NCSX VACUUM VESSEL PL Goranson Final Design Review November 17, 2005 Man Access Port /Lateral Supports NCSX.

Slides:



Advertisements
Similar presentations
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Advertisements

WING SUPPORT CONCEPTS FOR WINGS # 2,3,6,7 AND 9 GARY MCGINNIS 09/19/ – TAPPING HOLES FOR STUDS 2 – STUD AND INSERT WELDING 3 – WELDING BRACKETS.
FDR Station 3 lift fixture, laser screens and brackets T. Brown and L. Morris with analysis support from A. Brooks December 3, 2007.
J. H. ChrzanowskiNSTX TF Flag Joint Design Review1 NSTX TF Flag Joint Design Review Fabrication and Assembly April 10, 2003 By: James H. Chrzanowski.
NCSX Vacuum Vessel Overview Paul Goranson WBS 12 Manager Vacuum Vessel Manufacturing Study Kickoff meeting April 29, 2003.
WBS3 Diagnostics Planning Update Presented by B. Stratton with input from T. Brown, M. Cole, E. Fredrickson, R. Feder, P. Goranson, L. Guttadora, D. Johnson,
Integration of Cavities and Coupling Coil Modules Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting March 28 – April 1, 2004.
MICE RF and Coupling Coil Module Integration Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 27, 2004.
1 Configuration Development for HIF Final Focus Superconducting Quadrupole Array HIF Final Focus Meeting July 2, 2002 Tom Brown Chang Jun Phil Heitzenroeder.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
NCSX Office of Science Project Review Cryostat, WBS171 August 15-17, 2007 NCSX Fabrication, Operations, and Maintenance Division Engineering Department.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
NCSX NCSX CDR May 21-23, 2002 Larry Dudek Slide 1 Facility Systems (WBS 62-65) L. Dudek, G. Gettelfinger, M. Kalish.
SC Project Review of NCSX, April 8-10, 2008 NCSX Heater Control System P. L. Goranson Work package 1270.
1 Stage 3 Peer Review October 26, 2006 T. Brown. 2 Field Period Assembly (FPA) 1.Make sure the requirements for the tooling is well defined (including.
NCSX Vacuum Vessel Joint Design Mike Viola PPPL July 1 st, 2003.
NCSX VACUUM VESSEL PL Goranson Comprehensive Final Design Review May 05, 2005 Vacuum Vessel Supports Heating/Cooling System NCSX.
1 BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnet and Girder Integration Lewis Doom, NSLS-II Project National Synchrotron Light Source II (NSLS-II) will.
1 WBS 1 Design Analysis Status NCSX Analysis Meeting Dec 3, 2003.
SC Project Review of NCSX, April 8-10, 2008 NCSX Coil Services P.L. Goranson Work Package 161.
NCSX A. Brooks, P. Fogarty, G. Lovett, D. Williamson June 3, 2005 Modular Coil Type-C Final Design Review – Part II.
NCSX VACUUM VESSEL PL Goranson Thermal Insulation Final Design Review July 31, 2006 WBS12 NCSX.
Metrology Milestones Metrology Task Force –Vacuum vessel manufacture - P. Goranson –Mod. Coil Form manufacture - D. Williamson –Mod. Coil winding- S. Raftopoulos.
1 MC Assembly over the VV FPA Station 3 FDR Review July 17, 2007 T. Brown.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
SC Project Review of NCSX, April 8-10, 2008 NCSX Fueling and Vacuum Pumping Systems W. Blanchard WBS 21 and 22 Manager.
NCSX NCSX TF Coil Procurement 1 February 3, 2006 Michael Kalish NCSX TF Coil Procurement.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
Vacuum Vessel lateral loading (Neutral beam port only)
SC Project Review of NCSX, April 8-10, 2008 Job 1260 Neutral Beam Transition Duct (NBTD) P. L. Goranson.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
NSTX Response to the Lessons Learned Report NSTX TF Coil Repair Review September 3-4, 2003 Al von Halle.
