SNuMI: WBS 1.1 Booster Upgrades Eric Prebys $642K FY06$ (no contingency, no G&A) xx% contingency Main Injector & Recycler BNB NuMI Tunnel Booster Ring.

Slides:



Advertisements
Similar presentations
ANU Cooling Systems Karl Williams Fermilab Accelerator Division CD-2/3a DOE Review of NO A October 23-25, 2007.
Advertisements

Chris Smith Booster RF Cavity Upgrade Contents: The Booster Existing RF Cavities Why Upgrade? New Cavities Prototype Plans University Involvement Prototype.
1 Proton Upgrades at Fermilab Robert Zwaska Fermilab March 12, 2007 Midwest Accelerator Physics Collaboration Meeting Indiana University Cyclotron Facility.
Proton Source Workshop December 7 & 8, 2010 John Reid December 8, 2010.
Re-commissioning the Recycler Storage Ring at Fermilab Martin Murphy, Fermilab Presented August 10, 2012 at SLAC National Laboratory for the Workshop on.
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
Proton Improvement Plan Bob Zwaska August 3, 2015 All-Experimenters Meeting.
Proton Plans at Fermilab Robert Zwaska - Fermilab Science and Engineering at Henderson- DUSEL Capstone Workshop Stony Brook University May 5, 2006 Outline.
SNuMI: Phase I & Phase II Nancy Grossman Phase I: $33.4M FY06$ (no contingency, no G&A) 41% contingency Phase II: $53.7M FY06$ (no contingency, no G&A)
F MI High Power Operation and Future Plans Ioanis Kourbanis (presented by Bruce Brown) HB2008 August 25, 2008.
Getting Beam to NuMI (It’s a worry!) Peter Kasper.
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
PIP Update Feb 20 th Agenda Summary Update – Current Activities/Updates – Startup Schedule Highlights – Upcoming Talks, Reports, Meetings Updates/Talks:
All Experimenters Meeting PIP Report William Pellico on behalf of PIP team 4/7/2013.
Mu2e WBS 2 Accelerator Progress Report Mu2e WGM 6/15/2011 Steve Werkema L2 Manager for the Accelerator Systems.
SNuMI (>1MW) SNuMI 1 Motivations for SNuMI The neutrino experimental program for the next decade –NOνA (long baseline νμ→νe search) –MINERνA (Main Injector.
Proton Plan Director’s Review 8/15/06 Prebys 2006 Shutdown Eric Prebys, FNAL Accelerator Division.
AAC February 4-6, 2003 Protons on Target Ioanis Kourbanis MI/Beams.
F Project X Overview Dave McGinnis October 12, 2007.
Proton Planning Eric Prebys FNAL Accelerator Division.
Proton Improvement Plan William Pellico FRA Visiting Committee Meeting March 14-15, 2011.
Proton Study Meeting 4/19/05 Eric Prebys 1 Proton Plan Stage I Eric Prebys.
Recent RF Development at Fermilab Weiren Chou and Akira Takagi Fermilab, U.S.A. July 7, 2003 Presentation to the FFAG03 Workshop July 7-12, 2003, KEK.
F 1 MW Proton Beam for Neutrinos Dave McGinnis AAC Meeting May 10, 2006.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Diagnostics in the Fermilab Proton Source (Linac + Booster) Eric Prebys FNAL Beams Division.
F Proton Plan Eric Prebys and Ioanis Kourbanis, FNAL Accelerator Division.
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
Accelerator Issues Fermilab Antiproton Experiment Keith Gollwitzer Antiproton Source Department Accelerator Division Fermilab.
PIP Budget Codes Budget FY12 Updates October 19, 2011 PIP Meeting.
Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Project X RD&D Plan Beam Transfer Line and Recycler Injection David Johnson AAC Meeting February 3, 2009.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
Mu2e Mu2e CD-2 Review Template Eric Prebys Extinction October 21-24, 2014.
Proton Improvement Plan Overview Bob Webber July 13, 2011.
What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003.
Proton Planning – Major Projects, Schedule, Decisions, and Projections Eric Prebys FNAL Accelerator Division.
Doug Michael Sep. 16, GeV protons 1.9 second cycle time 4x10 13 protons/pulse 0.4 MW! Single turn extraction (10  s) 4x10 20 protons/year 700.
Proton Plan PMG 2/23/06 E Prebys 1 Proton Plan Status January Report Eric Prebys.
Proton Plan Expectations Eric Prebys AD/Proton Source.
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
PIP Update June 18 th Agenda Summary Update – Current Activities/Updates – Reid, Slabaugh.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Proton Plan PMG 2/22/07 E Prebys 1 Proton Plan Status January Eric Prebys.
High Intensity Booster Operations William Pellico PIP II collaboration Nov. 9 th 2015.
F A Fermilab Roadmap Dave McGinnis May 28, f Fermilab Roadmap - McGinnis Timelines  Divide the road map into three parallel paths  ILC - Energy.
Proton Plan Director’s Review 8/15/06 Prebys Proton Plan Summary Director’s Review August 2006 Eric Prebys.
Proton Planning Eric Prebys FNAL Accelerator Division.
Proton Plan PMG 10/13/05 E Prebys 1 Proton Plan Status September Report Eric Prebys.
Early Beam Injection Scheme for the Fermilab Booster: A Path for Intensity Upgrade Chandra Bhat Fermi National Accelerator Laboratory DPF2015, ANN ARBOR,
Proton Plan Director’s Review 8/15/06 Prebys Proton Plan Answers to Questions Director’s Review August 2006 Eric Prebys.
F Possible Proton Capabilities at Fermilab Dave McGinnis April 16, 2007.
Proton Plan Eric Prebys, FNAL Accelerator Division.
Proton Plan PMG 4/18/05 E Prebys/J. Sims 1 Proton Plan Status March Report Eric Prebys Jeff Sims.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Proton Improvement Plan Bob Zwaska September 9, 2013 All-Experimenters Meeting.
PAC Meeting, December 12, Prebys 1 The Problem.
Limitations to Total Booster Flux Total protons per batch: 4E12 with decent beam loss, 5E12 max. Average rep rate of the machine: –Injection bump magnets.
Proton Plan 1/10/07 E Prebys 1 Proton Plan Meeting Agenda:  Project/campaign reorganization: Prebys  Status updates: all  Booster Water Proposal: Cooper.
Booster High Power RF at PIP-II Era John Reid February 18, 2014.
PIP Update May Agenda Summary Update – Activities – Budget – Plans Update Slides – Solid StateTom – ModulatorsRene – High Power Ferrite Testing.
Presenter : Yang Wu McMaster University Work conducted at IHEP.
PIP Update June 17 th Agenda Summary Update – Current Activities – Updates (Matt – Cavity Refurbishment) – Additional Meetings/Notes.
Proton Economics Eric Prebys FNAL Accelerator Division.
Accelerator Division View Sergei Nagaitsev DOE Independent Project Review of PIP-II 16 June 2015.
High Power RF Systems for 2-8 GeV Fast Cycling Synchrotron PROJECT X (ICD-2) John Reid September 11, 2009.
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
Presentation transcript:

