To grid or not to grid Vijay Modi Professor, Earth Institute and Columbia Engineering
80
Ayse Selin Kocaman / Modi Research Group
Ayse Selin Kocaman / Modi Research Group Sounds simple, but where exactly people live was not obvious from census data
Ayse Selin Kocaman / Modi Research Group Mean Cost Calculations (MID) Results for Different Dispersion of Structures
Ruhiira, Uganda: 200 km 2, Southern Uganda (near Mbarara)
Data Acquired for: – Households – Institutions – Commercial – Productive use Unit Type Number Education 27 Health 6 Markets 27 Grinding Mills 32 Household Clusters 399
> 13,0000 Households (from satellite imagery) can be clustered into ~400 demand points Min # HHs = 1 Max # HHs = 253 Average = 33
Demand Estimates: Electricity Consumption data and estimates are made for electricity demand at all points (kWh/year)
Input data: Facilities and Household Clusters Unit Type Number Education 27 Health 6 Markets 27 Grinding Mills 32 Household Clusters 399
Grid Connection
Off-Grid Connection Points in darker shades are those with off-grid connection
Percentage of Grid vs Off-Grid Coverage
Decision-making thru data (WB Report) Local Priorities and Constraints Roll-out plans and timelines with costing Rural and national linked
Senegal, national planning
Photograph Credits: Jose Barnuevo Potou cluster, SENEGAL, first Electricity for social institutions Stand-alone technologies mini-grids Local Level Planning and Priorities Grid extension
Roll-out: By Branch (MV) Connect most cost-effective branches first Phase 1 < 20 Phase 2 20 – 25 Phase 3 > 25 Investment per capita
Africa-Wide Transmission Scenario