Town of Genoa October 6, 2015. Agenda Why are we here? Background Capacity Analysis & Facilities Plan Preferred Alternative Board Direction Implementation.

Slides:



Advertisements
Similar presentations
Agreement between the Village of Owego and Inflection Energy.
Advertisements

Wakulla County Sewer Project Eutaw Utilities Presentation April 7, 2011.
Status of Wastewater Implementation February 20, 2013 Elizabeth Wood Monroe County, Sr. Administrator – Sewer Projects.
Stanlick Sewer Treatment Plant Upgrade Implementation Date: September 1, 2008.
Floyd County Board of Commissioners Special Town Hall Meeting Topic: Update on status of Georgetown WWTP.
PROPOSITION 218 IMPACTS ON UTILITY USER FEES Case Study City of Dixon Sewer Rate Repeal of 2007.
Article 41 Wastewater Planning Capacity Study To determine whether the Town will vote to adopt a resolution supporting the Town Manager’s allocation of.
City of South Burlington City Council Adopted January 12, 2013 FY 2014 Budget - Keys to Financial Success Prepared by Sandy Miller, City Manager and Bob.
How to Use the Clean Water State Revolving Fund SRF Overview Planning Intended Use Plan Application Environmental Review Bidding and Construction Construction.
Commercial-type activities of a government, such as public utilities:  Water and sewer authorities—either fully independent or component units of local.
1 Wastewater Capital Improvement Program (CIP) Large Users Meeting March 15, 2010.
City of Farmersville, Texas Water and Wastewater Rate Study February 2011.
Cuba’s Future Development Needs, Funding Models, and Alternatives. A Perspective of the Operation of a Cuban Water & Sewer Utility. Eduardo Vega-Llort,
AIRPORT AREA INFRASTRUCTURE TIF DISTRICT: Public Hearing Presentation Oct 21, 2013.
Presentation to CITY OF PALM COAST, FLORIDA WATER AND WASTEWATER RATE STUDY AND BOND FEASBILITY REPORT Prepared in Conjunction with the Issuance of Utility.
Ohio Planning Conference Transportation Connects Ohio 1 Rich Winning Ohio Department of Transportation Acting Deputy Director, Division of Finance July.
Report on Investment Strategy for the Commercial Paper Program Vernon D. Evans Vice President for Finance/ Treasurer Item 7 January 3, 2008.
JOINT LEGISLATIVE AUDIT COMMITTEE HEARING SENATE BUDGET and FISCAL REVIEW COMMITTEE Delivering Energy Savings for California AMERICAN RECOVERY & Karen.
+ Proposed Lockwood Targeted Economic Development District 2015 Yellowstone County.
Federal, state and local government entities working together to meet the health, welfare and public safety needs of Wyoming’s citizens. January 11, 2011.
2013 City Budget Manhattan ~ Kansas Work Session Two.
Council Workshop, February 24, Image Date: 1/15/2014 Future WWTF No. 2 Capacity 2.0 MGD., Expandable to 6.0 MGD. Future WWTF No. 2 Capacity 2.0.
Presentation to CITY OF PALM COAST, FLORIDA WATER AND WASTEWATER RATE STUDY AND BOND FEASBILITY REPORT Prepared in Conjunction with the Issuance of Utility.
Metropolitan Council Environmental Services A Clean Water Agency Presented to the Environment Committee March 22, 2011 Info Item: East Bethel Update Bryce.
Pasadena Water and Power APPROVE A PROJECT CONTINGENCY AMOUNT OF $2,500,000 FOR EXISTING CONTRACTS RELATED TO THE LOCAL GENERATION REPOWERING PROJECT -
Water Supply Planning Initiative State Water Commission November 22, 2004.
Economic Incentive Plan and Impact Fee Update Board of County Commissioners Work Session February 7, 2012.
Independent Review of FY 2008 Proposed Rates D.C. Water and Sewer Authority Public Hearing June 13, 2007.
Redevelopment Grant Program Implementation Workshop Spring 2010.
KENTUCKY INFRASTRUCTURE AUTHORITY GOVERNOR’S LOCAL ISSUES CONFERENCE August , 2011.
Texas Water Development Board Financing Programs Presentation by Ignacio Madera, Jr. Office of Project Finance & Construction Assistance December 2, 2003.
