Commissioning Hardware and IP Configuration of ATF / 12 / 19 ATF2 project meeting at KEK Toshiyuki Okugi (KEK)
Commissioning Hardware for ATF2 I proposed the following hardware preparation to SLAC at the ATF2 meeting in March ) BPM ; - I, Q information from each readout electronics (SLAC) - Temporal BPM control panel for commissioning (KEK) (x, y) = A * Sqrt (I^2+Q^2) * Sgn ( I or Q ) A ; free parameter I,Q ; from SLAC First pulse calibration result seems to be good performance. Can we use the BPM information from the beginning of the commissioning? If YES, we don’t have to prepare the temporal BPM control panel. 2) Screen, ICT (KEK) and information of amplitude of reference cavity (SLAC). 3) Quad Movers Calibration and control system should be ready before commissioning (SLAC). First priority of the ATF commissioning is to transport the beam to the end of ATF2 beam line without beam loss.
Shintake Monitor Area IP QD0 S-band BPM Sweeping Magnet Honda Monitor Carbon Wire Scanner C-band BPM 180 Screen Monitor 825 Dump Bend Stripline BPM ICT IP configurations presented at Annecy Meeting IP-BPM Small vertical aperture How to put all of the devices in the limited space ? Is it possible to shorten - the length of the stripline kicler ? - the Shintake monitor support table thickness ? - the thickness of the adopter of S-band BPM ? - the length of Honda monitor ?
SBPM QC3 SBPM FFTB 2.13 S3.00 SF1FF QF1FF SBPM QC3 SBPM FFTB 2.13 S3.00 SD0FF QD0FF Final Doublet Table Configuration mm space is necessary for S-band BPM with adopter.
IP BPM Chamber 100mm IP 135mm100mm IP BPM will be located on the chamber. Honeycomb Table IP BPM chamber will be mounted in the hole of the Shintake monitor honeycomb table
Sweeping Magnet Flange to Flange Length150 mm Electrode Length80 mm Electrode Gap40 mm Power Supply SpecificationDC +/- 100V, double pulse, bipolar Kick Angle6.1nrad / V Scan Position at IP 3.7nm / V Dynamic Range+/- 370nm - enough for Shintake monitor, carbon wire and IP FB. - However, it is too week for Honda monitor. The old stripline kicker will be modified for the sweeping magnet. For the nominal operation, one side of electrodes should be open, and use DC PS. For the first feedback, one side of electrodes should be connect to the load.
IP QD0 S-band BPM Sweeping Magnet Honda Monitor Carbon Wire Scanner C-band BPM 180 Screen Monitor 825 Dump Bend Stripline BPM ICT New IP configurations IP BPM
Stripline BPM Device List Blue ; wide beam pipe Red ; Long Electrode ( High Resolution) Old BPM Name Electrod e Length Pipe Diamet er OriginalModifiedBellows Magnet Thicknes s Pipe Length Total Length Magnet Thickness Pipe Length Total Length OriginalModified Electrode Side No Electro de Electrode Side No Electrode ML1X40Narrow ○○ ML2X40Wide ×○ ML3X40Wide ×○ ML4X40Wide ×○ ML5X40Wide ○○ ML6X40Wide ×○ ML7X40Narrow ×○ ML8X120Narrow ○○ ML9X120Narrow ○○ ML10X120Narrow ○○ ML11X120Narrow ○○ ML12X120Narrow N/A ○○ ML13X40NarrowN/A 170N/A 170×× ML14X40NarrowN/A ×○
nameold namefunctiontype locationcomments ML1XML2XBPMstripline (L.R.)d/s end of QF1X (Hitachi 180) MS1X move by +35mm ML2XML3XBPMstripline (L.R.)d/s end of QD2X (Hitachi 180) ML3XML4XBPMstripline (L.R.)d/s end of QF3X (Hitachi 180) ML4XML5XBPMstripline (L.R.)d/s end of QF4X (Hitachi 180) ML5XML6XBPMstripline (L.R.)u/s end of QD5X (Hitachi 180) ML6XML7XBPMstripline (L.R.)u/s end of QF6X (Hitachi 180) ML7XML1XBPMstripline (L.R.)d/s end of QF7X (Hitach 60) ML8XML14XBPMstripline (H.R.)d/s end of QD8X (Hitachi 180) ML9XML8XBPMstripline (H.R.)u/s end of QF9X (Hitachi 180) ML10XML9XBPMstripline (H.R.)d/s end of QF13X (Hitachi 180) ML11XML10XBPMstripline (H.R.)d/s end of QD14X (Hitachi 180) ML12XML11XBPMstripline (L.R.)d/s end of QF15X (Hitachi 180) QBPM1X BPMC-band cavityd/s end of QD10X (QEA 180) No mover QBPM2X BPMC-band cavityd/s end of QF11X (QEA 180) No mover QBPM3X BPMC-band cavityd/s end of QD12X (QEA 180) No mover QBPM4X BPMC-band cavityd/s end of QD16X (QEA 180) No mover QBPM5X BPMC-band cavityd/s end of QF17X (QEA 180) No mover QBPM6X BPMC-band cavityd/s end of QD18X (QEA 180) No mover QBPM7X BPMC-band cavityd/s end of QF19X (QEA 180) No mover QBPM8X BPMC-band cavityu/s end of QD20X (Hitach 60) C-band BPM with Hitachi QBPM9X BPMC-band cavityd/s end of QF21X (Hitach 60) C-band BPM with Hitachi nameold namefunctiontype locationcomments ML1FFML12XBPMstripline (H.R.)between QM12FF and QM11FFpulse-to-pulse feedback ML2FFML13XBPMstripline (L.R.)d/s dump bend