Campus Plan Roosevelt Island campus > Laboratory of innovation > Open and inviting to the public > Sustainable and energy-efficient
BLOOMBER G CENTER
Public Open Space > More than 20% of the Site > No Gates, Walls or Barriers > Public Programming
Public Open Space > Laboratory of innovation > State of the art technologies > Sustainable and energy-efficient Bloomberg Center > Collaborative Work Environment > Net-Zero Goal > Public Café, Art and Programming
The Bridge > Co-Location Space for Companies > Cornell Tech Studio Space > Common Spaces for Programming
Residential Building > First High Rise Passive House in the World > Housing for Students, Faculty & Staff
2017 Phase One
Project Schedule Start of DemolitionJanuary 2013 End of DemolitionJune 2015 Start of SiteworkDecember 2014 Start of Bloomberg Ctr.March 2015 Start of The BridgeMay 2015 Start of Residential June 2015 Phase I OpeningSummer 2017
December 2014
January 2015
February 2015
March 2015
April 2015
May 2015
June 2015
July 2015
August 2015
September 2015
October 1, 2015
Bloomberg Center
October 1, 2015 Bloomberg Center The Bridge (Co-Location)
October 1, 2015 Bloomberg Center The Bridge (Co-Location) Residential Building
October 1, 2015
Current & Upcoming Work Sitework Utility installation on East and West roads (closed to public) Utility installation on campus Completion of CUP structure & start of equipment installation North Road to re-open by the week of October 12 Bloomberg Center Steel structure started September Façade/enclosure to start in January 2016 The Bridge (Co-Location) Steel structure to start in early October Façade/enclosure to start in Winter 2016 Residential Superstructure to start in mid October Façade/enclosure to start in Winter 2016
September 2015 Utilities & Roadways
September 2015 Utilities & Roadways
September 2015 Bloomberg Center
September 2015 Bloomberg Center
September 2015 Bridge (Co-Location)
September 2015 Bridge (Co-Location)
September 2015 Residential
September 2015 Residential
Construction Commitments Reduce truck traffic through largest voluntary barging effort in NYC history Minimum 17% MWBE participation in construction Union labor on all construction projects On-site air monitoring for duration of the project Extensive roadway & utility improvements Close communication with Roosevelt Island stakeholders
Barging for Demolition Reduction of more than 12,000 truck trips on Main Street
September 2015 Barging for Demolition
Barging for Construction
September 2015 Barging for Construction
Upcoming Milestones Reopening of North Loop Road Relocation of West Road fence to facilitate road reconstruction Steel construction at Bloomberg Center & The Bridge Concrete superstructure at Residential Building Start of geothermal wellfield
2017