Group 15 Simon Phelan Phillip Barry Simon White Fabien Raoux.

Slides:



Advertisements
Similar presentations
A. T. Tankut Middle East Technical University, Turkey
Advertisements

Buildings and Structures 1
Why Is Special Inspection Good For Us?
Timber Portal Frame Construction
Portal Framed Construction
Introduction to Lateral Force Resisting Systems
CASTING A CONCRETE WALL
D&C PT Contractor’s Role & Responsibilities Chris M. Harris Contracts Manager, Structural Systems & PTIA Technical Committee.
METHODS OF RETROFITTING
Riverview Heights Darren K. Howard Structural Option Architectural Engineering Spring Thesis 2005 Advisor: Dr. Ali Memari.
CONCRETE AND MASONRY CONSTRUCTION
Structural System Overview
Concrete and Masonry Work Different forms of concrete work Each has it’s own unique hazards – Lift Slab – Pre-stressed Concrete – Concrete Pumping – Masonry.
We are reviewing Chapt. 1&2 and we assigned Chapt. 3 & 4 for
Skyscraper Construction
5/1/2015OSHA Office of Training & Education 1. 5/1/2015OSHA Office of Training & Education 2 Subpart Q - Concrete & Masonry Construction ( )
“It’s All Fun and Games Until the Parking Garage Collapses” CASE STUDY: 2003 Tropicana Casino Parking Garage Collapse.
Mechanics of materials ** progressive collapse **  The term progressive collapse is defined as the collapse of all or a.
Design C a s t i n g E r e c t i o n F i n a l S t r u c t u r e D e s i g n C o n s t r u c t i o n P r o c e s s P r e–c a s t C o n c r e t e 3D M o.
OSHA Subpart Q Concrete and Masonry Construction.
ATHENS 12 th of April, M. Eng. Velyan Petkov The European Center for Risk Prevention, Sofia, Bulgaria Bulgarian seismic design codes and civil construction.
LEGISLATION OVERVIEW & PROCEDURES Douglas Walker Chairman Scottish Registration Board Structural Engineers Registration Ltd.
CTC 422 Design of Steel Structures
Next Act Wall: 3 Different Panels All wood is 2x4 unless otherwise specified.
C-23 The effective length factor (K) was introduced in page (C-7) for six ideal conditions, these are not encountered in practical field conditions. LRFD.
What have we accomplished? STRENGTH OF MATERIALS
Seismic Performance Assessment of Flat Plate Floor Systems John W. Wallace, Ph.D., P.E. Thomas Hyun-Koo Kang, Ph.D. Student Department of Civil and Environmental.
Rectangular framed structures
Michelle Perticarari Rebeca Peña
for Earthquake Resistance
SITE SUPERVISION (CITADEL TOWER)…………….…1 SITE SUPERVISION (CITADEL TOWER)…………….…1 DESIGN OF A 3 BEDROOM STOREY BUILDING…..2.
Frank Burke Structural Option Sallie Mae HQ Reston, VA.
Construction Safety Council. by David G. Allie Subpart R - Steel Erection ( ) Tiered buildings not adaptable to temporary floors - Safety.
Appendices Subpart R Steel Erection
Villanova University Dept. of Civil & Environmental Engineering CEE 8414 – Structural Dynamics Northridge Earthquake 1 Northridge Earthquake - Concrete.
Concrete Construction I Chapter 19. Mehta, Scarborough, and Armpriest : Building Construction: Principles, Materials, and Systems © 2008 Pearson Education,
Ethical Disasters Group 8 By Dominique Amos, Josh Seuss, Alex Finkelstein, Mike Hite, Kevin Hao.
SEISMIC REHABILITATION BY SYSTEM IMPROVEMENT (METU APPROACH) Presentation atUniversity of Texas and Purdue University November 2008 UĞUR ERSOY Bogazici.
Gateway Plaza Wilmington, DE Elizabeth Hostutler Structural Option.
Mathew Nirenberg AE Senior Thesis Structural Option.
Third Avenue NY, New York Michelle L. Mentzer Structural Option.
Robert M. Arnold Building Fred Hutchinson Cancer Research Center
Stability systems in high rise buildings - Neo Bankside, Southbank, London - The Gherkin (Swiss Re Bank) 30 St Mary Axe, London Maryam & Elisavet.
Welcome to Daniel Painter’s Architectural Engineering Senior Thesis Presentation of Two Freedom Square April 16, 2003 Pennsylvania State University.
The Great Exhibitions. The Great International Exhibitions With the advent of the industrial revolution, new inventions helped to suit the production.
L’Ambiance Collapse Group 15 David Lawlor Emma Quinn Daniel O’Sullivan Cian O’Sullivan.
Matthew Murphy Andrew Goulding Jennifer Young Rosanna Kleemann.
L'Ambiance Plaza Collapse Bridgeport, Connecticut April 23, 1987
The Royal Plaza Hotel Collapse. Background on Collapse  Collapsed Friday 13 th August 1993 at 10:10 a.m.  The collapse took less than 10 seconds! 
 Building Background  Building Structural System  Problem Statement  Proposed Solution  Structural Investigations  Architectural Impact  Sustainability.
Controlled Rocking of Steel Braced Frames
Design of Bracing Connections in Concentrically Braced Frames
Hartford Arena Roof Collapse.  January 18th  Snowstorm.  Roof plummeted 83 feet to the arena floor.  What caused the 300-x 360ft. roof to collapse?
Royal Plaza Hotel, Thailand
 CREATING A BUILDING PROJECT Create a building model using individual building elements. walls, windows, doors, floors, roofs, and so on. Create a building.
Royal Plaza Hotel Collapse Thailand Group 24. Summary on Collapse Collapsed on Fri 13th August 1993 in less than 10 seconds 379 people in the Hotel were.
Strength and Stability Questions
Construction 101 Start to Finish
4th Annual Construction Law Summit
Anjar substation control building with
CIVIL WORKS CONSTRUCTION TECHNOLOGY 2017/18
Toledo I-280 Crane Accident
By the name of Him.
STRUCTURAL FAILURES-CAUSES AND REMEDIES:
Mitre III Building McLean VA Debra Schroeder Structural Option.
Masonry Bearing Walls.
Toledo I-280 Crane Accident
Commercial Structural Framing Systems
Chapter 8 Framing Systems.
RiverView Condominiums II Chicago, IL
Presentation transcript:

