1 draft NO A WBS J. Cooper NO A Working Group Meeting June 29,2005 Work is the effort of Ron, Dave, Bill, Suzanne, Harry, not just me.

Slides:



Advertisements
Similar presentations
TPC Proposal for the 35 Ton Liquid Argon Test Abstract We propose to equip the 35 ton cryostat with one APA and two CPA’s, and all the necessary equipment.
Advertisements

Bill Miller NOνA-May 04 NOνA Total Active Liquid Scintillator Detector Installation First Pass Estimate Bill Miller U of M.
Mu2e WGM 6/15/2011 R. Ray Mu2e Project manager. Reviews We were on Lehman’s schedule for early August. We gave up that slot 2 weeks ago when it became.
23/04/2008VLVnT08, Toulon, FR, April 2008, M. Stavrianakou, NESTOR-NOA 1 First thoughts for KM3Net on-shore data storage and distribution Facilities VLV.
PALM-3000 Management Update A. Bouchez, J. Roberts Team Meeting #15 10/29/09.
MINER A NuMI MINER A DAQ Review 12 September 2005 D. Casper UC Irvine WBS7: Electronics and Data Acquisition  Overview (this talk): D. Casper  Front-end.
MINER A NuMI MINER A DAQ Review 12 September 2005 D. Casper UC Irvine WBS 7.2 & 7.3: Data Acquisition D. Casper (UC Irvine)
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
Hall D Online Data Acquisition CEBAF provides us with a tremendous scientific opportunity for understanding one of the fundamental forces of nature. 75.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
Mu2e WGM 7/27/2011 R. Ray Mu2e Project manager. Director’s Review We have settled on date for the Director’s CD-1 Review; Oct Focus of review will.
HPS Budget and Schedule Marco Oriunno, June 4-6, 2013 HPS Collaboration Meeting, JLAB.
Manchester Partnership Community Engagement Strategy, Guide and Website Angela Corf Senior Programme Officer, Community Engagement March 2011.
David Finley / LArTPC Group Meeting / June 13, Fermilab Slide 1 LArTPC Detector Costs Context History Next (perhaps) steps.
NoVA FNAL Engineering Needs 9 February 2009 Dave Pushka.
August 2 and 3, 2010 Project Cost, Schedule, Risk and Contingency Jay Elias.
Cost for Large Liquid Scintillator Detector Ken Heller University of Minnesota Active Detector – Liquid Scintillator Target Material - Water Read Out –
NOvA Project Status April 3, 2007 John Cooper Ron Ray Nancy Grossman.
Global Design Effort Americas Region Efforts and Resources Mike Harrison GDE.
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
Extrusion Modules – The Active Detector Ken Heller University of Minnesota Talks by: Tom Chase – Progress on End Seals and Leak Detection QA Alex Smith.
Status of the NO ν A Near Detector Prototype Timothy Kutnink Iowa State University For the NOvA Collaboration.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
International Linear Collider The ILC is the worldwide consensus for the next major new facility. One year ago, the choice was made between the two alternate.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
NO A Project Status John Cooper & Ron Ray October 18, 2006.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
Mu2e Cost and Schedule Ron Ray Mu2e Project manager Fermilab PAC Meeting November 3-4, 2008.
TOF Project Construction Project Plan
Director’s Review 5/5/03 Spalding DRAFT RLS 1 Project Planning  Documentation to DOE June 1  DOE Review ~July 22 Documents Summary Project Overview,
ILC US detector R&D H.Weerts, Argonne Nat. Lab. Status & progress in the US Organizational status.
Philip Burrows SiD meeting, Chicago 15/11/081 Progress on the LoI Philip Burrows John Adams Institute Oxford University Thanks to: Hiro Aihara, Mark Oreglia.
P.NapierEVLA Advisory Comm, 14 Dec 2004 Project Overview Peter Napier, EVLA Project Manager Status 2003 Committee Response.
