1 Field Period Assembly Office of Science Project Review Princeton Plasma Physics Laboratory Princeton, NJ November 2, 2005 T. Brown Princeton Plasma Physics.

Slides:



Advertisements
Similar presentations
NCSX Mod Coil C1 features requiring rework at PPPL.
Advertisements

BARTOSZEK ENGINEERING 1 The Design of the Booster Collimators Larry Bartoszek BARTOSZEK ENGINEERING 3/10/03.
RF Cavity Module G. Gosling Dept. of Mechanical Engineering Imperial College London.
Engineer Training XL1200 Mechanics. Engineer Training XL1200 Mechanics Confidential 2 The XL1200 is both a Roll to Roll and a Roll to Sheet Printing Machine.
Deviations from fiducial locations are unacceptable in areas despite high accuracy at alignment points.
Mu2e Production Target Remote Handling By: Michael R. Campbell, Fermi National Accelerator Laboratory, , System Layout Basic.
1 MC Assembly via Test Cell Crane FPA Stage 3 Peer Review August 12, 2005 T. Brown.
FDR Station 3 lift fixture, laser screens and brackets T. Brown and L. Morris with analysis support from A. Brooks December 3, 2007.
NCSX Vacuum Vessel Overview Paul Goranson WBS 12 Manager Vacuum Vessel Manufacturing Study Kickoff meeting April 29, 2003.
Multipole Girders - Alignment & Stability (Multipole Girder Alignment technology & R&D) S. Sharma ASD: J. Skaritka, D. Hseuh, V. Ravindranath, G. Miglionico,
Metrology for NCSX Steve Raftopoulos and the NCSX Metrology Team.
Integration and Alignment of Optical Subsystem Roy W. Esplin Dave McLain.
Lab 3 - Centering. Centering; or the smart way to align centered optical elements and systems This lab will make use of concepts used in the previous.
DELTA Quadrant Tuning Y. Levashov, E. Reese. 2 Tolerances for prototype quadrant tuning Magnet center deviations from a nominal center line < ± 50  m.
RF Cavity / Coupling Coil Module
NCSX Modular Coil Turning Fixture FDR. FDR Charge (answers were added below after the review) Modular Coil Turning Fixture FDR - Charge to Reviewers –The.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
MC Type-B fit up review1 Review of MC Type B assembly clearances reviewing A-to-B and B-to-C interfaces 3/1/07 Summary: Wing interfaces look okay between.
1 Stage 3 Peer Review October 26, 2006 T. Brown. 2 Field Period Assembly (FPA) 1.Make sure the requirements for the tooling is well defined (including.
NCSX Vacuum Vessel Joint Design Mike Viola PPPL July 1 st, 2003.
NCSX Modular Coil Turning Fixture FDR. Background Modular Coil winding forms are cast structures which provide the foundation on which the coils are constructed.
1 Dimensional Control for the National Compact Stellarator Experiment R. Ellis, A. Brooks, T. Brown, W. Reiersen, S. Raftopoulos, B. Stratton Presented.
1 NCSX Modular coil winding pack To shim or not to shim? NCSX WBS 1 Engineering Meeting July 7, 2004 What is requirement? What is baseline winding pack.
1 Stage 3 Peer Review October 26, 2006 T. Brown. 2 Field Period Assembly (FPA) – Stage 3 1.Make sure the requirements for the tooling is well defined.
Pre-Lehman Review Briefing Reiersen December 18, 2006.
10/31/2007Mike Viola1 NCSX Field Period Assembly + + = October 31, 2007 Mike Viola Field Period Assembly Manager.
Twisted Racetrack Manufacturing & Metrology. Winding/metrology prototype chronology Various keystoning tests – Completed. –Established keystone effect.
SC Project Review of NCSX, April 8-10, 2008 NCSX Coil Services P.L. Goranson Work Package 161.
NCSX A. Brooks, P. Fogarty, G. Lovett, D. Williamson June 3, 2005 Modular Coil Type-C Final Design Review – Part II.
10/31/2007Mike Viola1 NCSX Field Period Assembly + + = October 31, 2007 Mike Viola Field Period Assembly Manager.
NCSX VACUUM VESSEL PL Goranson Thermal Insulation Final Design Review July 31, 2006 WBS12 NCSX.
NCSX Metrology. Goals –Need to accurately make measure measurements for several NCSX systems Modular coil –As-built measurements of coil form –Conductor,
Metrology Milestones Metrology Task Force –Vacuum vessel manufacture - P. Goranson –Mod. Coil Form manufacture - D. Williamson –Mod. Coil winding- S. Raftopoulos.
