Lessons Learned from Block Load Transfers following Hurricane Rita Reliability and Operations Subcommittee Meeting January 13, 2006.

Slides:



Advertisements
Similar presentations
T&D Losses Reflecting Losses in DR within ERCOT August 22, 2012.
Advertisements

1 Direct Participation Demand Response Tariffs Demand Response Phase IV Workshop March 21, 2011.
1 Wal-Mart’s View on Demand Response Program Design Anoush Farhangi Angela Beehler.
BRAZOS ELECTRIC COOPERATIVE Dobbin 345 Project David Albers, P.E. Manager – System Planning.
GDS Associates, Inc. ERCOT Reliability Operations Subcommittee June 10, 2010 Tex-La Electric Cooperative of Texas Load Forecast Methodologies.
Profiling Working Group 1 PWG Update Report By Brad Boles of Cirro Energy ERCOT PWG Vice-Chair for COPS Meeting November 6, 2007.
11/08/2005 Ken Donohoo Report on Lessons Learned – Hurricane Rita November 10, 2005 ROS Meeting Austin Control Center (MET Center)
Retail Market Update June 5, New meter is requested for a specific customer’s location. 2.Application is filed by customer and/or the customer’s.
Hurricane Rita. 2 ERCOT Preparation ERCOT started alerts to QSEs and TOs on 9/21 Did a site failover of EMMS system Austin Taylor Procured satellite voice.
CCET as a Forum to Help Resolve Interoperability Issues Grid-Interop Stakeholders Coordination Panel Nov 11-13, 2008 Atlanta, GA Milton Holloway, Ph.D.
1 AMS Data Workshop ERCOT Overview of AMS Data Processes June 27, 2014 ERCOT June 27, 2014.
Profiling Working Group January xx, PWG Update Report By Ernie Podraza of Reliant Energy ERCOT PWG Chair for RMS Meeting January ??, 2006.
RMSUpdate January 6, 2005 Retail Market Subcommittee Update to TAC.
Compiled by Load Profiling ERCOT Energy Analysis & Aggregation
ERCOT Demand Side Working Group Mary Anne Brelinsky Eagle Energy Partners.
1 Welcome to Load Participation Orientation Elev MenWomen Phones Info Presentation and other Load Participation information will be posted at:
1 Presented to ERCOT Retail Market Subcommittee January 9, 2002 Profiling Working Group Darryl Nelson, Chair Load Profiling Operating Guides (LPOG)
1 RMS Update - ERCOT June 10, Supporting Reports Section.
Advanced Metering Implementation Team Update Christine Wright Public Utility Commission of Texas October 2008.
ERCOT MARKET EDUCATION
Advanced Meter Settlement Background and NPRR. Overview PUC Rule (wholesale settlement) Project – Wholesale Settlement Project Filed Deployment.
Real Time Settlement Timeline Workshop Debrief To TAC 11/29/2012 Evaluation and consideration of reducing the RT Settlement Timeline Jim Galvin- CSWG Chair.
1Texas Nodal Market Trials Update. 2Texas Nodal Full System Market and Reliability Test 24-Hour Test Observations Duration of Test for Week of 8/ Hour.
ERCOT MARKET EDUCATION Retail 101. Introductions, Roles and Responsibilities.
RMS Update to TAC January 8, Voting Items From RMS meeting on 12/10/2008  RMGRR069: Texas SET Retail Market Guide Clean-up – Section 7: Historical.
Mandy Bauld ERCOT October 9, 2012 RTM SETTLEMENT TIMELINE.
Profiling Working Group March 14, PWG Update Report By Ernie Podraza of Reliant Energy ERCOT PWG Chair for COPS Meeting March 14, 2006.
Calculation of Net Energy for Load COPS. 2 2 Outline  Definition of Net Energy for Load  How Net Energy for Load is calculated in ERCOT.
Settlement Accuracy Analysis Prepared by ERCOT Load Profiling.
SPP Presentation. Retail Open Access for ETI within SPP Implementation Considerations Stakeholder Meeting February 21, 2007 Austin, Texas.
1 ESI ID SERVICE HISTORY AND USAGE DATA EXTRACT SYSTEM CHANGE REQUEST (SCR 727) February 24, 2003.
1 RMS Update - ERCOT May 14, Supporting Reports Section.
October 9, 2012 Commercial Operations Subcommittee RMS Update Kathy Scott RMS Vice Chair.
RMS/COPS Workshop VI 1 October 06, Antitrust Admonition ERCOT strictly prohibits Market Participants and their employees who are participating in.
1 Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee January 12, 2006.
MARS Advanced Metering – ERCOT Market Facing Changes Jackie Ashbaugh Manager Data Integrity and Administration 3/9/2009.
AMS Indicator ERCOT Recommendations
ERCOT MARKET EDUCATION Retail 101. Smart Meter Technology.
Tuesday, October 6, 2015 (following RMS) COPS-RMS-WORKSHOPShttp://
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee May 8, 2008.
COPS NOVEMBER 2014 UPDATE TO TAC 11/20/2014 Harika Basaran, Chair Tony Marsh, Vice Chair.
Texas Competitive Market & Governance October 4, 2015.
Retail Market Subcommittee (RMS) Update Kathy Scott April 9, 2013Commercial Operations Subcommittee 1.
Distributed Generation Registration June 30, 2008.
ERCOT MARKET EDUCATION Retail 101. Introductions, Roles and Responsibilities.
Texas Regional Entity ROS Presentation January 15, 2009 T EXAS RE ROS P RESENTATION J ANUARY 2009.
ERCOT MARKET EDUCATION Retail 101. Advanced Meter Technology.
1DRAFT for DISCUSSION Transition From Non-IDR to IDR Load Profile and LSE 15-minute Data for AMS Market Advanced Readings and Settlements Taskforce 10/9/09.
February 2, 2016 RMS Meeting 1. * Reasons: * Per the ERCOT Board Report dated 8/5/14 there were 6.6M Advanced Metering System (AMS) Electric Service Identifiers.
Role of Account Management at ERCOT 2006 TAC Subcommittee Review ERCOT Board February 21, 2006.
COPS DECEMBER 2013 UPDATE TO RMS 12/18/2013 Harika Basaran, Chair Jim Lee, Vice Chair.
ERCOT MARKET EDUCATION Retail 101. Market Rules Overview Topics in this lesson...  Introduction to Market Rules Public Utility Regulatory Act PUCT Substantive.
1 Commercial Operations Sub-Committee Update to RMS November 10, 2005.
Load Participation in Nodal Training Session Update DSWG December 7, 2007.
Commercial Operations Subcommittee Update to TAC Debbie McKeever COPs Chair 2011.
Feb 7, 2013 Technical Advisory Committee RMS Update Rob Bevill.
MMWG Performance Measures Questionnaire. Performance Measure Reporting Requirements The reporting requirements allowed the commission to obtain information.
PWG Long Term Strategy How do we maximize scarce resources?
Profiling Working Group 1 PWG Update Report By Brad Boles of Cirro Energy ERCOT PWG Vice-Chair for COPS Meeting June 11, 2007.
Impact of Hurricane Ike on CenterPoint Energy’s Transmission System Paul Rocha Director, Transmission Planning Presented at October 2, 2008 ERCOT TAC Meeting.
February 26, 2015 Technical Advisory Committee (TAC) Update to RMS Kathy Scott March 3, 2015 TAC Update to RMS 1.
ERCOT MARKET EDUCATION
Impact of Hurricane Ike on
Compliance Report to ERCOT BOD December 2006
Hurricane Rita.
August 25, 2016 TAC Update to COPS
June 7, 2016 Retail Market Subcommittee Update to COPS
The New Texas Wholesale/Retail Market
Texas Energy Market About ERCOT ERCOT market participants
Texas Energy Market About ERCOT ERCOT market participants
Presentation transcript:

Lessons Learned from Block Load Transfers following Hurricane Rita Reliability and Operations Subcommittee Meeting January 13, 2006

2 Lesson’s Learned Purpose: Brief evaluation of Block Load Transfers (BLTs) in the aftermath of Hurricane Rita to pick up load in Entergy Gulf States Service territory Involved Parties: TXU Energy Delivery – Deep East Texas Cooperative BLT (≈10 MWs) Centerpoint – Crosby Station BLT (≈80 MWs) Entergy Gulf States

3 Lesson’s Learned Physical Issues: Very little ERCOT can do. Work needed to block load over and all closely associated activities are between TDSPs. One-line drawings delivered ASAP are very important for a timely transfer (acceptable format) Contractual issues between the TDSP’s (how to compensate TDSPs for work) can slow up transfer

4 Lesson’s Learned Commercial Issues: Need to create a LSE in ERCOT’s system was a hindrance Contractual Issues between the TDSPs should be considered in advance of the need to use an emergency BLT Settlement quality metering during a BLT for emergency restoration (.2% vs.6% CT accuracy) Frequency for providing metering data as well as method for providing data

5 Lesson’s Learned Recommendations: ERCOT will investigate the creation entities and their relationships ahead of time (LSE for BLT into ERCOT; RE for BLT into other control area). Metering CT accuracy (.6%) will be allowed for emergency load restoration. ERCOT recommends actual meter data be provided before initial settlement run. Use of default profiles would introduce significant error if used. ERCOT will be flexible as to the format for data submittal (Loadstar, Excel, etc.). Investigate clearing Interstate Commerce issues in advance for BLTs that could block loads across state lines. Develop checklist for entities to use as a guide to prepare for an emergency.