SNuMI: WBS 1.1 Booster Upgrades Eric Prebys $642K FY06$ (no contingency, no G&A) xx% contingency Main Injector & Recycler BNB NuMI Tunnel Booster Ring Accumulator Ring (phase II) Pond Expansion (phase II)

WBS 1.1: Booster Upgrades SNuMI Director’s Preliminary Review November 2006 Eric Prebys 2 Overview Introduction/Proton Plan Scope of system & WBS interfaces Performance Specifications Design Issues, Progress & Plans Value Engineering & Risk Management Costs Schedule & Milestones Summary

WBS 1.1: Booster Upgrades SNuMI Director’s Preliminary Review November 2006 Eric Prebys 3 The Booster The Booster is a rapid cycling synchrotron which takes beam from the 400 MeV Linac and accelerates it to 8 GeV for injection into the Main Injector. It has not changed significantly since it was built ~35 years ago. The magnets are run in an offset 15 Hz resonant circuit, which sets a fundamental clock for the entire accelerator complex. The Booster delivers beam at an instantaneous rate of 15 Hz, but pulsed elements limit the average rate, but pulsed elements in the RF system currently limit the average rate to about 9 Hz.

WBS 1.1: Booster Upgrades SNuMI Director’s Preliminary Review November 2006 Eric Prebys 4 Proton Plan The Proton Plan is the current campaign to maximize proton delivery to NuMI and MiniBooNE during the collider era: –Hardware projects complete in 2008 shutdown –Plan complete in 2009 –SNuMI assumes success of Proton Plan The Main Goals of the Proton Plan are: –Increase overall reliability of Linac/Booster –Increase Booster efficiency to reduce uncontrolled beam loss in Booster tunnel (currently the limiting factor in beam delivery) –Achieve Booster beam quality necessary for slip stacking in the Main Injector –Increase average Booster repetition rate to at least 9 Hz If the first three goals are met, they will satisfy the needs of SNuMI Repetition rate remains an issue

WBS 1.1: Booster Upgrades SNuMI Director’s Preliminary Review November 2006 Eric Prebys 5 WBS Interfaces Within the scope of the SNuMI plan, there are no predecessors to the Booster task. The Booster section does depend on the success of the Proton Plan, and scope will need to be added if the Proton Plan does not meet its goals. The Booster also depends on the 400 MeV Linac. –Possible issues would be beam stability and beam loss –If new scope is necessary, it can be added under this section The Booster will deliver beam to the Recycler (1.2) –Must verify beam quality sufficient for slip stacking

WBS 1.1: Booster Upgrades SNuMI Director’s Preliminary Review November 2006 Eric Prebys 6 Performance Specifications ParameterProton PlanSNuMI ISNuMI IIUnit Extracted Batch Intensity4.3E E+12protons Average Pulse Rate Hz Average Beam Rate Hz Norm. Trans. Emittance at Extr.15  95% Long. Emittance per Bunch at Extr %  p (After Bunch Rotation) 888(±) 95%

WBS 1.1: Booster Upgrades SNuMI Director’s Preliminary Review November 2006 Eric Prebys 7 Repetition Rate (1.1.1) After the Proton Plan, the Booster should be able to run at 9 Hz. It’s possible it could run at the 10.5 Hz needed by SNuMI, although there might be reliability issues. In general, if we determine that we need upgrades to run reliably 10.5 Hz, we will do what is necessary to get to 15 Hz. –Also good to start on 15 Hz upgrades needed for phase II We have budgeted the things we feel are the most important: –RF tuner cooling ( ) –RF Anode supplies ( ) –RF Bias supplies ( ) We are evaluating other things that might be issues: –Feeder capacity ( ) –480V distribution system ( )

WBS 1.1: Booster Upgrades SNuMI Director’s Preliminary Review November 2006 Eric Prebys 8 RF Bias Supplies ( ) Each of the 19 RF cavities in the Booster has three biased ferrite tuners which sweep the frequency from 37 to 53 MHz as the Booster accelerates. The end cones of these tuners could overheat at high repetition rates and become damaged. There is a cooling channel in these end cones, which is not currently used. We will inspect these and repair if necessary –$???K M&S –$???L Labor Tuner (1 of 3)

WBS 1.1: Booster Upgrades SNuMI Director’s Preliminary Review November 2006 Eric Prebys 9 Anode Power Supplies ( ) Supply power to the anodes of the power amplifier tubes in the Booster Pulsed power of A Original to the lab. –Probably OK to 10.5 Hz –Problematic at 15 Hz A full replacement would cost $2-3M Plan to refurbish with new transformers –$???K M&S –$???K Labor

