ERCOT Clarification for PCRR Allocation Terms and Conditions Should this sentence be included under Refund option [Section 7.4.2(c)(i)] Before the applicable.

Slides:



Advertisements
Similar presentations
Lead from the front Texas Nodal 1 Texas Nodal Settlements Mini-Market - CARD July 27, 2007.
Advertisements

Nodal Credit Limit Overview Credit Work Group May 28, 2008 Cheryl Yager.
March 13, 2013 ERCOT Public CRR Transaction Limits NPRR463 Implementation Update Matt Mereness ERCOT Manager Day-Ahead Market and CRR Auction.
1 Revisions to M2 and RT Final Component of UFTA CWG/MCWG ERCOT Public January 22, 2014.
1 Shams Siddiqi, Ph.D. Representing LCRA and Rates and Resources Council (RRC) consisting of 31 NOIEs serving Central Texas TAC.
CRR Shortfall – Revenue Equalization Part 2 (Continuation from 2/21/08 TPTF discussion) Bill Barnes TPTF 3/5/2008.
NPRR Proposed Changes TPTF Meeting 26 Aug 2008.
CRR Update Dave Maggio CMWG July 18, CMWG 7/18/ Transaction Limit Utilization Metrics Discussion on Special “One-Time” Auctions of CRRs Upcoming.
Review of NPRR586 CMWG 1/7/2014. Existing Credit Lock Process ERCOT calculates a “preliminary allocated CRR transaction limit” based on “eligible” CRRAHs.
March 20 & 22, 2013 ERCOT Public ERCOT NPRR463 Market Call NPRR463/CRR Rolling Auction Implementation Update ERCOT CRR Team Manager: Matt Mereness.
January 14, New logic and invoices used in January 2015 when closing out December 2014 New Bill Determinants: CRRBAFA- CRR Balancing Account Fund.
Market Mitigation Concept Group Update Jim Galvin April 26, 2004.
WMS Subgroup – CRR Credit 3.Review of CRR margining methodology for PTP Obligations in Nodal Protocols 4.Potential credit margin alternatives Cheryl Yager.
CRR Auction Scope John Moseley. To outline aspects of the CRR market process to assure that these proposed CRR market protocols (as interpreted by ERCOT.
12/4/2007 ERCOT Public INF MP Identity Management: Roles Gary Macomber.
Texas Nodal Section 9: Invoicing ERCOT, Settlements & Billing SDAWG - August 2007.
ROS Meeting – 12/06/071Texas Nodal Program - TPTF Update Texas Nodal Transition Plan Task Force ROS Meeting Stacy Bridges, ERCOT Thursday, 12/06/2007.
Lead from the front Texas Nodal 1 Texas Nodal CRR Requirements Overview of Requirements for TPTF Shawna Jirasek and Beth Garza September.
February, 2012 ERCOT Public ERCOT CRR Update Matt Mereness ERCOT Manager Day-Ahead Market and CRR Auction.
September 2012 Wholesale Market Subcommittee Report to Technical Advisory Committee.
Matt Tozer ERCOT Manager, Settlements & Billing 9/4/2013 ERCOT Update Management of the Balancing Account CMWG.
Lead from the front Texas Nodal 1 Texas Nodal Congestion Revenue Rights (CRR) EDS 3 Release 7 - Overview EDS 3 Phase 2 MP Planning.
CRR Shortfall – Revenue Equalization Part 3 (Continuation from 3/5/08 TPTF discussion) Bill Barnes/Sharon Wang TPTF 3/21/2008.
April 2, 2008 CRR Team Update PCRRs CRR Team UpdateApril 2, 2008 Table of contents 1.What is a PCRR? 2.Which NOIEs are eligible for PCRRs? 3.What.
1 Market Trials Congestion Revenue Rights Weekly Update May 6, 2010.
1 Market Trials Congestion Revenue Rights Weekly Update April 30, 2010.
CRR Issues Transparency provided by CRR Reports CRR EDS handbook Business process NPRR TPTF November 27, 2007.
Protocol Revision Subcommittee Tom Burke June 7, 2012.
JUNE 18, 2012 CSWG CRR AUCTION RESULTS FORMAT ISSUE FOR DISCUSSION AUSTIN ENERGY 1.
1 Market Trials Congestion Revenue Rights Weekly Update September 3, 2010.
NPRRs 663NPRR Ancillary Service Insufficiency Actions. This Nodal Protocol Revision Request (NPRR) specifies the actions ERCOT will take to ensure sufficient.
TCR to CRR Transition Plan Proposed method for TCR Auction Revenue refunds Contingency plans For TAC Nov 1st, 2007.
9/17/2012 CSWG CSWG – ERCOT Update ERCOT. 2 Settlements Project & Operational Updates February 27, 2012 NPRR 347: Combined Daily Invoice –Still on track.
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Settlement Invoices Business Requirements Settlements and.
Outage Scheduler Transition Plan Kenneth Ragsdale NATF.
Nodal Short Pay and Uplift Process CWG Meeting May 28, 2008.
Congestion Revenue Rights 1 Texas Nodal Market Implementation Program CRR Requirements Updates CRR Project Team – Presented by Beth.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee October 6, 2006.
NPRR533, Clarification of PCRR Eligibility Requirements, Workshop Brad Jones Vice President, Commercial Operations Chad V. Seely Assistant General Counsel.
ERCOT Market Credit Working Group Presentation to the Finance and Audit Committee Payment Short Pay/Default and Uplift for Congestion Revenue rights (CRRs)
March 13, 2007 – Slide 1 ERCOT Nodal 101 COPS Market Guide Commercial Operations Market Guide Section 5 a. Overview of ERCOT ERCOT Overview Market Overview.
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Nodal Dispute Management System Business Requirements ERCOT.
Nodal Readiness Plan Update Ron Hinsley Update for TAC November 3, 2005.
1 NPRR 484/554 Phase 2 Suresh Pabbisetty, ERP, CQF, CSQA Lead Technical Analyst, Credit CWG / MCWG May 20, 2015 ERCOT Public.
Total Potential Exposure (TPE) Overview Credit Work Group May 28, 2008 Cheryl Yager.
July 28, 2010 Market Readiness Seminar Credit Transition to Nodal (Preliminary)
Market Operating Level Agreement (OLA) Discussion Betty Day 8 December 2009 Nodal Advisory Task Force.
Discussion on FGR Settlement Protocol Language David Maggio CMWG February 17, 2014.
Congestion Revenue Rights Market Trials Kickoff. Agenda Topics: I.Overview of CRR Market Trials Phase 3.0 II.Entry Criteria (including System Requirements)
Congestion Revenue Rights 1 TCR to CRR Transition Plan NOIE Workshop Nodal CRR registration process for NOIEs (REVISED) Beth Garza.
TAC Update April 7, Update Nodal Protocol Revision Requests (NPRRs) (Vote): –NPRR306, Revisions to Protected Information to Include Black Start.
Lead from the front Texas Nodal 1 Integrated ERCOT Readiness and Transition (IRT) TPTF – December 4 th, 2006 ERCOT Qualification.
Lead from the front Texas Nodal 1 Nodal Transitional Qualification Approach to Qualifications for the Nodal Market August 16, 2007.
1 Credit Parameters Review TAC July 2, Protocol Section , “Credit Requirement for DAM Bids and Offers” specifies: Credit Requirement for.
Retail Workshop ERCOT Nodal Update October 06, 2010.
Nodal Credit Monitoring and Management – Business Requirements ERCOT CREDIT Department September 28, 2006.
Network Operations Model Go-Live Decision Kenneth Ragsdale TAC July 1, 2010.
CRR Network Model One-Line Diagram Beth Garza TPTF April 22, 2008.
CRR Default and the Nodal Market Wholesale Market Subcommittee February 20, 2008.
Money Transfer Due to Real-Time Irresolvable Constraint Resmi Surendran ERCOT.
Texas Nodal Program ERCOT Readiness & Transition (ERT) Supplemental Information TPTF January 12, 2009 Kevin Frankeny.
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Settlement Statements and Calendar Business Requirements Settlements.
Market Trials Congestion Revenue Rights
TAC Report to the ERCOT Board
NPRRs 815NPRR Revise the Limitation of Load Resources Providing Responsive Reserve (RRS) Service.  This Nodal Protocol Revision Request (NPRR) revises.
ERCOT CRR Update to CMWG
PR CRR Framework Upgrade
Settlements Analysis due to SFT Deration Issue
CEO Report Thomas F. Schrader ERCOT Board of Directors May 17, 2005
Update on Market Trials
Presentation transcript:

ERCOT Clarification for PCRR Allocation Terms and Conditions Should this sentence be included under Refund option [Section 7.4.2(c)(i)] Before the applicable CRR Auctions, the NOIE must nominate the months (designating CRR amounts as defined by the criteria specified in Section 7.3(6)) for which it will use its PCRRs (i.e.., the NOIE may shape the PCRRs representing 40% of the capacity for each Resources). When selecting the Refund option, can blocks be specified?

CRR Auction Settlements  Section When the term CRR is used in this Section does it refer to just CRRs or does it refer to both CRRs and PCRRs?

CRR Delinquent Payments  Under Section 7, it does not address the issue of delinquent payments of CRR Auction Invoices.  Is it the intention of the Market to charge CRR Account Holders an interest charge for late payments?

Timely Payments of PCRR Invoices  Under ERCOT Protocols Section (5),it states that “Any unpaid PCRs that remain outstanding after five (5) days after the issuance of an invoice will be included in the monthly auction.”  Should this sentence or a similar one be included in the ERCOT Nodal Protocols?

Refusal of PCRRs  Following the annual CRR/PCRR Auction, can a Municipally Owned Utilities (MOUs) and Electric Cooperatives who sought PCRRs refuse their allocated PCRRs?

Self-imposed Credit Limit for PCRRs  Can Municipally Owned Utilities (MOUs) and Electric Cooperatives, who submit nominations for PCRRs and do not have to submit bids for them, submit a self-imposed credit limit for PCRRs?

CRR Account Holder Requirement  Is there any notice in the ERCOT Nodal Protocols which prevents a party from participating in a CRR Auction other than Section 16.8, Registration and Qualification of Congestion Revenue Rights Account Holders?  Can a Transmission and/or Distribution Service Provider (TDSP) qualify?