Global Design Effort CLIC-ILC BDS & MDI work Materials for discussion Daniel Schulte, Rogelio Tomas and Emmanuel Tsesmelis for CLIC team Andrei Seryi for.

Slides:



Advertisements
Similar presentations
Global Design Effort Goals and Introduction Andrei Seryi, SLAC, September 17, 2007.
Advertisements

Global Design Effort Beam Delivery System & Machine Detector Interface Andrei Seryi, SLAC Annual DOE HEP Program Review June 11-14, 2007.
Summary of wg2a (BDS and IR) Deepa Angal-Kalinin, Shigeru Kuroda, Andrei Seryi October 21, 2005.
BDS GDE context LC-ABD2 : WP4 - Beam Line Design 12 th April 2007, LC-ABD Plenary, RHUL Deepa Angal-Kalinin ASTeC, The Cockcroft Institute.
NLC - The Next Linear Collider Project NLC IP Layout What’s New? Tom Markiewicz LC’99, Frascati, Italy October 1999.
NLC - The Next Linear Collider Project NLC IR Layout and Background Estimates Jeff Gronberg/LLNL For the Beam Delivery Group LCWS - October 25, 2000.
ILC BDS Collimation Optimisation and PLACET simulations Adina Toader School of Physics and Astronomy, University of Manchester & Cockcroft Institute, Daresbury.
ILC BDS Collimation Optimisation and PLACET simulations Adina Toader School of Physics and Astronomy, University of Manchester & Cockcroft Institute, Daresbury.
A.Seryi, Oct. 26, BDS comparison and positron source A.Seryi October 26, 2005 Discussion of BDS and positron source is given in [1] “Comment on.
NLC - The Next Linear Collider Project IR Working Group Summary Tom Markiewicz LC R&D Workshop, UCSC June 29, 2002.
European Design Study Towards a TeV Linear Collider WP 2 : Beam Delivery System Co-ordinator: Deepa Angal-Kalinin CCLRC, Daresbury Laboratory.
July 7, 2008 SLAC Annual Program Review Page 1 Andrei Seryi, SLAC American Regional Team leader for BDS Deputy of ATF Spokesperson for ATF2 Global Design.
Beam Delivery System Review of RDR(draft) 1.Overview 2.Beam parameters 3.System description 3.1 diagnostic, tune-up dump, machine protection MPS.
ILC Beam Delivery System Layout and Lattice Design Deepa Angal-Kalinin ASTeC, Cockcroft Institute Cockcroft Institute SAC th November 2006.
November 07, 2006 Global Design Effort 1 Beam Delivery System updates BDS Area leaders Deepa Angal-Kalinin, Hitoshi Yamamoto, Andrei Seryi Valencia GDE.
Global Design Effort Push-pull studies How to proceed LCWS07 June 1, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi.
February 26, 2007 Global Design Effort 1 Most recent in Beijing BDS/IR talk, February 4, 2007:
UK/EU Plans for ATF2 G.A. Blair ATF2-IN2P3-KEK kick-0ff meeting, Annecy, 8 th October 2006 Overview EUROTeV UK.
ILC MDI Andrei Seryi JAI with input from many colleagues working on MDI IWLC
Global Design Effort Beam Delivery System => EDR LCWS07 June 2, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi Yamamoto.
D. Angal-KalininEUROTeV Annual Meeting, DESY WP2 : Beam Delivery System D. Angal-Kalinin ASTeC, STFC, Daresbury Laboratory 4 th EUROTeV Annual.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
Feedback On Nanosecond Timescales (FONT): Robert Apsimon, Philip Burrows, Neven Blaskovic, Douglas Bett, Glenn Christian, Michael Davis, Davide Gamba,
SiD IR & MDI Engineering Progress Prelude to a Discussion of Integration with ILD and Based on Marco Oriunno’s Jan 2008 Talk at SiD CM Tom Markiewicz/SLAC.
ILC Beam Delivery System / MDI Issues for LCC-phase (~
11th December 2007 LET workshop, SLAC 1 Beam dynamics issues in Beam Delivery System Deepa Angal-Kalinin ASTeC, Daresbury Laboratory.
BDS Andrei Seryi, Deepa Angal-Kalinin, Emmannual Tsesmelis, Rogelio Tomas, Andrea Latina, Daniel Schulte Detectors Civil engineering.
Global Design Effort ILC Crab Cavity Overview and requirements Andrei Seryi SLAC on behalf of ILC Beam Delivery and Crab-Cavity design teams Joint BNL/US-LARP/CARE-HHH.