Council Workshop, June 24, Image Date: 1/15/2014 Future WWTF No. 2 Capacity 2.0 MGD., Expandable to 6.0 MGD. Future WWTF No. 2 Capacity 2.0 MGD.,
Wastewater Treatment Plant # 2 Engineering Services Council Workshop July 8, 2014.
Canaan Valley Tucker County, West Virginia Decentralized Wastewater Management Facility Plan July 28, 2005 Pio Lombardo, P.E Lombardo Associates, Inc.
Department of Environmental Quality Water Infrastructure November 17, 2015 Water Infrastructure Funding to Financing.
Department of the Environment Maryland Water Quality Revolving Loan Fund Financing Stormwater Infrastructure Jag Khuman, Director Maryland Water Quality.
Road Map to the Future: The Consolidation of Sewer Infrastructure in Rutherford County, NC November 16 th, 2015.
Fiscal Year Revenues and Expenses  Recurring Revenues Fund Recurring Expenses Property Taxes State Aid Estimated Local Receipts Other Available.
Ledyard Wastewater Facilities Management Plan A Presentation to the Ledyard Town Council/ Water Pollution Control Authority By Maguire Group Inc. January.
FEBRUARY 22, 2016 FY 2017 County Administrator’s Recommended Budget.
Long-Term Financial Planning Plan of Finance 1 Debby Cherney, Deputy General Manager Charles Turner, Director of Finance
RATE ANALYSIS FY FY 2019 March 6, 2014 CARSON VALLEY WATER UTILITY FUND 326 – DEPARTMENT 864.
1 EASTERN MUNICIPAL WATER DISTRICT Temecula Valley Regional Water Reclamation Facility 23-MGD Expansion Project Joe Mouawad, P.E. Senior Director.
1 EASTERN MUNICIPAL WATER DISTRICT Temecula Valley Recycled Water Pipeline Joe Mouawad Sr. Director of Engineering September 2, 2015.
Wastewater Treatment and Disposal Upgrade Nampa Wastewater Advisory Group Meeting #10 October 9, 2012.
Wastewater Treatment Plant No. 2 Construction Contract City Council Workshop February 9, 2016.
City of Fernley, Nevada – 164 th Ave. NE, Suite 300, Redmond, WA April 18, 2007 Rate Study Findings Water and Sewer Utility Rates.
Phase II and Compost Facility Upgrade Projects February 16, 2012.
Operating Efficiencies Costs to operate and maintain the water and sewer system have not varied significantly during the first 5 years of operation.
Orange County Water and Wastewater Utility Bonds, Series 2016 Discussion Agenda March 15, 2016 Orange County.
Presentation to CITY OF PALM COAST, FLORIDA FINANCIAL FORECAST AND CAPITAL FACILITIES FEES ANALYSIS Prepared in Conjunction With the Utility System Revenue.
1 City of Cocoa Michael Burton - President Andrew Burnham - Senior Vice President Ashley Venturoni – Project Consultant Presented by: FY 2013 Water, &
City of Fernley, Nevada – 164 th Ave. NE, Suite 300, Redmond, WA April 18, 2007 Rate Study Findings Water and Sewer Utility Rates.
Financial and Capital Highlights Fiscal Year Second Quarter Charles Turner, Director of Finance
PARK STREET/CAMPANELLI PARK SEWER EXPANSION PROJECT Public Meeting Wednesday, June 22, 2016.
Loan Programs.  What is the PFA?  How does PFA financing work?  What is the Capital Financing Program?  What is the State Revolving Fund Program?
FY 2017/18 General Budget Workshop
Fund Accounting Overview
Water & Wastewater Capacity Charge Work Shop
Final Rate Study Findings
City of Rialto Midyear Changes Budget-Fiscal Year 2012/2013
Recycled Water Project – Sharon Heights GCC
CITY OF MARSHALL CHLORIDE ISSUES September 26, 2017
Financial Audit Presentation Year Ended June 30, 2017
Joshua Basin Water District Revised Rate Recommendations
ELECTRIC REVENUE REFUNDING BONDS SERIES 2016A
Successor Agency to the PCDC FY 2017 Recommended Budget
Article 41 Wastewater Planning Capacity Study
City of Rehoboth Beach Water and Wastewater Financial and Rates Review
Funds for Clean Energy: Overview of Programs & Schedules
Presentation transcript:

Town of Genoa October 6, 2015

Agenda Why are we here? Background Capacity Analysis & Facilities Plan Preferred Alternative Board Direction Implementation Schedule Funding Redevelopment Agency “RDA” Service Area Map Findings and Conclusions 2

