Coordination of Right of Way on Design-Build Contracts By- Richard Bennett State Right of Way Director Virginia DOT.

Slides:



Advertisements
Similar presentations
Right of Way Acquisition Process Jesse W. Smith Right of Way Manager.
Advertisements

Metro Muncipal Agreement Program
Office of Purchasing and Contracts Research Funded Procurement Outreach Training Level III Procurements $50,000 and Above.
TH 55 Mill and Overlay Design-Build Project S.P
Gene Shawcroft, P.E. Central Utah Water Conservancy District April 29-30, 2013.
Your Presenters Lisa Dal Gallo Dave Kirn Regional Executive/Justice Market Leader Partner, LEED AP
Oklahoma Department of Transportation Susan McClune Regulatory Services.
The Design-Build Experience. I-95 Honda Interchange $ 8 million Wateree River $ 8 million Reedy & Enoree Bridge $ 3 million SC 170 Widening $100 million.
Subcontracts 101 By Mitali Ravindrakumar USC Collaboration between Parties Perform Subcontractor Analysis Sponsor - Fund Project/Subcontr act Negotiate.
Alternative Project Delivery
Lunchtime Topics Craig Weise Construction Reform Program Director Lisa Conomy Construction Counsel OSU Office of Legal Affairs.
Government Services How to Respond to a Request for Proposal (RFP) 2006.
RFP PROCESSES Contracts for Professional Services.
Getting Certified In Consultant Selection Steps and Processes Diana Foster.
Selection of Consultancy Services
1 BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Procurement Methodology David Dale NLSL II Procurement Manager.
Legal Perspective on NDOT Alternative Procurements Geoffrey S. Petrov, Nossaman LLP.
PROCEDURES FOR SELECTING THE CONTRACTOR
New York State Department of Transportation
New York State Department of Transportation
THE EVALUATION PROCESS FOR RFP’S: THE DIFFERENCE BETWEEN THE ARCHITECTURAL RFP AND A GENERAL SERVICE RFP TREENA BRADLEY, ROOSEVELT ELEMENTARY SCHOOL DISTRICT.
Understanding Right of Way Process Dawn Haecker - Training & Technical Support Supervisor INDOT Trent Newport - VP, CrossRoad Engineers.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Interstate 81 Bridges over Route 80 Design-Build Project (PIN , D900023) Town of Tully, Onondaga County.
WELCOME TO THE PROCUREMENT SEMINAR Procurement and Contracts An Overview of Contract Administration.
Using QBS A Qualifications-Based Selection Process Presenters: Ron Brenke, PE - QBS Manager.
State of Oklahoma Information Services Division Contracts and Purchasing Unit 1.
Procurement Process Economic Stimulus. Items to Be Discussed Professional Services Information Design Build vs. Conventional Where to Find Advertisements.
New York State Department of Transportation
Public Works Contracting Marsha Reilly Office of Program Research House of Representatives recommended.
PM/CAM Training H. Jeff Moore May 11, AGENDA Overview CM at Risk Design (Completion) / Build Lunch Break / Discussion – 11:30 AM – 12:30 PM CM Agency.
Right of Way Section Dee Jones State Right of Way Manager Richard Dunlap Operations Manager Joe Gray Region 5 Right of Way Manager
Design Build, Job Contracting, or Construction Manager at Risk In early 2000 the legislators added an alternate way to accelerate construction project.
Purchasing Overview. Fundamentals of Purchasing Procedures.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Region 9 Design-Build Project (PIN , D900020) Broome, Delaware,
Texas Turnpike Authority Division AASHTO Right of Way & Utilities Committee Conference Wednesday – April 22, 2009.
Understanding Right of Way Process Dawn Haecker, Training & Technical Support Supervisor, INDOT Trent Newport, VP, CrossRoad Engineers.
Consultants' Competitive Negotiation Act Acquisition of professional architectural, engineering, landscape architectural, or surveying and mapping.
RIGHT OF WAY BEST PRACTICES FOR LOCAL PUBLIC AGENCIES.
1 Procurement. 2 Overview Every municipality should keep procurement records that allow an auditor or other interested party to track the specific nature.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Regions 2 & 9 Design-Build Project (PIN , D900022) Herkimer,
Elk Run Interchange Design-Build Project S.P (TH 52) Elk Run Interchange Design-Build Project S.P (TH 52) PROJECT INFORMATIONAL MEETING.
Procurement Authority Representative Roles and Responsibilities Amanda Price, Program Development Coordinator, Planning and Programming, Transportation.
UNDP Bangladesh Procurement Fair Objectives of the Fair; - UNDP Procurement principles; - Procurement plan ; - UNDP Procurement Roadmap;
July Accomplishments: Authority and Design Build Contractor staff conducted the 3rd Urban Design committee meeting. Committee members viewed proposed station.
Presented By: Jeffrey T. Folden, P.E. Assistant Chief, Innovative Contracting Division.
1 Test Operations Contract RFP Volume III ITO Briefing RFP NNS09ZDA008R – TEST OPERATIONS CONTRACT (TOC) Ground rules This presentation is intended to.
1. Land Conservation Act (LCA) * Public Agency Webinar Public Acquisition Notification Procedure – A Step by Step Guide * LCA, also known as the Williamson.
1. Design-Build is a project delivery process in which the design and construction phases of a project are combined in a single contract. The consultant.
Ohio Department of Transportation John R. Kasich, Governor Jerry Wray, Director Real Estate Overview Matt Kouskouris, Division.
Construction Management At Risk Process
CONDUCTING BUSINESS WITH THE TOWN OF MIAMI LAKES Construction Services October 28, 2013.
Procurement of Professional Services.  Professional Services:  Architects, Engineers  Surveyors  Geotechnical engineers  Nonprofessional Services:
Southeast Rail Extension FasTracks Monitoring Committee July 14, 2015.
US Army Corps of Engineers BUILDING STRONG ® Building and Preserving Alaska’s Future Alaska District Design-Build Contracts Moolin Seminar November.
Compliance with CCNA F.S..  Advertisement  Longlist  Shortlist  Request for Proposal  Scope of Services Meeting  Technical Proposal Review.
What is Tax Increment Financing?
Procurement & Strategic Sourcing
Light Rail Transit Project
Award Management Services
CM at Risk v. Design-Bid-Build
QBS: The Process Selecting a Design Firm
Request for Proposal - Best Value
Consultant Selection Training
DIVISION OF STATE SERVICES BUREAU OF CONTRACTS
AX7665D82 Areawide Total Maximum Daily Load (TMDL) Design-Build
Request for Proposal - Best Value
PROJECT DELIVERY METHODS
Right-of-Way the right way
Understanding the Right-of-Way Process
Brieana Reed-Harmel, Broadband Project Manager
Presentation transcript:

Coordination of Right of Way on Design-Build Contracts By- Richard Bennett State Right of Way Director Virginia DOT

Overall VDOT Design-Build Process Mostly use two-step process More defined smaller project uses one combined process P 3 projects are generally unsolicited

Design-Build Procurement (2 Step) Internal review to determine projects suitability for D-B and information available VDOT issues request for Statement of Qualifications (SOQ) providing general project information Selection Committee established SOQ received from offerors (usually Contractors are Prime) Selection Committee evaluates SOQ and shortlists 3 offerors

Design-Build Procurement (2Step) (continued) VDOT issues a Request for Proposal from short- listed offerors RFP includes specific requirements including Right of Way acquisition methods and utility relocation coordination RFP response is a separate detailed technical proposal and cost proposal Selection Committee evaluates technical proposal (30% score) and then opens and evaluates cost proposals (70% score). May involve interview Project awarded to offeror with highest total score

Right of Way Involvement Part of internal review is to determine ROW requirements –Can project be built in existing ROW –Is fee needed or only temporary construction easements –Potential for VDOT to acquire prior to award –ROW acquisition in D-B contract

Right of Way in Design-Build Contract Creation of ROW allowance for payment Establishes qualification for ROW Team Establishes general requirements of process All consultant cost included in set bid price

Right of Way Coordination D-B contractor submits detailed ROW plan after award for DOT approval D-B contractor submits detailed schedule to submit plans for approval and to acquire properties and relocate displacees Work flow process is mapped and response timeframes are set (usually 15 to 21 days) Often weekly or biweekly Over The Shoulder (OTS) reviews are included

VDOT Right of Way Reviews & Approvals Completeness of plans for public participation meeting. Plans adequate for approval to acquire ROW Notice to commence acquisition (Project or Parcels) Approval of appraisal and just compensation

VDOT Right of Way Reviews & Approvals (continued) Review and comments on displacee interviews Review and approval of RHP and Moving Costs Review and approval of settlement above offer Review and approval of eminent domain filings

VDOT Right of Way Reviews & Approvals (continued) Certification of parcel/project clearance & notice to commence construction Payment of landowner or displacee compensation

Right of Way Certification As parcels are cleared through Option or Eminent Domain a certificate and notice to commence construction is issued Most projects involve certifying a group of parcels together (re-same block or construction feature)

Design-Build Contractor Provides Preliminary Title Report Appraisal and Appraisal Reviews (separate subs) Negotiations (30 days min.) Relocation Assistance Services & computations Settlement recommendations

Design-Build Contractor Provides (continued) Eminent Domain Documents for refusals Option agreement and closing documents for voluntary conveyances Closings, Recording and Title Insurance Complete file

Quality Control Over the Shoulder reviews Appraisal and Just Compensation Approval Negotiation Report for Closing or Eminent Domain filing Relocation activities and RHP calculations

D-B vs. VDOT Issues Timely resolution of design issues Limits of right of way to be acquired Limited Access issues Appraisal quality and scope Adequacy of negotiations Pressure to complete parcel for construction access Cost of design changes for ROW issues