US Army Corps of Engineers BUILDING STRONG ® Rock Arch Rapids Fish Passage Cape Fear River Lock and Dam No.1 Bladen County, NC US Army Corps of Engineers.

Slides:



Advertisements
Similar presentations
Conserving Americas Fisheries U.S. Fish and Wildlife Service Columbia River Fisheries Program Office Future of Our Salmon A Vision of Restoration in the.
Advertisements

Upstream and Downstream Passage of American Eels at the Medway Project, Penobscot River, Maine Scott Hall ————————————— PPL Maine, LLC Milford, Maine Steve.
Chattahoochee River Restoration Aquatic Ecosystem Restoration City Mills Dam Eagle and Phenix Dam.
Kennebec River Watershed Anadromous Fish Restoration Maine Department of Marine Resources 21 State House Station Augusta, Maine
Removal of the Marvel Slab reopens section of the Cahaba River Photos Courtesy of Paul Freeman, The Nature Conservancy BEFORE (October 15, 2004) AFTER.
Lower Yellowstone River Diversion Dam Project – Phase II - Physical Modeling of the Rock Ramp BRT, COE, MTAO Update Meeting November 4, 2010.
John H. Kerr Dam and Reservoir John H. Kerr Dam and Reservoir U.S. Army Corps of Engineers Wilmington District.
US Army Corps of Engineers BUILDING STRONG ® Mid-West Electric Consumers Association September 16, 2014 Corps of Engineers US Army Missouri River Mainstem.
NWHA- Panel Discussion “Spawning Better Ideas for Fish Passage”
November 14, 2012 Presented By Jill Winton. BACKGROUND.
US Army Corps of Engineers BUILDING STRONG ® Skiatook Lake Drought Issues and Management.
US Army Corps of Engineers BUILDING STRONG ® St. Louis District Low Water Operations Russell Errett Water Control St. Louis District February 2013.
Agenda Item 9 Sutter Bypass CVFPB Meeting April 17, 2009.
US Army Corps of Engineers BUILDING STRONG ® Coordinating U.S. Army Corps of Engineers Regulatory Permits with Species Conservation Plans November 16,
US Army Corps of Engineers BUILDING STRONG ® USACE – ACF Operations Bailey Crane Water Management USACE, Mobile District.
Three Gorges Dam Brilliant solution to Southern China energy crisis or environmental disaster Concept and Environmental.
INTRODUCTION Like many fluvial ecosystems of the United States the Willamette Valley has undergone numerous environmental changes since the introduction.
US Army Corps of Engineers ® Engineer Research and Development Center West Bay Diversion Evaluation 1-Dimensional Modeling CWPPRA Technical Committee and.
Planning for Restoration of the Mississippi River in the Twin Cities Christian Lenhart.
Federal Columbia River Power System Operations Planning.
CHARLESTONMOBILE WILMINGTON SAVANNAH JACKSONVILLE US Army Corps of Engineers BUILDING STRONG ® NC Water Resources Congress Christine Brayman Deputy For.
Savannah Harbor Expansion Project
Susquehanna River Hydroelectric Projects 1 Shawn A. Seaman September 27, 2010 Image or Graphic.
US Army Corps of Engineers ® Engineer Research and Development Center Coastal and Hydraulics Laboratory Greenup Locks and Dam, Ohio River.
US Army Corps of Engineers BUILDING STRONG ® NC WATER RESOURCE CONGRESS ANNUAL RALEIGH MEETING Jim Medlock Chief, Programs Management Branch Wilmington.
February 26, 2003 Presentation in Clarksville, Virginia to the Bi-State Commission Overview of and Interlink of John H. Kerr, Philpott, and Private Hydropower.
Cape Fear River Fisheries Restoration: An Economic Engine October 31, 2013 Dawn York, Coastal Scientist October 31, 2013 Dawn York, Coastal Scientist.
US Army Corps of Engineers BUILDING STRONG ® U.S. Army Corps of Engineers St. Paul District Channels & Harbors Project Presentation for 2012 WEDA Midwest.
Status of Hudson River Fishes: Local and Regional Perspectives Karin E. Limburg, SUNY-ESF Kathryn A. Hattala, Amanda L. Higgs, Andrew W. Kahnle, Hudson.
Integrating Other Laws into BLM Planning. Objectives Integrate legal requirements into the planning process. Discuss laws with review and consultation.