Report from MICE project teams Feedback from PPRP MICE funding: various scenarios Issues  Financial year 2003/04  iMICE common fund.
Gary Feldman MINOS in Cambridge 24 March NO A Update MINOS Collaboration Meeting Cambridge, England 24 March 2009 Gary Feldman.
F Axis NO A Status NO A Collaboration Meeting Fermilab 17 November 2006 Gary Feldman.
Mark McKinnon NSF Mid-Project Review May 11-12, Baseline Project Definition Mark McKinnon Project Manager.
DoE Review June 6, 2000 Cost Estimate  New Cost Estimate u Manpower Costs (Op. SWF) u Equipment Costs (Eq. M&S) u Contingency  Conclusions Mike Tuts.
DUSEL Beamline Working Group Meeting March 09, :00 AM – Snake Pit (WH2NE) By Dean Hoffer - OPMO.
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
Pcubed MPUG 12/2/04 Presentation 1 The realities of a Project-Specific PMO Microsoft Project User Group Quarterly Meeting December 2 nd, 2004 Celine Gullace,
LIGO-G M Advanced LIGO Cost, Schedule and Management Gary H Sanders NSF Review of Advanced LIGO Caltech, June 11, 2003.
AVAILABLE Will Build to Suit Could the University of Minnesota do this? –Alternate to Line Item or to a DOE grant? from Marvin Marshak (in the Middle.
Off-Axis Collaboration Meeting Feb 7, 2004 Richard Talaga, Argonne (Liquid) Scintillator Structure Workshop Report Workshop Purpose –To review the current.
US CMS DOE/NSF Review: April 11-13, Trig. - Estimate to Complete.
Proton Driver Resources & Schedule (R&D Plan) Rich Stanek May 10, 2005.
AGS RSVP Weekly Meeting P. Pile 6 Jan 2005 AGS RSVP Weekly Meeting 6 Jan 2005 Useful Links: RSVP Project : C-AD.
NOvA Project Status February 6, 2007 John Cooper Ron Ray Nancy Grossman.
Eric Prebys LARP Program Director July 14, LARP FY10 and Beyond - E. Prebys 2 Guidance: LARP funding decreases $1M/yr Assume: $13 M LARP total for.
Status of the NOνA Experiment Satish Desai - University of Minnesota For the NOνA Collaboration APS Meeting - April 2013 Denver, Colorado.
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
1 Project Integration Using MS Project PMI Scheduling Forum June 2, 2009 Presented by: Ric Albani.
09/05/2006Project Status Report1 Nova DAQ Software Development Project Status Update for 09/05/2006 Gerald Guglielmo (CD/CEPA/OAA)
Workshop summary Outline  Workshop’s aims  Highlights from the presentations (my selection!)  Costing Exercise – What we learnt  Summary - Roadmap.
K. Long, 25 June, 2016 IDR: structure and overall timeline: Slides are to introduce discussion of how we prepare IDR. Propose to revise slides as we discuss.
FISCO2 – Financial and Scientific Coordination Work Package dedicated to ENSAR2 management WP leader: Ketel Turzó WP deputy: Sandrine Dubromel ENSAR2 Management.
MUSE NSF Review March 24, MUSE Project Management Ronald Ransome Rutgers The State University of New Jersey For the MUSE Collaboration.
Hall D Computing Facilities Ian Bird 16 March 2001.
Jim Fast Pacific Northwest National Laboratory
Completion and Pre-Exploitation Costs for the Initial ATLAS Detector
WBS 1.03 Readout Systems Scope, Cost and Schedule
EDR HLRF Work Packages Draft Summary
S4 will be a “big” Collaboration:
DOE: Transition from MIE to Early Operations Kevin Reil LSST Camera Commissioning Lead LSST Commissioning Plan Review January 24-26, 2017.
Preparations for a Lehman Review
Remarks on US Costing Activities for the US ITER-TBM
RF System (HLRF, LLRF, Controls) EDR Plan Overview
Update on progress since last WG meeting (13-14 June 2002)
Preliminary Project Execution Plan
Presentation transcript:

1 draft NO A WBS J. Cooper NO A Working Group Meeting June 29,2005 Work is the effort of Ron, Dave, Bill, Suzanne, Harry, not just me.