11/2/2005Mike Viola1 November Lehman Review November 2, 2005 NCSX VVSA NCSX Vacuum Vessel Fabrication Major Tool and Machine – S F 3 120° segments.
F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF, TF, & Trim Coil Supports (WBS-15) Core Base Support Structure (WBS-17) F. Dahlgren NCSX Coil.
1 NCSX WBS HANDLING/SUPPORT UPDATE PLG 7/23/03 STATUS Study is for 120 degree VVSA field period assembly. Vessel Installation Support Concept.
NCSX NCSX CDR May 21-23, 2002 H.W. Kugel Slide 1 Conceptual Design for NCSX Auxiliary Systems Heating, Fueling,Wall Conditioning and Vacuum Systems.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab NFMCC at LBNL January 25, 2009.
1 MC Assembly over the VV FPA Station 3 FDR Review July 13, 2007 T. Brown.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62) Manager.
SC Project Review of NCSX, April 8-10, 2008 NCSX Machine Assembly E. D. Perry.
NCSX November 18-20, 2003NCSX Performance Baseline ReviewMichael Viola 1 NCSX Vacuum Vessel R&D, Risk Management and Manufacture Mike Viola, Phil Heitzenroeder,
1 Assembly Tooling PU Workshop on NCSX Cost & Schedule Princeton Plasma Physics Laboratory Princeton, NJ Mar 1-4, 2007 T. Brown Princeton Plasma Physics.
Field Period Assembly Wayne Reiersen SC Project Review PPPL May 2006.
1 PFC requirements  Basic requirements  Carbon based  Provisions for adding (interface design included in research prep budget)  NBI armor  Trim coil.
NCSX 21 March 2003 Reiersen - 1 PDR Preparations Wayne Reiersen NCSX Engineering Meeting 21 March 2003.
9/28/20051 Mike Viola 1, T. Brown 1, P. Heitzenroeder 1, F. Malinowski 1, W. Reiersen 1, L. Sutton 1, P. Goranson 2, B. Nelson 2, M. Cole 2, M. Manuel.
Engineering Operations Outage Status: New shielding of HHFW/in-vessel components has been completed. Fit-ups of OH bus lead upgrades to reduce error fields.
NCSX VACUUM VESSEL HEATING/COOLING PL Goranson Final Design Review April 4, 2006 Coolant Hose Assemblies and Thermo- hydraulics NCSX.
SEPT 20, 2006 T. Brown, M. Cole, P. Fogarty, P. Goranson, K. Freudenberg, D. Williamson NCSX STAGE 2 COIL TO COIL ASSY.
12/19/2006Mike Viola1 December Lehman Review December 19, 2006 Mike Viola Field Period Assembly Manager NCSX Field Period Assembly + + =
Phil MottAMS-02 Phase II Safety Review1 Vacuum Case Mechanical Design Alpha Magnetic Spectrometer (AMS) - 02 Phase II Flight Safety Review Vacuum Case.
NCSX VVSA / MCWF FDR A Systems Engineering Perspective Wayne Reiersen Bob Simmons NCSX VVSA / MCWF FDR May 19-20, 2004 PPPL.
Stellarator Core Machine Configuration NCSX Project Meeting Dec 19-20, 2000 B. Nelson, M. Cole, P. Fogarty P. Goranson, G. Jones, D. Williamson O AK R.
Proposed integration of cryo BLMs in LHC during LS1 V.Parma, CERN, TE-MSC With contributions/input from: M.Sapinski (BE-BI) Th.Renaglia (EN-MME) N.Bourcey.
NCSX Day 1 ECC (Extra Cheap Cryostat) Cryostat Configuration Status Report – September 30, 2006.
1 CD-2 ECP Preparations What is Needed. 2 Background As part of the CD-2 process, we need to establish a fully supported and documented cost and schedule.
1 VV Support Fixture FPA Stage 1 PDR Review August 10, 2005 T. Brown.
1 NCSX VV Assembly Joint Issue B. Nelson 17 Mar 2005.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
NCSX Vacuum Vessel Fabrication
M1M3 Fan Coil Unit Status Gary Muller & Brian Johnson LSST 2017 Project & Community Workshop 8/17/2017.
2000SS 2½”-12”.
2K CB FDR Overview:  Agenda, Charge, Review Process
2000SS 2½”-12”.
SNS PPU Cryomodule Thermal Shield
SNS PPU Cryomodule Vacuum Vessel
SNS PPU Cryomodule Space Frame
SNS PPU Cryomodule Space Frame
SNS PPU Cryomodule Thermal Shield & MLI
Overview of the TARGET Monolith Rough Vacuum
Presentation transcript:

NCSX VACUUM VESSEL PL Goranson Final Design Review November 17, 2005 Man Access Port /Lateral Supports NCSX

Talk Overview CHARGE STATUS BACKGROUND PUMPING PORT / LATERAL SUPPORT CONCEPT DRAWINGS ANALYSES CONCERNS CHIT RESOLUTION CONCLUSION

NCSX Charge 1. Is the design of the VV lateral support system adequate for normal, fault, and handling loads, including upgraded first wall and a full complement of diagnostics? 2. Do the supports have adequate capability and adjustment to facilitate field period assembly, final assembly, and motion during cool-down and bake-out? 3. Is the personnel access port adequate for initial operation and maintenance? 4. Are the interfaces with other systems (primarily the mod coil shell and cryostat) adequately defined? 5. Are the analyses complete and documented, including stress in the port assembly and heat leak to the mod coils? 6. Are the design drawings adequate for procurement?

NCSX Status-Drawings & Other Design Req. DrawingsNameStatus SE Man Port AssyIssued SE Man Hole Port WeldmentIssued SE Port Cover ModificationIssued SE MCD Flange ModificationIssues SE Lateral Supports Weldments and DetailsIssued DACS Related documents NCS-CALC Design Basis Analysis VV Structural Analysis/Seismic Analysis NCSX-CALC Lateral Support Bracket Analysis NCSX-CALC Man Access Lateral Support Bracket Analysis New, analysis is complete, DAC is being checked. CHITS Outstanding chits from FDR resolved

NCSX Background Decision to delay Neutral Beam Transition Duct (NBTD) left no pumping duct or man access into VV –NB port cover not removable from outside –Port 4 would give inadequate conductance for pumping –Special mod kit on NB port cover required to react lateral loads Cost effective replacement for NBTD was desirable

Pumping port duct concept proposed for replacing NBTD had problems NCSX Original Proposal Did not significantly reduce cost compared to NBTD Did not provide man access - bolts only accessible from inside VV - needs transition joint

NCSX Man Access Port Concept Splits original duct concept into two parts - interface duct supplied by WBS 12 -a pumping duct by WBS 2 Electrical breaks part of pump interface

Man Access/Pump Port Design NCSX 21” access duct on NB ports, accessible from outside - uses commercial SS wire seal flange - flange is interface for cryostat boot - can be retrofit onto NB blank-off port - body is Inconel to permit 350 C bakeout

Lateral Support NCSX Same components and location as NBTD design Loads are the same Analyses documented for mount - stresses are low - DAC in work

NCSX Cryostat Interface Present wall interface interferes -Cryostat penetration at NB port needs to opened up to accommodate Man Access port Flange clears wall Supports lie within outer boundary 27” flange perimeter is Cryostat boot interface

NCSX Neutral Beam port requires sheet metal “cuffs” to retain fabric boot. Cuffs are shown welded in place Fabric boot is not shown for clarity The cuffs will be cut to required shape from flat patterns developed from solid models Cuffs do not bridge electrical break Sheet Metal Cuffs

NCSX Assembly Drawing

NCSX Port Weldment

NCSX Weldment Details

NCSX Port Cover Modification

NCSX Wire Flange Machining

NCSX Lateral Support Parts

NCSX loading Model fixed at vacuum vessel flange Standard earth gravity applied 6000 lb applied normal to lateral support bracket

Stress Intensity (Tresca) NCSX

Deformation NCSX

Typical heat tape and thermocouple installation philosophy covers NB port as well. Heater routing is detailed as part of heater assy drawings. NCSX Drawing for Large Diameter Ports

Wire seal flanges from MDC may not meet permeability requirements - VV conflats had to be replace with Trinos 316LN flanges - special order on these flanges could be price and schedule problem - need to verify permeability and/or determine compromise maximum value acceptable before purchase NCSX Concerns

NCSX Chit Resolution CHIT 1Man access port design basis analyses and interfaces (e.g. w/cryostat) are incomplete. [Reiersen] Analyses are complete. ICDs will be updated under another broader review 4Check on requirements on location for insulating breaks in personnel access part and pumping duct. [Reiersen] Port does not have break but pumps may at their isolation valves. Not part of WBS12 5Verify that budget and schedule activities for personnel access port is in the project baseline. [Reiersen] Budget and schedule covers the port with 54K$, under There is additional budget at pppl for lateral support fab. 23Need to coordinate with the Cryostat folks and make sure they can interface with the Man Port. Also work with the pumping duct folks to verify this meets pumping interfaces. [M. Cole] Duct size was pre-approved by WBS2 before design. WBS6 approved provided port flange extends past Cryostat wall, which it does. 28Determine whether the man access port will be used for pumping prior to procurement of all three covers blankoff cover. A. Yes it will. 2 blanks and 1 with a hole. [B. Nelson]

NCSX Conclusion There is documentation work remaining but nothing that will hold up procurement. The review charges have been met. A reduced cost port has been designed which can provide interface for pumping and/or man access into the VV It will interface a boot for the cryostat It is designed to be compatible with 350 C bakeout so it can bridge across MIE operation into future upgrades It provides mounting provisions for the lateral supports without change in their design Compatible with MC insulation seal concept No changes in I&C or Heater tapes