Built New license studies & application Watershed analysis Settlement Agreement 2001 New License issued 2003 (Nov 13) New License.
Dam of the Day Bonneville Dam Duffy Dessalines September 27, 2001.
The Columbia River Basin Where we’ve been. Where we’re going. October 18, 2005.
BUILDING STRONG SM Partnering and Coordination to Accomplish the Navigation Mission.
InCom Working Group 127 Fish Passes Mark Cornish U.S. Army Corps of Engineers Rock Island District PIANC USA Annual Meeting 15 July 2008.
Estuaries By Dan Lawson. What is an estuary? An estuary is a coastal body of water which is openly connecting a freshwater stream with a saltwater environment.
OP-Navigation.ppt1 U.S Army Corps of Engineers Savannah District.
Are Kootenai River White Sturgeon Bad Parents or Have We Just Messed Up Their Habitat?
Wilmington Harbor Project - 96 Act Brannon Quel. Port of Wilmington The Cape Fear River serves as the shipping channel to the State Port in Wilmington,
USACE Managing a Drought  Overview  Timeline  Depletion Scenario Current Status– 17 Oct 07.
Effects of a Dam Removal on River Channel Morphology and Habitat Daniel Hayes Michigan State University First Note – make lettering so big it looks silly.
Estuary Actions for Salmon and Steelhead Columbia River Estuary Science Policy Exchange September 10-11, 2009 NOAA 2008 FCRPS Biological Opinion Estuary.
Fish Passage Lessons Learned on the Hudson River Hudson Valley Restoration Coordination Meeting Columbia Greene CC, Hudson, NY, Oct. 15, 2015 Curtis Orvis,
1. Water Trust Board Grant Agreement Scope and Objectives: Removal of islands below the Isleta Diversion Dam Restore this reach of the Rio Grande to the.
US Army Corps of Engineers BUILDING STRONG ® Mid-Columbia River Projects and Large Spill Events Ken Duncan Portland District PM Environmental Compliance.
NOAA’s National Marine Fisheries Service Biological Opinion for Water Supply, Flood Control Operations & Channel Maintenance by the Army Corps, SCWA, and.
BUILDING STRONG ® Rock Removal on the Middle Mississippi River 1 RRAT 2014.
Threatened and Endangered Species Issues on the Kennebec River, Maine
Historical Review Fish Migration Data. Two Management Approaches Spill for Fish Passage Planning dates Percent passage dates.
Fremont/Tisdale Sturgeon Rescues April 2011 Joseph Johnson Senior Environmental Scientist.
Penobscot River Restoration Project Projected Conditions Post-Dam Removal The Penobscot River Restoration Project is an unprecedented collaboration between.
SEPTEMBER 2013 SEACAP 3 rd Workgroup Call. Anadromous fish weighting scenario Results tiered into 5% bins-- the precise order isn’t as meaningful as the.
Pear River Navigation Canal Project Authorized by congress in Included channelization of the W. Pearl River, construction of 3 low head sills, an.
Wanapum Dam Total Dissolved Gas Characterization Evaluation of the Wanapum Dam Fish Bypass (WFB) 2008.
BUILDING STRONG ® St. Louis District Low Water Operations Russell Errett Water Control St. Louis District November 29 th, 2012.
Russian River Estuary Management.
Pa’s Most Mighty Migratory Fish
2016 FHWA National Hydraulic Engineers Conference
Building a Fishway for Sturgeon
LIFE HISTORY OF AMERICAN SHAD
Acipenseridae Family Sturgeons
Effects of persistent drought on Lake Mead and the Las Vegas Valley
Fish Passage Restoration at Roy’s Pools
Brian murphy and Emily valenzuela
North Carolina Surface Water Analysis
Roza Dam Evaluation Post Modifications
McNary Juvenile Fish Emergency Bypass System
Eightmile Creek Barrier Assessment
Web Page Up Date. Web Page Up Date Cape Fear River Lock and Dam #2 Scour Hole Repair, Elizabethtown, NC Client: Lambert Engineering, LLC and CJ Mehen.
LIFE HISTORY OF AMERICAN SHAD
Presentation transcript:

US Army Corps of Engineers BUILDING STRONG ® Rock Arch Rapids Fish Passage Cape Fear River Lock and Dam No.1 Bladen County, NC US Army Corps of Engineers Wilmington District NC WATER RESOURCES CONGRESS Annual Meeting October 31, 2013