2 draft NO A WBS J. Cooper, Project Manager R. Ray, Deputy

3 Far Site, 1.1 – 1.7 Starting now with the EAW process Major work Maybe 2 contractors, maybe 1 RGU complication mostly applies here This “outfitting” is tied to the building Crucial to proper containment Need “Roads & Grounds” during Detector assembly phase Safeguards & Security Under Lab / University umbrellas except at Far Site Value at scattered assembly sites is low, major value is at Far site e.g. thinking security fence, video surveillance, gates, …. $ 7.4 M $ 13.7 M $ ? $ ~ 3.0 M ~ 19 % of cost + contingency $ 6.8 M

4 Strategic Materials, 2.1 – 2.3 All are large phased procurements Value management will dictate competition e.g. 2 extrusion vendors with 33% each? Mix vs. buy scintillator? All have cost fluctuation problems $ to Yen Price of crude oil Together they dominate the detector cost + contingency therefore the cost risk & contingency All have a common thread of QA Sustained over several years, often done on the same object in several places All need to aim for conservative HEP version of “just in time delivery” to the far site Delivery from vendors within our cost profile Delivery to the sites where the raw materials are needed Need to minimize storage $ 20.0 M $ 34.8 M ~ 44% of cost + contingency $ 17.4 M 27,000 km 7.5 M gallons, 24 kt 374 km, 6 kt Structural, but also light gathering

5 Near structure identical to Far, so can roll each up Except add “fast electronics” task to Near – this is 5 planes only Far is now the assembly of 24,000 objects of various kinds APDs, TE coolers, ASICs, PC boards Module factories –Manifolds and bottom closures Trigger / DAQ (underestimated?) –But is a large fraction of the EDIA –Supernova complication? –Slow controls… & Final Assembly at Far Site Block Raiser, Assembly tables Crew NO A Detectors 3.1 – 3.3 ~ 23 % of cost + contingency $ 3.1 M “no cost” $ 2.8 M $ 0.4 M $ 10.1 M $ 8.1 M $ 13.5 M

6 Level 4 Details in Detector 3.1 One module part is structural and dear to heart of “Assembly 3.1.5” Scintillator Distribution & QA is now the act of filling extrusions, separate from the building distribution task in 1.

7 Details of Simulations Why is this in the Project? Needs structure, leaders Direct feedback in many cases to project scope / details Could correlate with total mass May imply design changes Near Detector details E.g. move up slope if LSND confirmed Overburden question Prototype Near, Final Near Must carry calibrations to Far “no cost” since thought to be all scientist effort So having this in the project allows us to track the total scientific effort better “DOE liked this for BTeV” ??

8 Project Management 4. Project Office - $ 4.7 M SWF for non-scientists Travel, computing $ 14.1 M of “additional contingency” listed in proposal stashed here Expect to farm this out to other WBS elements in resource loaded schedule exercise i.e. not for Director’s Review ~ 12 % of cost + contingency

9 draft NO A WBS Comments Need Near subtasks in Strategic Materials if we are to roll up a real total for Near Suzanne notes the Detector roll-up has an additional level, implies two financial reports…. Add some Level 2 task and make 1,2,4 at Level 2 below that?

10 draft NO A WBS MORE Comments Do we want to include the R&D in this “project”? Want to duplicate structure to track it anyway? Should start with FY05 The “$ 165 M” cost does NOT include the R&D –Additional ~ $ 3 M of M&S –Additional ~ $ 3 – 4 M of SWF (crude estimate) –Mike Procario heard these numbers February 28, –The March 2005 NO A Proposal is consistent with these numbers.

11 draft NO A WBS - Level 1 Managers? S. Dixon ?R. RayJ. CooperJ. Cooper / S. Pasek / K. Kephart ? J. Cooper, Project Manager R. Ray, Deputy Clearly would depend on 3 strong Level 2 managers

12 More structure, not WBS PMP usually shows Project  PPD  Directorate  DOE, line management Collaboration with Spokespersons to one side in a separate line –NO A has an Executive Committee Project might have a Technical Advisory Committee to the Project Manager –Composed of Level X managers + a few more? So eventually the structure is way more complicated than shown today