 2007 LET Issues (Cai/Kubo/Zisman) Global Design Effort 1 Low-Emittance Tuning Issues and Plans Yunhai Cai, Kiyoshi Kubo and Michael S. Zisman.
ATF2 Tuning Updates Glen White, SLAC Sept
Fifth ATF2 Project Meeting, dec. 2007, KEK, Japan Emittance measurements with multiple wire-scanners and quadrupole scans in ATF EXT C. Rimbault,
Continuous Run in May K.Kubo. Final Focus Test Line IP; ~40 nm beam ATF Linac (1.3 GeV) ATF Damping Ring (140 m) Extraction Line Photo-cathode.
Summary of Commissioning and Tuning session Philip Bambade LAL-Orsay 5 th ATF2 project meeting KEK, 21 December 2007.
ATF2 beam commissioning status and beam time request Toshiyuki Okugi 2008 / 11 / 12 ATF2 Commissioning Meeting.
ILC BDS Static Beam-Based Alignment and Tuning Glen White SLAC 1.Aims. 2.Error parameters and other assumptions. 3.Overview of alignment and tuning procedure.
Mark Woodley, SLACATF2 Project March 20-21, Summary of Tuning, Corrections, and Commissioning.
Intermediate  configurations at the IP for commissioning and optimization Sha BAI IHEP/LAL Philip BAMBADE LAL.
Highlights and discussion at LAL FKPPL & FJPPL “Toshiko Yuasa” workshop Philip Bambade Laboratoire de l’Accélérateur Linéaire Université Paris 11, Orsay,
Technical Board “issues” Philip Bambade Laboratoire de l’Accélérateur Linéaire Université Paris 11, Orsay, France ATF2 Technical Review KEK, 3-4 April.
8 th Meeting of the ATF TB/SGC 11 June Hardware Status Fast Kicker – FID pulsers have had a reliability problem: this appears to have been solved.
ATF2 Commissioning Toshiyuki Okugi 2008 / 7 /9 ATF2 beam commissioning meeting, KEK.
Low emittance tuning in ATF Damping Ring - Experience and plan Sendai GDE Meeting Kiyoshi Kubo.
Vertical Emittance Tuning at the Australian Synchrotron Light Source Rohan Dowd Presented by Eugene Tan.
1 H. Hayano ATF Status June/2004 H. Hayano ATF: emittance status beam study status plan nm-project collaboration & plan ATF review 6/17/2004.
First analysis results of EXT MW0-4 X,Y,- 10,-10 wire-size measurements to reconstruct the 4D betatron phase-space.
J. Brossard, C. Rimbault a P. Bambade LAL / / 8-9 nov LAL 1 Exercising emittance measurements in the ATF EXT line Upgrade.
ATF2 Tuning Summary Nov & Dec 2010 Glen White, SLAC 11 th ATF2 Project Meeting, SLAC Jan
ATF2 Software Review LAL June SHORT SUMMARY - Philip Bambade ATF2 weekly meeting July
Upcoming Shift Work at ATF (November 26 – December 21, 2007) and Remote Participation from SLAC ATF training shifts proposal Rob Appleby (contact person,
Status of ATF2 final focus prototype ( emphasizing French involvement ) Philip Bambade LAL-Orsay Andrea Jérémie et al. (LAPP) Marc Verderi & Hayg Guler.
Task Lists of ATF2 commissioning Toshiyuki Okugi ATF2 Project Meeting 12 / 17 / 2008.
Beam Based Optics Measurements CTF3 Collaboration meeting CERN Yu-Chiu Chao, TJNAF.
Emittance measurements with multiple wire-scanners and quadrupole scans in ATF EXT C. Rimbault, Brossard, P. Bambade (LAL) Main goal : - Try to improve.
Summary of Tuning, Corrections, and Commissioning ( Short summary of ATF2 meeting at SLAC in March 2007 ) and Hardware Issues for beam Tuning Toshiyuki.
Simulation of the α, dispersion, coupling and β multiknobs in large β optics Sha Bai, Philip Bambade, Benoit Bolzon, Javier Resta Lopez
Status of EXT coupling measurement analysis 9 th ATF2 project meeting C.Rimbault (LAL) S. Kuroda, T. Tauchi, N. Terunuma (KEK), G. White, M. Woodley (SLAC)
Michael Röhrs On-crest slice emittance measurements Michael Roehrs.
For discussion of ATF2 beam time requests SLAC team October 1, 2008.
Status and plan of Beta-matching in Extraction line Kiyoshi Kubo.
2nd ATF2 Project Meeting (May 30, 2006)M. Woodley [SLAC]1 ATF2 Layout/Optics (v3.3) nBPM (SLAC) nBPM (KEK) FONT Compton / laserwire ODR Existing ATF Extraction.
Technical Board Summary Preliminary Philip Bambade Laboratoire de l’Accélérateur Linéaire Université Paris 11, Orsay, France ATF2 project meeting, Technical.
ATF2 Software tasks: - EXT Bunch-Bunch FB - IP Bunch-Bunch FB - FB Integration Status and plans Javier Resta-Lopez JAI, Oxford University ATF2 commissioning.
Status of ATF2 linear collider focus prototype emphasizing France-China joint contributions Philip Bambade Laboratoire de l’Accélérateur Linéaire Université.
4 th ATF2 Project Meeting, 31 May 2007 A. Seryi 1 Summary of SLAC simulation study of emittance growth in the ATF extraction line SLAC team: J. Amann,
Simulation for Lower emittance in ATF Damping Ring Kiyoshi Kubo Similar talk in DR WS in Frascati, May 2007 Most simulations were done several.
IP Tuning Task Updates Glen White, SLAC January
ATF2 Status N.Terunuma, KEK
FACET Tests Update A. Latina, J. Pfingstner, D. Schulte,
Task 9.4 Beam Delivery System CERN, 27-Mar /3/2009
ILC BDS Alignment, Tuning and Feedback Studies
Measurements and analysis of beam parameters at post-IP wire-scanner
Expected hardware status and Priority of the commissioning task
Updated coupling study-2 from 12 March 08 measurements
Emittance Dilution and Preservation in the ILC RTML
Transverse Beam Jitter Propagation in Multi-bunch Operation at ATF2
Beam-based alignment measurements
RTML and Main Linac Design (2.6.1 and 2.7.1)
Beam Optics Set-Up at SLAC End Station A
3rd ATF2 Project Meeting, December 18-20, 2006
Emittance Diagnostics
Emittance Diagnostics
Presentation transcript:

ATF2 Software Review LAL June 2008 Philip Bambade & Glen White ATF2 weekly meeting June

Overall objectives Review requirements for ATF2 control & tuning software Prioritise & organise software work as tasks within ATF2 collaboration Main sessions Introduction / Overview of project and commissioning plan (half day) Review of simulation work (half day) Control software development Planning of tuning software & controls interface (full day) Flight Simulator hand’s-on teach-in session (half day) Organisation and management of software tasks (half day) Participants ( that we know of… ) LAL & LAPP : Bambade, Bai, Brossard, Renier, Rimbault, White, Bolzon, Jérémie KEK : Kuroda, Okugi, Tauchi MAN + RHUL + UCL : Boogert, Gournaris, Scarfe CERN ? : Tomas & Zimmermann (1 day) + Webex (Oxford, CI, IFIC, SLAC, KEK,… )

Conclusions and prospects ATF EXT projected vertical emittance consistently measured  3 times DR values at e - /bunch Quad scans more precise than multi-wire technique to measure projected X and Y emittances & Twiss parameters, due to small betatron phase separation between wire scanners in present EXT line – the latter should improve in new ATF2 EXT line thanks to better optical design. Identified reason for vertical projected emittance growth : QM7 DR quad, traversed off-axis by EXT beam, can induce x-y coupling through the sextupole field component in the presence of a vertical offset. However modeling and beam size measurements at downstream OTR suggests it cannot be sole explanation. Spurious  y at OTR leaking out from DR must also be controlled not to mask effects. Full 4D beam matrix measurements required to determine linear coupling source(s) & correction. Set of normal and skew quad scans are investigated, combining X, Y and 10° wire measurements  may be more precise & reliable than traditional multi-wire 4D technique in which determination suffers from unfavorable error propagation. Significant phase-space variations are found at EXT input on successive shifts :  time-consuming pre-tuning needed before any sensible investigations in EXT line are performed,  need to optimize shift planning in this respect + work on reproducibility of DR optical tuning. Reliable control of apparent vertical emittance growth from x-y coupling in ATF2 EXT line will require precise Twiss parameter, dispersion & trajectory control on time-scale of typically 1 shift, in addition to x-y coupling correction ability further downstream. Automation of procedures essential for speed & reliability  develop all tools in “Flight Simulator”. More efficient collaborative multi-partner / site team work  better defined procedures and information flow during and after shifts, with improved sharing of data & algorithms : check-lists and measurement programs, common data areas, on-call experts for specialist topics & questions, standardized scheme to upload e-log book & shift reports, respectively during and after shifts. Dedicated instrumentation  investigate adding 2D profile measurements based on OTR stations near each wire-scanners in ATF2 EXT line, for multiple & fast, and measurements.