Why are we here? Public Works is in the process of developing a comprehensive finance plan to fund the expansion of the North Valley Wastewater Treatment Facility. Public Works is recommending to the Douglas County Redevelopment Agency (“RDA”) the use of RDA funds to assist in the project funding. NRS (4) (b) requires the Board to consider the opinions of persons who reside in the redevelopment area or the immediate neighbor in which the redevelopment area is located. 3

Background 1. Discharge permit requirement(s) B.TF.8“The Permittee shall notify the Administrator… after the 30-day average daily influent rate first equals or exceed 85% of the design treatment capacity… The letter shall include:” B.TF.8.4“A status report on the treatment works which will outline… modifications to the treatment works which are needed to attain the permitted flow rate…” B.TF.8.5“The Permittee’s schedule of compliance to provide additional treatment capacity before the 30-day average daily influent flow rate equals the present design treatment capacity of the Permittee’s facility.” Douglas County has ~150 EDUs of remaining capacity under ideal conditions 4

Capacity Analysis & Facilities Plan Non-Capacity Deficiencies Capacity Deficiencies Evaluate five (5) alternatives Alternative Analysis Five (5) Alternatives Economic Evaluation (Project Cost, Cost per gallon) Non-Evaluation (Reliability, Operability, etc.) Life Cycle Cost Analysis 5

Preferred Alternative Construct Alternative LT-2 Sequencing Batch Reactor & Partial SH-2 Geotextile Dewatering Total Project Cost $7.5 Million 6 Rolling A SBR, Dayton, NV

September 3, 2015 Board Direction Adopt the Facility Plan and Capacity Analysis with Alternative LT-2 Treatment – Sequencing Batch Reactor (“LT-2 SBR”) coupled with SH-2 Geotextile Dewatering (“SH-2 GD”) as the preferred and recommended project. Direct Public Works to begin the solicitation process to hire a design consultant for the implementation of Alternative LT-2 Treatment – Sequencing Batch Reactor (“LT- 2 SBR”) coupled with SH-2 Geotextile Dewatering (“SH-2 GD”). Direct Public Works to file an EDA Grant application with WNDD, and authorize the Public Works Director to sign the grant application. Direct Public Works to bring back an agreement with WNDD for grant administration, if the grant is awarded. Direct Public Works and Finance to file a SRF Clean Water Loan Application with NDEP. Direct Public Works and Finance to initiate the bonding process (G.O. / Revenue Bonds) required for the SRF Loan. 7

Implementation Schedule October 2015 – Submit EDA grant application January 2016 – Select engineering design consultant March 2016 – BOCC Meeting Approve engineering contract March 2016 – Begin design/implement funding plan March 2017 – Permitting May 2017 – Bidding August 2017 – BOCC Meeting Approve construction contract October 2017 – Begin construction October 2018 – Plant startup December 2018 – Final completion 8

Funding Potential Funding Resources Grants EDA – Grant up to $2.0M $10,000 per job creation or retention 50% local match Redevelopment Agency FY 2016 budgeted unappropriated capital reserves = $3,495,147 M State Revolving Fund Loan SRF – Low Interest Loans below Market Rate Flexible – Interest only on loan draws until project closure with final debt service based on actual loan draws 9

Funding Scenario Funded by Utility Revenue & Grants Project Cost = $7.5 M (LT – 2 SBR coupled with SH – 2 GD) EDA/RDA Grant = $2.0 M Debt finance balance of project cost (SRF Loan) New annual debt service = $380,000 (PV = $5.5 M, i = 20 years) Debt Service Repayment 1 Shift $100,000 operating expense to annual debt service Operating Revenue (system $507,000 in FY 2019) 10 New Annual Debt Service($308,000) Operating Revenue 1 $607,000 Cash Flow$227,000 No increase in monthly rates to the users Maintain positive cash flow

Redevelopment Service Area 11

Redevelopment Agency Findings and Conclusion NVWWTF provides sewer service to a significant portion of the Redevelopment Plan Area(s) Future development of the RDA Plan Area(s) is dependent upon the availability of sewer capacity in the North Valley Wastewater Treatment Facility. The Project meets the definition of a Redevelopment project and is consistent with many of the purposes and goals outlined in the Redevelopment Plan approved in The economic benefits of the Project are considerable. 12

QUESTIONS 13