BUILDING STRONG ® Reason for Fish Passage  Mitigation for blasting to deepen Wilmington Harbor  Major species of concern for blasting impacts: Endangered Shortnose & Atlantic Sturgeon  Fish passage increases likelihood of sturgeon reaching their traditional spawning sites upstream of Fayetteville and thus increasing population 2

BUILDING STRONG ® North Carolina Anadromous Fish (Fish that spend most of their lives in saltwater but run up rivers to spawn) Shortnose Sturgeon Acipenser brevirostrum Striped Bass Morone saxatilis 3

BUILDING STRONG ® All Three Cape Fear River Locks and Dams Are Located in Bladen County, NC 4

BUILDING STRONG ® Fish Passage Coordination Numerous on and offsite meetings and conference calls Consensus reached on rock arch rapids alternative Dr. Luther Aadland (MNDNR) involved in design and construction of more than 40 rapids including Lock and Dam # 1 5

BUILDING STRONG ® Fish Passage Alternatives  Removal of lock and dam –precludes navigation and public water supply  Modify existing locking procedures – already optimized  Rock arch rapids across the dam – selected alternative  Other alternatives o Short or long bypass channel – sturgeon not likely to find entrance o Fish lifts and ladders – high construction and maintenance cost and would clog with debris 6

BUILDING STRONG ® DAM 2 to 3’ diameter wearing/armor stone: Stones sized according to maximum shear stress in rapids 4 to 6’ diameter boulder weirs/vanes: Boulders sized to resist movement due to debris 25:1 SLOPE Conceptual Longitudinal Profile Rock Arch Rapids FLOW Boulder vanes are located about every 8’’ change in elevation and are about 20 feet apart. Adapted from Luther Aadland, MNDNR 5-12” Rock fill 7

BUILDING STRONG ® Rock Arch Rapids near Completion Cape Fear River, NC, Lock and Dam #1 Average spring flow ~ 6,000 cfs 8 ~2,000 cfs October 12, 2012

BUILDING STRONG ® Pre-Construction Fish Passage Monitoring  Only available fish passage is via locking o Fixed and mobile sonic tag monitoring stations o Tagged 50 striped bass and American shad each of 4 years o 50 to 65% of the American shad and 50 to 77% of the striped bass passed Lock and Dam #1 o Only 35% of the American shad and 25% of the striped bass passed all three locks and dams to reach their traditional spawning grounds above Fayetteville  Too few sturgeon available 9

BUILDING STRONG ® Post-Construction Fish Passage Monitoring  Passage via rock rapids, fish locking discontinued at L&D#1 o Interagency team developed 2-year post-construction monitoring plan. Monitoring collaborative effort lead by NCSU in the Spring of 2013 & NCDWR, NCWRC, NCDMF, NMFS, USFWS, Corps Goal: Minimum 80 percent passage of American shad, striped bass and flathead catfish pass Lock and Dam #1. Passage success = # fish that pass the dam/ # of fish that approach the dam, e.g. 40/50x100%=80% passage Too few sturgeon to assess passage - flathead catfish used instead o Similar to pre-construction monitoring using sonic tags to detect passage 10

BUILDING STRONG ® Monitoring Results & Future Actions  % tagged fish that passed Lock and Dam #1 in 2013 o 80% of Flathead Catfish Passed o 50% of American Shad Passed However appeared to be more shad at L&D#2 o 21% of Striped Bass Passed o Results have been coordinated with all resource agencies  2013 may not have been a representative year o Assess 2014 monitoring results before drawing conclusions on passage success 11

BUILDING STRONG ® Monitoring Results & Future Actions  Alternatives if 80% passage goal is not met in 2014 o Modify the rapids Create several wider pathways for fish passage o Augment passage by reinitiating locking  If modifications necessary, continue monitoring to determine success  Optimistic that the rapids will meet success criteria 12

BUILDING STRONG ® Questions? 13

BUILDING STRONG ® Extra Slides if Needed 14

BUILDING STRONG ® Rock Arch Rapids near Completion Cape Fear River, NC, Lock and Dam #1 Average spring flow ~ 6,000 cfs 15 ~2,000 cfs October 12, 2012

BUILDING STRONG ® Construction and Cost  Construction Window o No spring in-water construction to avoid anadromous fish migration  Rock Rapids o Began June 2011 o Completed November 2012  $13 million –filling 45’ deep scour hole, rapids and stabilizing lock wall 16