Big Stone II – Delivery Study Phase 6 and Supplemental #2 For Northern MAPP SPG Meeting 4/3/07 Elk River Richard Dahl Missouri River Energy Services.

Slides:



Advertisements
Similar presentations
The Midwest ISO from a Transmission Owner Perspective.
Advertisements

Cleco Transmission Planning Summit 2013
AN INTRODUCTION TO THE MIDWEST ISO By Bill Malcolm Manager-State Regulatory Affairs Pierre, South Dakota June 9, 2006.
Excelsior Energy’s Mesaba Energy Project Update for the NM-SPG August 16, 2006.
Big Stone II Study Update SPG Meeting October 19, 2006.
RPG: September 24, Approach for ERCOT Independent Review of the 2013 Houston Import Project Jeff Billo, Manager, Transmission Planning September.
March 26, 2014 Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting.
STATUS OF BULK ELECTRIC SYSTEM DEFINITION PROJECT
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
Company LOGO Cleco Planning Process. Models Cleco uses SPP’s annual series of models to determine the NERC reliability violations. Cleco uses SPP or VST.
La Crosse 161 kV Capacitor Addition Northern MAPP Subregional Planning Group April 3, 2007 Daniel Kline.
NTTG Economic Study and Biennial Study Update NTTG Economic Study and Biennial Study Update NTTG Study Cycle.
Santee Cooper’s 2013 Formula Rate Transmission Tariff presented via WebEx May 28, 2013.
North Mankato Load Serving study Xcel Energy Great River Energy.
Houston Import Evaluation Cross Texas Transmission & Garland Power & Light ERCOT RPG Meeting August 27th, 2013.
October 30, 2014 Terry Wolf, Manager of Transmission Services.
Cleco Transmission Planning Summit 2011 Coughlin Transmission Operations Center April 15, :00 – 11:00am.
Twin Cities Minnesota Zone Meeting Xcel Energy October 27, 2004 St. Paul, MN.
Buffalo Ridge Incremental Generation Outlet (BRIGO) Transmission Study Presentation to National Wind Coordinating Committee June 22, 2005 W Grivna, PE.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
WECC PCC Meeting Salt Lake City, UT July 16, 2014.
1 Local Area Planning Update to TRANSAC – July 29, 2015 Mitigation Update, Uncertainty Scenarios, and Next Steps.
Xcel Energy Smaller Scale Transmission Projects Northern MAPP Subregional Planning Group April 3, 2007 Srinivas Vemuri, Jason Standing, and Daniel Kline.
New Richmond Load Serving Study Northern MAPP Subregional Planning Group August 16, 2006 Daniel Kline.
1 Local Area Planning Update to TRANSAC – September 18, 2014.
111 TAG Meeting June 8, 2015 Teleconference / Webinar FINAL.
Potential Transmission Construction Scheduling In Southern Minnesota--- Fall Spring 2006 Xcel Energy has posted Significant Transmission construction.
Report on the NCTPC 2006 Collaborative Transmission Plan Mark Byrd, Manager – Transmission Planning Progress Energy Carolinas, Inc January 25, 2007.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
NW Resource Adequacy Forum Steering Committee Conference Call November 4, 2010.
0 CapX /1/2015 CapX 2020 Transmission Plan: Ensuring Reliable Electricity.
Reliable Power Reliable Markets Reliable People Performance Targets for the Customer Interconnection Process January, 2008.
1 Transmission Advisory Group Meeting January 25, 2007 Raleigh, NC.
1 Transmission Line Projects in Maryland – an Overview Sandra S. Patty PPRP - Manager, Transmission Projects PPRAC Meeting Country Inn & Suites, Annapolis,
Rocky Mountain Power Five Year Study Findings and Kick Off Meeting December 2013.
1 Local Area Planning Update to TRANSAC – Sept 16, 2015 Mitigation Update, Uncertainty Scenarios, VAR Margin Study.
June 19, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
ERCOT PUBLIC 4/21/ RTP: Cascade Analysis April 21, 2015.
MISO Northwest Exploratory Study Presented to National Wind Coordinating Committee Participants in study – MISO, Various utilities in Minnesota, North.
Local Area Study Local Area Study Mitigation Plan Update and Uncertainty Scenarios
Entergy AFC Stakeholder Meeting February 16, 2005 Houston, TX.
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
2013 Wind Conference. Transmission Service Study Process Steve Purdy.
Long-Term Solution for Negative Generation Entergy Transmission AFC Stakeholder Meeting August 22, 2006.
June 2008 Windsor-Essex Electrical Service Needs and Solutions.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.
AEPSC Live Oak County Transmission Project – ERCOT Independent Review TAC September 24, 2015.
August 22, 2014 Terry Wolf, Manager of Transmission Services.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting June 20 th, 2008 Austin, TX.
Entergy AFC Stakeholder Meeting March 9, 2005 Houston, TX.
October 16, 2009 RPG Meeting ERCOT Independent Review of the Corpus Christi Improvements Project Jeff Billo.
Coordinated Planning Concept (For Discussion Only) revised 11/30/04 07/01/04.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
November 16, 2012 Terry Wolf, Manager of Transmission Services.
2006 Preliminary Reliability Study Results Bryan Guy September 7, 2006.
2010 Draft Transmission Expansion Plan (Local Planning Projects)
Local Area Planning Update – TRANSAC Base Case Status Base case study models representing the base scenarios will be completed as follows for.
Reliability Must Run Workshop RMR Study Process May 24, 2016.
Freeport Area Master Plan Project -
Columbia Grid Wind Integration Study Team Dynamic Transfer Capability Studies Update 9/10/09.
Status Update for Reliability/Market Power Mitigation Assessment
Excelsior Energy’s Mesaba Energy Project
Excelsior Energy’s Mesaba Energy Project
2019 Attachment O customer meeting
Excelsior Energy’s Mesaba Energy Project
Big Stone II Study Update
Presentation transcript:

Big Stone II – Delivery Study Phase 6 and Supplemental #2 For Northern MAPP SPG Meeting 4/3/07 Elk River Richard Dahl Missouri River Energy Services

Study phases Phase 1: 2009 Summer Peak w/ only confirmed reservations for MISO and MAPP DRS. Phase 2: 2009 Summer Peak w/ confirmed and prior queued study mode reservations for MISO and MAPP DRS. Phase 3: 2014 Summer Peak w/ confirmed and prior queued study mode reservations for MISO and MAPP DRS. Phase 4: 2010/11 Winter Peak w/ confirmed and prior queued study mode reservations for MISO and MAPP DRS. Phase 5: High Transfer (MWSI = 1480 MW, MHEX_S=2175 MW, NDEX=2080 MW pre-BSP II) summer off-peak (70% of peak) for MAPP DRS only. Phase 6 …… we will go through the scope in more detail later in the presentation.

Where are we at with studies? Phase 1-4 studies submitted to DRS in August 2006, and approved (with contingent items) November Phase 5 studies submitted to DRS in September 2006, and approved (with contingent items) November Supplemental report 1 submitted to DRS in November This report removed some contingent items associated with Phase 1-4.

Where are we at with studies – cntd A Supplement 2 report was submitted to the DRS, and approved on 3/30 removing the following contingent items:  Bismarck area 115 kV lines : These will be upgraded by the end of the year.  Kerkhoven – Kerkhiven Tap 115 kV: Line rating has increased sufficiently.  Blanchard 115 kV bus voltage: Criteria is 0.92 not 0.95 pu. Also misc. upgrades increase voltage to above 0.97 pu.  Four Corners 115 kV bus voltage: 115 kV bus w/o load or generation fed from 69 kV. Not a concern.  International Falls 115 kV: Not issue per discussions w/ MP. There a still more contingent items to resolve Phase 6 Delivery Service Study will be submitted to DRS tentatively for their June Meeting, but report should be complete well in advance of this. Not seeking action from NM SPG today. Just informing the group of where we’re at and looking for any feedback.

