The Design-Build Experience. I-95 Honda Interchange $ 8 million Wateree River $ 8 million Reedy & Enoree Bridge $ 3 million SC 170 Widening $100 million.

Similar presentations


Presentation on theme: "The Design-Build Experience. I-95 Honda Interchange $ 8 million Wateree River $ 8 million Reedy & Enoree Bridge $ 3 million SC 170 Widening $100 million."— Presentation transcript:

1 The Design-Build Experience

2 I-95 Honda Interchange $ 8 million Wateree River $ 8 million Reedy & Enoree Bridge $ 3 million SC 170 Widening $100 million Cooper River Bridges $ 531 million Conway Bypass $ 386 million Southern Connector $ 206 million Carolina Bays Parkway $232 million

3 Reedy River Bridge Enoree River Bridge First Design-Build Bridge Replacement in SC First Design-Build Project to Start Construction in SC 1996 RFP Process Two Bridge Replacements $ 3 million Designer Wilbur Smith Associates

4 Cost Summary Cost Summary n Estimate for Design-Bid-Build$ 3,222,000 n Design-Build Price$ 3,125,000 Time Summary Estimated Design-Bid-Build 628 Days Design-Build581 Days

5 Wateree River Bridge Bridge Replacement $ 8 million RFP Process - 1997 Designer Ralph Whitehead & Assoc.

6 Wateree Cost Summary n Estimated Design-Bid-Build $ 9,162,000 n Design-Build Price $ 7,956,000 * * Includes $50,000 for SCDOT Preliminary Engineering & $50,000 for Construction Monitoring $50,000 for Construction Monitoring Wateree Time Summary n Estimated Design-Bid-Build967 Days n Design-Build457 Days

7 HONDA INTERCHANGE New Interchange Bridge Replacement $ 8 million RFP Process - 1998 Designer Consoer Townsend Envirodyne Total Timeframe – 11 Months

8 HONDA INTERCHANGE Total Tracts – 1 Condemnation Rate – 0%

9 CONWAY BYPASS New Location Freeway 28 Miles in Length Fluor Daniel $386 Million 39 Months RFP Process - 1994 Contract Signed - 1998

10 Conway Bypass Total Parcels – 233 Condemnation Rate – 49%

11 SOUTHERN CONNECTOR Greenville County, SC New Location Toll Road 16 Miles in Length Interwest Carolina Group $206 Million 45 Months Maintenance by SCDOT Toll Collection/Operation by Interwest RFP Process - 1995 Contract Signed - 1998

12 SOUTHERN CONNECTOR Total Parcels – 160 Condemnation Rate – 46%

13 SC 170 Widening Beaufort County, SC 12.5 mile widening 2 miles of bridges Includes Right of Way Acquisition $80 million RFQ – RFP Process - 1999 Designer Lawrie & Associates

14 SC 170 Widening Total Parcels – 129 Condemnation Rate – 23% Total Timeframe – 36 Months

15 Carolina Bays Parkway Horry County, SC New Location Freeway 22 miles in Length Includes Right of Way Acquisition $232 million RFQ – RFP Process - 1999

16 Carolina Bays Parkway Total Parcels – 74 Condemnation Rate – 46%

17 Cooper River Bridge Two Bridge Replacements - $ 531 million Charleston, SC

18 Total Parcels – 93 Condemnation Rate – 19% Timeframe – 60 Months

19 Accelerated project completion. PROS OF DESIGN BUILD Generally, final cost less than initial cost estimate. Benefit of having facility available to public. Positive public perception.

20 Reduced timeline for Right of Way acquisition. CONS OF DESIGN BUILD Increased condemnation perception.

21 R/W acquired and cleared in accordance with Uniform Relocation Assistance and Real Property Policies Act of 1970, as amended, and state R/W procedures. FHWA Requirements R/W certification must be submitted to and approved by FHWA prior to work commencing on individual tracts or entire project.

22 FHWA Requirements Request for R/W services must be included in request for proposals. Design/Builder must submit written acquisition and relocation procedures to STD for approval; should contain appraisal, acquisition, and relocation strategy.

23 Role of SCDOT Develop a concise RFP. Provide an on-sight R/W Project Manager as single point of contact with authority to approve all settlements and provide tract certification. Provide constant oversight to insure all federal guidelines are adhered to.

24 Lessons Learned Assign Project Manager and authorize to approve just compensation, appraisals, relocation, administrative adjustments, etc. Establish “critical path” for construction and stage R/W and relocation accordingly. Identify new methods to handle R/W issues; i.e., purchase of improved property without appraisal including establishment of total benefits to landowner, use of auction company for disposal of 14 homes (less than 3 years old).

25 Questions