WBS 1.1: Booster Upgrades SNuMI Director’s Preliminary Review November 2006 Eric Prebys 10 RF Bias Supplies ( ) These supplies provide the current to the ferrite loaded tuners described in Half of these were built with transformers capable of continuous 15 Hz operations. The other half weren’t Probably OK to 10.5 Hz. To go to 15 Hz, need to replace internal transformer, which requires some minor rework of the chassis –$???K M&S –$???K Labor Modulator Bias Supply

WBS 1.1: Booster Upgrades SNuMI Director’s Preliminary Review November 2006 Eric Prebys 11 Other Elements (not related to repetition rate) Must verify that Booster has met its Proton Plan goals in terms of batch size and efficiency –These currently appear as milestones Verify Booster meets beam loss requirements Verify Beam quality requirements –These sections provide a place for scope increase, if goals are not met Need to address radiation safety (1.1.3) –Booster shielding assessment limits beam to 1.35E17 protons/hour –Enough for phase II w/o 8 GeV program –Booster protected by interlocked radiation monitors, so increasing shielding assessment primarily paperwork

WBS 1.1: Booster Upgrades SNuMI Director’s Preliminary Review November 2006 Eric Prebys 12 Value Engineering The bulk of the elements in the Booster section of SNuMI involve increasing the repetition rate of pulsed elements and power supplies. In all cases, we currently believe this can be achieved with straightforward refurbishments of existing systems.

WBS 1.1: Booster Upgrades SNuMI Director’s Preliminary Review November 2006 Eric Prebys 13 Risk Management In the matter of the repetition rate, the biggest risks are –Refurbishment of the anode supply determined to be inadequate Would require $2-3M anode supply replacement –480V network and/or feeder determined to be inadequate Not costed out yet, but on the order of hundreds of $K. If the Proton Plan does not meet its goals, it will result in increase of scope –Proton Plan carefully tracked and reviewed to establish that it is meeting its goals –At the end of the plan, the Booster will have a very sophisticated correction system, so further improvements will likely come from addressing beam physics problems through study and understanding, rather than major hardware projects i.e. time not money

WBS 1.1: Booster Upgrades SNuMI Director’s Preliminary Review November 2006 Eric Prebys 14 Cost Overview (no G&A or contingency)

WBS 1.1: Booster Upgrades SNuMI Director’s Preliminary Review November 2006 Eric Prebys 15 Cost Drivers The cost is driven by the upgrades that are required to increase the average repetition rate of the Booster RF system –Tuner cooling –Bias supply improvement –Anode supply refurbishment For the moment, there are no M&S requesitions planned in the next six months.

WBS 1.1: Booster Upgrades SNuMI Director’s Preliminary Review November 2006 Eric Prebys 16 Booster Upgrades Schedule Overview

WBS 1.1: Booster Upgrades SNuMI Director’s Preliminary Review November 2006 Eric Prebys 17 Booster Upgrades Milestones Very important to establish beam power requirements ( ) –At what level will we continue to run 8 GeV program, if at all? –This will drive the 15Hz vs Hz decision If we decide the 480V system and/or the feeder are inadequate for 15 Hz operation ( , ), any resulting increase in scope might be put off until Phase II. If we determine that the Booster has not bet the Proton Plan goals ( , ), it will increase the scope of Phase I

WBS 1.1: Booster Upgrades SNuMI Director’s Preliminary Review November 2006 Eric Prebys 18 Conclusions SNuMI benefits greatly from the existing Proton Plan –At the end of the Plan, the Booster should meet the SNuMI needs in terms of beam quality and total proton rate Majority of Booster activities aimed at increasing repetition rate, to full 15 Hz where possible –RF cooling –Anode power supplies –Cavity bias supplies Overall Cost (base cost of $642 K) –Total contingency for system xx% –Cost driven by the repetition rate items –Currently based on engineering estimates Schedule –Driven design and the delivery of tranformers to refurbish anode supplies –Not a critical path item in the overall project