Group 15 Simon Phelan Phillip Barry Simon White Fabien Raoux

 Residential project under construction in Bridgeport Connecticut in  16 storey structure with 3 parking levels and 13 apartment levels.  There were two offset rectangular towers, separated by a construction joint at the central elevator lobby.  The building used the lift-slab method of construction.  Lateral restraint in the structure was provided by shear walls in each of the towers.  On April 27, the incomplete structure was overloaded and collapsed, killing the 28 workers.

 Improper arrangement of post-tensioning tendons in concrete slabs, columns around openings.  Over stressed concrete sections due to open slots left in the slabs to accommodate later casting of shear walls.  The lifting collar design was deemed inadequate as well as the lift slab construction technique  Frame stability and lateral strength was poor due to incomplete and inadequate temporary connections.

Schematic of L’Ambiance Plaza Aftermath

 A two-judge panel mediated a universal settlement between 100 parties closing the L’Ambiance Plaza case. Twenty or more separate parties were found guilty of "widespread negligence, carelessness, sloppy practices, and complacency."  Those injured and the families of those killed in the collapse received $30 million.  Another $7.6 million was set aside to pay for all of the claims and counter claims between the designers and contractors of L’Ambiance Plaza.  This also ended all investigations prematurely, leaving the exact cause of collapse undetermined.

 Responsibility for design was fragmented among so many subcontractors that several design deficiencies went undetected.  Adequate safety factor not implemented for design.  Assumptions that the design engineer made about sequencing were not clearly communicated to those responsible for field operations.

 Appointment of a Construction Manager whose sole purpose is to oversee the various parts of the construction sequence.  A high factor of safety should be provided during construction also, not just once completed.  During all stages of construction, temporary lateral bracing should be provided.  Cribbing (temporary posts which support the concrete slab until it is completely attached to the column) should be used.  Sway bracing (cables which keep the stack of floors from shifting sideways) should be used. This was required, but not used in L’Ambiance Plaza.