ISTOG INDUSTRY ISSUES Interactive Session Gregg Joss (Ginna Station Vice Chair ISTOG) Ron Lippy (True North Consulting ISTOG Facilitator)

Slides:



Advertisements
Similar presentations
Safety Absolutes Green Lake
Advertisements

FHM TRAINING TOOLS This training presentation is part of FHM’s commitment to creating and keeping safe workplaces. Be sure to check out all the training.
1 Welcome Safety Regulatory Function Handbook April 2006.
Lock Out/Tag Out Training Lock-Out/Tag-Out OSHA Definition. Lockout/Tagout (LOTO) refers to specific practices and procedures to safeguard employees.
1 Component Design Basis Inspection (CDBI) Graydon Strong 6/17/14.
ASME SMR ROADMAP (STP-NU-072)
IAEA International Atomic Energy Agency Responsibility for Radiation Safety Day 8 – Lecture 4.
Modeling boiling water reactor main steam isolation valve leakage using MELCOR Presented at the 21 st Annual Regulatory Information Conference March 10-12,
NRC Perspective of Recent Configuration Management Issues Tom Farnholtz Chief, Engineering Branch 1 Division of Reactor Safety, Region IV June 2014 CMBG.
© April, 2005 LeBlond and Associates, LLC Overview of a Training Program Produced by LeBlond & Associates, LLC Thanks for taking the time to view this.
Louisiana Department of EnvironmentalQuality LDEQ CAM Plan Overview LDEQ’s 27 th Annual Conference on the Environment Cajundome Convention Center Lafayette,
Implementation and Management of Leak Detection and Repair Programs – New Rules and Other Considerations Nebraska Ethanol Safety & Environmental Coalition.
NRC PERSPECTIVE ON RELIEF AND SAFETY VALVES Charles G. Hammer Component Performance & Testing Branch Division of Component Integrity Office of Nuclear.
ISTOG MOV TESTING TRANSITION Prepared by: E. Cavey DTE-Fermi 2 Page 1 The GOAL of this effort was to develop implementation guidance for ASME Code Case.
Main Requirements on Different Stages of the Licensing Process for New Nuclear Facilities Module 4.7 Commissioning Geoff Vaughan University of Central.
Controlling Hazardous Energy
Fermi Case Study Flow Variance ≥ 2% Obtaining NRC relief to allow for use of a 2.78% total flow reference band for Fermi RHR Service Water Pumps ISTOG.
Protection Against Occupational Exposure
Codex Guidelines for the Application of HACCP
BRC Food Safety Quality Management System Training Guide
1 ISTOG Position on Pre-conditioning ISTOG Input on Interpretation and Clarification Of NUREG-1482 Sections 3.5 / 3.6.
Current Air-Operated Valve Regulatory Activities Steven Unikewicz US Nuclear Regulatory Commission Office of Nuclear Reactor Regulation January 2006.
DECEMBER 2010 ISTOG MEETING NEW Q & A CARD DISCUSSION.
Quality Assurance Program National Enrichment Facility Warren Dorman September 19, National Energy and Environmental Conference.
Page © ASME 2012 Standards and Certification Training Module B – Process B10.Performance Based Standards.
A SUMMARY OF CDBI FINDINGS IN SERVICE TESTING OWNERS GROUP December 2010 Clearwater, Florida.
QA Requirements for DOE Accelerator Safety System Software K. Mahoney Group Leader, Safety Systems TJNAF Presented at the 2008 DOE Accelerator Safety Workshop.
Fatigue Management Rule Russell Smith Nuclear Energy Institute (NEI)
FRANKLIN engineering group, inc. Start-up Shutdown Malfunction Plan Development and Implementation Duncan F. Kimbro
11 Technical Session 3 – Rulemaking Process: NRC and Industry Perspectives on Improving Quality, Timeliness, and Consistency in 10 CFR 50.55a Raymond (Ray)
NHUG - Boston - 08/04/20101 Considerations for Operability of Chillers and Chilled Water Systems NHUG Summer Meeting August 4, 2010 Tim Mitchell Component.
Event Management & ITIL V3