Phase 6 Study Scope was sent out earlier to TO ad hoc group. Draft report also sent out about 2 weeks ago for ad hoc group to comment on. Ad hoc group was also solicited on model updates Thanks to all that helped review!

Phase 6 Study Scope Currently there’s two transmission expansion alternatives on the table:  Alternative 1: Big Stone – Johnson Jct. – Morris 230 kV + Big Stone – Canby – Granite Falls 230 kV  Alternative 2: Big Stone – Willmar 230 kV + Big Stone – Canby – Granite Falls 230 kV The project has stated along with the Minnesota Certificate of Need application that Alternative 1 is the preferred alternative. Phase 6 so far is only studying Alternative 1. Alternative 2 will only be studied further as needed.

Phase 6 Study Scope – cntd Steady state analysis for Delivery Service studies Two major goals of Phase 6 Studies  Evaluate the impact of converting Big Stone – Canby – Granite Falls 230 kV to 345 kV Additional constraints? Less constraint?  Evaluate the impact of other projects MTEP projects listed as planned CapX Brookings Co. – SE Twin Cities 345 kV Misc. model updates Also tabulate losses

Converting Big Stone – Canby – Granite Falls 230 kV to 345 kV The line conversion would mean that there would be a 345 kV line from Big Stone area tying into the Brookings County, SD – SE Twin Cities CapX project. The termination point for the 345 kV would be at the proposed Hazel Run substation near Granite Falls. Only studied in a post-CapX world (the one project only).

Impact of converting Granite Falls 230 kV line to 345 kV Studies shows no non-flowgate Significantly Affected Facilities per the MAPP DRS criteria. This is true for both voltage and thermal steady state analysis Flowgate analysis performed:  Using DFCALC w/ currently posted DFCALC input file.  Using DFCALC w/ updated DFCALC input file to include flowgates currently monitored by the MAPP OASIS  Using MISO’s monitored element file for MUST  No flowgate violations found Some facilities are unloaded (yet to be fully tabulated)

Impact of other transmission upgrades Blanchard 115 kV low voltage violation is no longer present due to system upgrades on the 115 kV system. Alexandria Area bus voltage violations  Many go away, some remains at Miltona, Elbow Lake, Grant County, and Brandon  Largely caused by MRES upgrades in the Alexandria area Erroneous voltage criteria  A 0.92 pu. low voltage criteria used for Glenwood and Villard 69 kV as opposed to less strict 0.90 pu. No longer in violation. Bismarck Downtown – Bismarck Expressway – East Bismarck 115 kV is no longer constraint when reconductored/ rebuilt to 160 MVA.

cntd CapX helps constraints found earlier  Kerkhoven Tap 115 kV bus voltage within criteria  Granite Falls – Minnesota Valley 230 kV loading well below normal rating at 56%  Fargo – Moorhead 230 kV loading below normal rating  Fargo 115/69 kV xfmr #2 loading down to emergency rating for relevant contingencies (as opposed to above emergency rating previously).  Belfield 345/230 kV xfmr loading below emergency rating. Contingency is loss of large Leland Olds 345/230 kV xfmr with cross-trip of the smaller one. Winter scenario sees the highest flows.  New Ulm area bus voltages is helped somewhat with the new Franklin 345/115 kV substation. However 115 and 69 kV is still a constraint for serving load in the area. Study on how to enhance load serving in this area is being performed w/ Xcel as lead.

Losses A small increase seen in the summer peak scenario A small decrease seen in the winter peak scenario

Going forward… Report will be submitted to MISO when complete. Report will submitted to MAPP DRS for approval tentatively at their June meeting, if not sooner. Goal: To have a final report in April

Questions?