1 MC Assembly over the VV FPA Station 3 FDR Review July 17, 2007 T. Brown.
NCSX NCSX TF Coil Procurement 1 February 3, 2006 Michael Kalish NCSX TF Coil Procurement.
10/31/2007Mike Viola1 NCSX Field Period Assembly + + = October 31, 2007 Mike Viola Field Period Assembly Manager.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM29 at RAL, UK February 17, 2011.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
NCSX Field Period Assembly (FPA) Operations, Cost and Schedule, Staffing, and Metrology Utilization Mike Viola Field Period Assembly Manager NCSX FPA Peer.
11/2/2005Mike Viola1 November Lehman Review November 2, 2005 NCSX VVSA NCSX Vacuum Vessel Fabrication Major Tool and Machine – S F 3 120° segments.
F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF, TF, & Trim Coil Supports (WBS-15) Core Base Support Structure (WBS-17) F. Dahlgren NCSX Coil.
NCSX Field Period Assembly (FPA) Operations, Cost and schedule, staffing, and metrology utilization Mike Viola Field Period Assembly Manager NCSX FPA Peer.
1 MC Assembly over the VV FPA Station 3 FDR Review July 13, 2007 T. Brown.
10/31/2007Mike Viola1 NCSX Field Period Assembly + + = October 31, 2007 Mike Viola Field Period Assembly Manager.
SC Project Review of NCSX, April 8-10, 2008 NCSX Field Period Assembly Mike Viola NCSX Field Period Assembly Manager NCSX Project Review April 8-10, 2008.
SC Project Review of NCSX, April 8-10, 2008 NCSX Machine Assembly E. D. Perry.
1 Stellarator Core Metrology issues NCSX WBS-1 Meeting April 2, 2003 What are we measuring? When? How do we take the measurements? How do we correlate.
1 Assembly Tooling PU Workshop on NCSX Cost & Schedule Princeton Plasma Physics Laboratory Princeton, NJ Mar 1-4, 2007 T. Brown Princeton Plasma Physics.
AWB Dimensional Control Requirements for the Modular Coils and TF coils Field Period Assembly Peer Review October 11-12, 2006 Art Brooks.
Field Period Assembly Wayne Reiersen SC Project Review PPPL May 2006.
1 FPA Stage 2 Peer Review May 12, 2006 T. Brown. 2 FPA Stage 2 Status Summary of Stage 2 activities Review current design status Review schedule details.
The Design: Totally bolted, electrically isolated 6 top and 6 bottom inboard flange holes, with tapped holes in one flange and a thru holes in mating flange.
1 Modular Coil Assembly Fixture (MCAF) Information Meeting February 23, 2005.
DRAFT Cost and schedule, staffing, metrology utilization 10 AM October 12, 2006 Mike Viola Field Period Assembly Manager.
9/28/20051 Mike Viola 1, T. Brown 1, P. Heitzenroeder 1, F. Malinowski 1, W. Reiersen 1, L. Sutton 1, P. Goranson 2, B. Nelson 2, M. Cole 2, M. Manuel.
10/31/2007Mike Viola1 NCSX Field Period Assembly + + = October 31, 2007 Mike Viola Field Period Assembly Manager.
Preparations for working on Station 1 November 22, 2005.
NCSX Strykowsky 1Cost and Schedule Rebaseline April 25, 2005 NCSX Project Re-baseline Review April 25, 2005 Cost and Schedule Ron Strykowsky.
SEPT 20, 2006 T. Brown, M. Cole, P. Fogarty, P. Goranson, K. Freudenberg, D. Williamson NCSX STAGE 2 COIL TO COIL ASSY.
8/15/2007Mike Viola1 NCSX Field Period Assembly + + = August 15, 2007 Mike Viola Field Period Assembly Manager.
12/19/2006Mike Viola1 December Lehman Review December 19, 2006 Mike Viola Field Period Assembly Manager NCSX Field Period Assembly + + =
1 FPA Stage 2 MC Flange Assembly Issues and Design Proposals June 20, 2006 T. Brown.
Engineer Training XL1500 Mechanics. Engineer Training XL1500 Mechanics Confidential 2 The XL1500 is both a Roll to Roll and a Roll to Sheet Printing Machine.
1 CD-2 ECP Preparations What is Needed. 2 Background As part of the CD-2 process, we need to establish a fully supported and documented cost and schedule.
1 VV Support Fixture FPA Stage 1 PDR Review August 10, 2005 T. Brown.
1 NCSX VV Assembly Joint Issue B. Nelson 17 Mar 2005.
1 NCSX Construction Overview NCSX Team (presented by L. Dudek) March, 2008.
NCSX Vacuum Vessel Fabrication
SNS COLLEGE OF ENGINEERING
Lab 3 - Centering.
Presentation transcript:

1 Field Period Assembly Office of Science Project Review Princeton Plasma Physics Laboratory Princeton, NJ November 2, 2005 T. Brown Princeton Plasma Physics Laboratory Oak Ridge National Laboratory

2 Stage 1 Stage 3 Stage 5 VV Prep MC installation over VV Field Period Final FP Assembly Stage 2 MC Half Period Assembly Lower segment, shim and fasten Stage 4 TF Half Period Assembly FPA is accomplished in five Stages (FY06) (FY07) (FY07, FY08)

3 Field Period Assembly (FPA)  What is involved with FPA  What are the FPA plans and schedule for FY 06 and FY 07  What technical issues and risks are associated with this activity  What R&D activities are used to reduce assembly risk and improve cost and schedule success

4 Bolts and a shear pin used to lock position Simple support stands are bolted to the floor and a mechanical worm gear is used to position the VV. Worm wheel to position the VV VV Prep Station – Stage 1

5 VV Prep Station – Stage 1 (cond.) Stage 1 is used to install (with metrology alignment) 15 magnetic loops on VV Field Periods 1 & 3 and 138 loops on FP 2. In addition 64 coolant tubes with ~ 1000 studs will be installed on each Field Period.

6 MC Half Period Assembly – Stage 2 An adjustable support stand is used to support the Modular Coil Half Periods (Type A, B and C) as the individual coil windings are set on three precision adjusted spherical seats. Adjustable support stand After a MC position is verified the flange surfaces are shimmed and bolted tighter. Completed MCHP Type-C assembly

7 MC HP Assembly – Stage 2 (cond.) Three spherical seat positions are pre-adjusted for every Modular Coil winding based on metrology measurements of the winding and manipulation of a NCSX Field Period Assembly CAD model prior to Modular Coil Half Period assembly. Adjustable male spherical seat Female side spherical seat Machine Tol

8 All 18 MC’s will be set to match the measured metrology data and spherical seats will automatically adjust to the correct position to align male and female interfaces. Setting the individual coordinates system results in spherical seat motion FPA CAD model used in the assembly process

9 MC HP Assembly – R&D Activity A pair of 20” x 30” plates with three spherical seat assemblies have been fabricated to use in an R&D set-up to test our ability to set the alignment of the plates and accuracy measure their position using our Leica laser metrology system.

10 MC installation over a VV FP – Stage 3 Stage 3 involves manipulating two 24,000 lb MCHP over a VV field period within the prescribed assembly path.

11 MC installation over a VV FP – Stage 3 Crane Supported – hand assisted assembly Mechanical Assembly An R&D activity was used to select a lower cost assembly approach for installing the modular coil half period over the VV period.

12 25,000 lb concrete block 120” long, 40” wide and 60” high MC crane assisted assembly simulation was set up using a concrete block with three lasers mounted to it. The concrete block motion was controlled by using a combination of the D-site crane, three chain-fall supports mounted to the crane hook and hand manipulation of the block for rotation. MC installation R&D Activity

13 The path traveled by each laser was plotted on sheets of velum and mounted to the screens, aligning pre-marked crosshairs located on the screen with marks on the printed paper One-quarter inch circles were used to define the required laser positions along the curve path. The block was manipulated to follow the sequential points with an occasional maximum deviation of about ¾” to 1”, all within our allowed assembly tolerances. Improvements will be made using motor driven mechanical screws with in-line encoder.

14 TF Half Period Assembly– Stage 4 Stage 4 involves assembling three TF coils and structure into a three coil half period.

15 Final FP Assembly– Stage 5 Stage 4 completes the FPA assembly process bringing together the VV/MCHP assembly, TFHP and attaching VV ports, correction coils and services.

16 Stage 5 Final FP Assembly details have been developed in sufficient detail to develop cost and schedule estimates. Stage 5 assembly design details

17 FPA Plans & Schedule Development Assembly tasks are design driven and solidified through peer reviews. Assembly steps have been established for all five FPA Stages based on current design understanding.

18 Input to MIT/QA pan Finalized process steps developed for Stage 1 will be used as input to MIT/QA pan

19 FPA activities are in-line with project schedules Engineering Fixture Fab FPA Stage Asmbly 33.5 K 45.8 K 59 K 27 K 66.6 K 2599 MH 1433 MH each 880 MH each 808 MH each 320 MH each 2728 MH each Complete

20 The FPA plans are in place to meet the NCSX FPA assembly requirements, A sound basis has been established for FPA cost assessments, and R&D activities have been used to reduce FPA risks. Summary