Interaction Region Issues and Beam Delivery R&D Issues & IR Design Status R&D Plans T. Markiewicz Klaisner Review 4/15/1999.
ILC Beam Delivery System and ATF2 design Andrei Seryi SLAC for BDS design team May 25-30, 2008, Budker INP, Novosibirsk, Russia.
Philip Burrows Snowmass 2005: SiD Concept Plenary, 15/8/05 SiD and MDI issues Philip Burrows Queen Mary, University of London Thanks to: Toshiaki Tauchi,
Interaction Region & IR integration EDR Planning Tom Markiewicz/SLAC SLAC BDS Kick-Off-Meeting 13 October 2007.
CLIC Workshop, CERN 1 CLIC/ILC Collaboration Report: Marc Ross (Fermilab); for Nick Walker, Akira Yamamoto Project Managers International Linear.
October 20, 2006 Global Design Effort 1 ILC Interaction regions : The GDE perspective Talk based on several talks presented by BDS area leaders Andrei.
February 05, 2007 Global Design Effort 1 Beam Delivery System R&D S4 Task Force Chris Damerell, Hitoshi Hayano, Marc Ross Deepa Angal-Kalinin, Andrei Seryi,
BDS: 1 October 13, 2007 BDS KOM EDR planning discussion Andrei Seryi October 13, 2007.
CLIC Machine-Detector Interface Working Group (MDI) Emmanuel Tsesmelis CERN TS/LEA CLIC-ACE of 3 September 2008.
NLC - The Next Linear Collider Project Machine-Detector Interface Tom Markiewicz LC R&D Opportunities, SLAC May 21, 2002.
March 3-6, 2008 Global Design Effort 1 BDS way forward summary for GDE-BDS Andrei Seryi, SLAC Thanks to all participants of GDE-BDS and ACFA-MDI sessions.
MDI towards technical design Lau Gatignon. Very preliminary ! To trigger discussions.
Low Emittance Generation and Preservation K. Yokoya, D. Schulte.
SiD Collaboration Meeting Highlights Tom Markiewicz/SLAC ILC BDS Meeting 08 May 2007.
Global Design Effort Beam Delivery System Summary Andrei Seryi, SLAC ALCPG/GDE meeting October 25, 2007.
Beam Delivery system design and plans Andrei Seryi SLAC on behalf of BDS design team ILC08 and LCWS08 17 November 2008 Illustration of beam dump with double.
Introdcution to Workpackage/Activity Reflection D. Schulte.
Beam Delivery (wg4) update since Snowmass Andrei Seryi for WG4 GDE meeting December 8, 2005 Snowmass 2005 GDE Meeting at INFN-LNF.
CERN, 27-Mar EuCARD NCLinac Task /3/2009.
Global Design Effort Progress and Plans of the Beam Delivery Systems and Machine Detector Interface WG Daniel Schulte (CERN), Brett Parker (BNL), Andrei.
FP7: EuCARD after a year of preparation… A.Jeremie.
IWLC10, 18 th -22 nd October10, CERN/CICG 1 Global Design Effort Updates to ILC RDR Beam Delivery System Deepa Angal-Kalinin & James Jones ASTeC, STFC.
BDS/MDI Deepa Angal-Kalinin Andrei Seryi AD&I Meeting, DESY, May 29, 2009.
Accelerator WG 5 summary Interaction region, ATF2 and MDI Deepa Angal-Kalinin, Lau Gatignon, Andrei Seryi, Rogelio Tomas IWLC
Beam Delivery System Summary Andrei Seryi LCWS 2010 / ILC 2010 March 30, 2010.
The design of the 2mrad extraction line Rob Appleby Daresbury Laboratory On behalf of the SLAC-BNL-UK-France task force ILC European Regional Meeting and.
Task 9.4 Beam Delivery System CERN, 27-Mar /3/2009
Machine Detector Interface Design Updates
Near IR FF design including FD and longer L* issues
DOE/NSF FY08 Americas Regional Team Review
Beam Delivery Systems and the Machine-Detector Interface Terms of Reference for the CLIC-ILC Collaboration Working Group B. Parker (BNL), D. Schulte.
Beam Delivery update Andrei Seryi December 12, 2005
CLIC Study Aim Conceptual design report in 2010
CLIC-ILC BDS & MDI work.
MACHINE DETECTOR INTERFACE WORKING GROUP STATUS
CLIC Detector studies status + plans
CLIC Detector CERN Status + plans
Beam Delivery System Schedule at ILC2010
Andrei Seryi Materials for discussion TILC-08
CLIC damping rings working plan towards the CDR
A 12-min Introduction to The ILC Machine Detector Interface and SiD
BDS EDR Discussion EDR Organisation? Discussion of WP distribution
Presentation transcript:

Global Design Effort CLIC-ILC BDS & MDI work Materials for discussion Daniel Schulte, Rogelio Tomas and Emmanuel Tsesmelis for CLIC team Andrei Seryi for ILC BDS team February 8, 2008

Global Design Effort 2 Feb 8, 2008, CLIC-ILC BDS Strategy Looking forward to work with CERN and CLIC colleagues Consider this as a natural continuation of long and fruitful collaboration Expect that challenging scientific tasks will benefit ILC and CLIC research, and both short and long term program of involved institutions Expect that ideas and solution would have broad applicability and we will be proactive in search of such opportunities

Global Design Effort 3 Feb 8, 2008, CLIC-ILC BDS Fruitful history => future ATF2, a prototype of advanced final focus for linear collider, was conceived at Nanobeam 2002, organized by CERN Idea evolved, and now being realized in iron and concrete Now looking forward to work with CERN colleagues on experiments at this facility L.Maiani J.Urakawa R.Assmann, F.Zimmermann Early scheme presented by Junji

Global Design Effort 4 Feb 8, 2008, CLIC-ILC BDS ATF2 Scaled down model of ILC final focus at KEK The ATF international collaboration include more than 200 researchers and the ATF MOU is signed by 20 institutions from all over the world

Global Design Effort 5 Feb 8, 2008, CLIC-ILC BDS ATF2 construction – January 2008 The last regular quadrupole is going to the destination

Global Design Effort 6 Feb 8, 2008, CLIC-ILC BDS Collimation beam Consumable collimators developed for NLC Concept applied for LHC phase II collimation Will be studied for CLIC T.Markiewicz at al

Global Design Effort 7 Feb 8, 2008, CLIC-ILC BDS Optics optimization Tools developed for optimization of beam delivery will be mutually used for further improvement of the designs R.Tomas, CLIC BDS optimization ILC BDS optimization

Global Design Effort 8 Feb 8, 2008, CLIC-ILC BDS Extended stabilized object SLAC CERN, now Annecy Small stabilized object SLAC Nonmagnetic inertial sensor Stability Long history & potential for future joint developments MONALISA at ATF2 interferometer to monitor FD stability D.Urner et al

Global Design Effort 9 Feb 8, 2008, CLIC-ILC BDS IR integration (or MDI) Variety of common interest tasks Focus of joint activity 8cm 20cm 113mrad 47mrad QD0 Mask Bcal Ex. BeamPipe

Global Design Effort 10 Feb 8, 2008, CLIC-ILC BDS 2m Spacer structure QDF Shielding Rails on the support tube QD0 He2 cryoline Dogleg cryo-line in the Pacman Marco Oriunno, SLAC IR integration, SiD example

Global Design Effort 11 Feb 8, 2008, CLIC-ILC BDS SC final double & its stability study Brett Parker et al BNL

Global Design Effort 12 Feb 8, 2008, CLIC-ILC BDS Alain Herve, CERN, et al Push-Pull studies for two detectors

Global Design Effort 13 Feb 8, 2008, CLIC-ILC BDS Detailed lists of tasks In preparation for CLIC-ILC meeting on February 8, a phone meeting was held on January 28. Participants: Andrei Seryi, representing GDE BDS & MDI, and Daniel Schulte, Rogelio Tomas, Emmanuel Tsesmelis and Andrea Latina (CLIC), representing CLIC BDS&MDI efforts Second preparatory phone meeting, Feb 5. Participants: Daniel Schulte, Rogelio Tomas, Emmanuel Tsesmelis and Andrea Latina for CLIC, and Andrei Seryi, Brett Parker, Tom Markiewicz and Deepa Angal-Kalinin for GDE BDS & MDI Lists being developed (see next pages) Next milestones –Identify contact persons for different tasks –Identify solutions for LHC that can be applied to ILC and CLIC –Identify solutions for ILC that can be applied to CLIC

Global Design Effort 14 Feb 8, 2008, CLIC-ILC BDS Detailed lists being developed… Optics design and optimization Collimation system Final focus system Extraction line Design concepts Optmisation tools Tracking tools Collimators Survival Wakefields ATF2 Tuning procedures Flight simulator Energy spectrometer Polarimeter Beam dump Crab cavity Design Phase stability Beam instrumentation BPMs Laser wires Extraction line instrumentation Feedback design Beam-based alignment and tuning procedures Survey Stabilisation Magnets and power supplies Final doublet design Intra-pulse IP feedback BPM for intra-pulse feedback Integration of corrector kicker Feedback design

Global Design Effort 15 Feb 8, 2008, CLIC-ILC BDS Detailed lists being developed… Background studies Common simulation tools BDSIM Integration into GEANT? FLUKA Halo and tail generation Common formats etc Study of machine induced background In particular, neutrons, muons and synchrotron radiation Mitigation strategies e.g. tunnel fillers against muons Study of beam-beam background and luminosity spectrum Support and stabilization Low-noise design Noise level measurements Among others, measurements at LHC Component design Mechanical design of quadrupole support Stabilization feedback design Sensors Actuators Inner/forward detector design General layout and integration Masking system Constraints on vertex detector Common tools for detector studies Low angle calorimeter Beam pipe design Vacuum etc. Crossing angle Try to find a common crossing angle Experimental area integration (to be done with other groups) Infra-structure Push-pull