Organization and Implementation of a National Regulatory Program for the Control of Radiation Sources Inspection Part II.
ISTOG Winter 2010 – Ed Cavey Fermi 2 1 ISTOG Issues - Code Inquiries / Proposed Code Cases ISTOG Issues from 2010 January meeting and subsequent telecons.
Prime Responsibility for Radiation Safety
Presented to: Transport Airplane Metallic and Composite Structures Working Group and Airworthiness Authorities By: Walt Sippel and Mike Gruber Date: Sept.
BIM Bridge Inspection and Maintenance Technical Standards Branch Class B Bridge Inspection Course Inspection Policies and Procedures INSPECTION POLICIES.
Main Requirements on Different Stages of the Licensing Process for New Nuclear Facilities Module 4.5/1 Design Geoff Vaughan University of Central Lancashire,
NRC Region I Lessons Learned Steve Barr Senior Emergency Preparedness Inspector Region I US Nuclear Regulatory Commission 2010 NRC Region I Joint Exercise.
Advisory Committee on Reactor Safeguards Full Committee Davis-Besse Nuclear Power Station Final & Supplemental Safety Evaluation Report November 4, 2015.
Guidance Training (F520) §483.75(o) Quality Assessment and Assurance.
IAEA International Atomic Energy Agency IAEA Safety Standards for Research Reactors W. Kennedy Research Reactor Safety Section Division of Nuclear Installation.
Assoc. Prof. Dr. Ahmet Turan ÖZCERİT.  System and Software  System Engineering  Software Engineering  Software Engineering Standards  Software Development.
06/01/20161 Benny Hoff TÜV NORD Sweden AB AFS 2002:1 Use of pressure equipment.
ASME OM CODE CASES Presented by Jeff Neyhard for Ron Lippy Intro 101???
1 Regulatory Experience With Preconditioning ISTOG Winter Meeting Orlando Florida January 24, 2008 Tim Smith Dominion Energy Kewaunee
1 ISTOG QUESTIONS ISTOG QUESTIONS IST Program Plan Submittals to Regulators: Prior to OM-2001, and going back to ASME Section XI, there.
1 Safety factors for periodic safety review for research reactors Group A: SF1 – SF4.
1 Public Meeting with ASME to Discuss Pump Inservice Testing Issues NRC Headquarters OWFN Room 1F22 June 4, 2007.
ISTOG – NRC Update Winter Meeting 2010 – Clearwater, FL Tony McMurtray Chief, Component Performance & Testing Branch Office of Nuclear Reactor Regulation.
Building Industry Authority Determination 2003/3 Commentary Paul Clements.
IAEA Training Course on Safety Assessment of NPPs to Assist Decision Making Diablo Canyon NPP Maintenance Rule Program Workshop Information IAEA Workshop.
Use and Conduct of Safety Analysis IAEA Training Course on Safety Assessment of NPPs to Assist Decission Making Workshop Information IAEA Workshop Lecturer.
Version 1.0, May 2015 BASIC PROFESSIONAL TRAINING COURSE Module XX Regulatory control Case Study This material was prepared by the IAEA and co-funded by.
NIEP Evaluation PO&A “How-to” Guide and Issue Classification
DCPP Performance Based on NRC Performance Indicators
South Carolina Perspective on Part 61 Proposed Revisions
Flooding Walkdown Guidance
Mitigation of Beyond Design Basis Events (MBDBE) Rule Implementation
NRC Cyber Security Regulatory Overview
First Break To establish minimum safety requirements when performing a first break “First Break” – Refers to the initial opening of piping/equipment.
NRC Event Number – Event Date
Monitoring Cathodic Protection Effectiveness and Record keeping
Control of Hazardous Energy
Unit I Module 3 - RCM Terminology and Concepts
TRTR Briefing September 2013
PREREQUISITE PROGRAMS
BASIC PROFESSIONAL TRAINING COURSE Module XX Regulatory control Case Study Version 1.0, May 2015 This material was prepared by the IAEA and.
GL 51 – Statistical evaluation of stability data
Nonconformity Writing
Presentation transcript:

ISTOG INDUSTRY ISSUES Interactive Session Gregg Joss (Ginna Station Vice Chair ISTOG) Ron Lippy (True North Consulting ISTOG Facilitator)

Topic 1—Check Valve Categorization Topic 1: When is a Check Valve a Category A/C Valve and when is it a Category C Valve?

Topic 1—Check Valve Categorization ISTC-1300 Valve Categories Valves in ISTC scope shall be categorized as: Category A Category B Category C Category D When more than one distinguishing category characteristic is applicable, all requirements of each of the individual categories are applicable, although duplication or repetition of common testing requirements is not necessary.

Topic 1—Check Valve Categorization Definitions: (From OM Code ISTC-1300) Category C—Valves that are self- actuating in response to some system characteristic, such as pressure(relief valves) or flow direction (check valves) for fulfillment of the required function(s), as specified in ISTA-1100.

Topic 1—Check Valve Categorization Category A—Valves for which seat leakage is limited to a specific maximum amount in the closed position for fulfillment of their required function(s), as specified in ISTA If a check valve has the characteristics of both Cat C and Cat A, it is considered Cat A/C.

Topic 1—Check Valve Categorization Licensee should consider Whether the flow requirements for connected systems can be achieved with the maximum possible leakage thru the CV Effect of reduced system flows as a result of leakage thru the CV on other systems/components Consequences of loss of water on system inventory Effect of backflow thru the CV on piping/components (i.e. temperature and thermal stresses The radiological exposure to plant personnel and the public.

Topic 1—Check Valve Categorization Per the NUREG 1482, R1, section 4.1 “if any of the above considerations indicate that Category C testing may not be adequate, licensees should assign the check valve to Category A/C and should comply with the associated leak testing requirements.”

Topic 1—Check Valve Categorization NRC Workshop Summary (July 1997), A valve which has a specific leakage limit assigned for the close direction is leak tested per Category A requirements. If a system has a leakage limit (e.g., for required inventory), but the individual valve(s) have no specific leakage assigned (as in off-site dose analysis), are the system valves required to be Category A in the IST program? If no, why are containment isolation valves required to be Category A, since the leakage limit is for the whole system (i.e., the containment)?

Topic 1—Check Valve Categorization The staff recently evaluated this issue (Reference letter dated August 20, 1996 from NRC to Arkansas Nuclear One, Docket and 368, “Safety Injection System Recirculating Valve Leak Test Requirements, Arkansas Nuclear One, Units 1 and 2”), and has determined that if a licensee has determined that a total system leakage limit, rather than a valve specific leakage limit is appropriate, Category A does not apply and reverse flow closure verification meets the inservice testing requirements for valve seating.

Topic 1—Check Valve Categorization Containment Isolation valves have a total system limit (i.e., 0.60 La per 10 CFR 50, Appendix J), therefore these valves would not have to be classified Category A, unless Option B of Appendix J was utilized or the licensee requires each valve’s leakage to be limited to a specific amount (See interpretation XI-81-01). Option B requires that a performance criterion be established for Type C tests. The staff in GL 89-04, Position 10, however states that all containment isolation valves that are included in the Appendix J program should be included in the IST program a Category A or A/C valves. Additional staff guidance may be required?????

Topic 1—Check Valve Categorization Clear that the regulatory position is NOT “fixed” as of today. We need to “help” the NRC establish clear definitions of the Categories by using the Code Committee to “clarify” the positions for Categorization. Example: – Category A and A/C valves are valves for which maximum leakage has been established based on guidance for the “operability” of the check valve. – Category C valves are valves for which maximum leakage has NOT been established based on guidance for the “operability” of the check valve.

Topic 1—Check Valve Categorization The concern exists as to what constitutes a Cat AC valve. Need to discuss “gross leakage” and “specified leakage” There has recently been some regulatory questions as to when a check valve is considered Cat AC and when it is ONLY a Cat C check valve.

Topic 1—Check Valve Categorization In other words, if the leakage of the valve is a requirement for determining “operability” of the valve versus “operability” of the system. Just some thoughts….. How about some of yours????

Topic 2—General Check Valve Issues: When is a check valve Active? (ISTA-2000) OM Code, Subsection ISTC-1300 Valve Categories – Category C: Valves that are self-actuating in response to some system characteristics, such as flow direction for fulfillment of the required function(s).

Topic 2—General Check Valve Issues: Active Valve (ISTA-2000): Valve(s) that are required to change obturator position to accomplish a specific function in shutting down a reactor to the safe shutdown condition, maintaining the safety shutdown condition, or mitigating the consequences of an accident.

Topic 2—General Check Valve Issues: When is a check valve Passive? Passive Valve: Valves that maintain obturator position and are not required to change obturator position to accomplish the required function(s) in shutting down a reactor to the safe shutdown condition, maintaining the safe shutdown condition, or mitigating the consequences of an accident.

Topic 2—General Check Valve Issues: When is a check valve Passive? NUREG 1482, R1, section 4.1 – A check valve would ONLY be considered Passive: Flow was blocked to the CV (flange, manual valve, etc.,) The obturator was POSITIVELY held in place (Stop- Check Valve)

Topic 2—General Check Valve Issues: Check Valves—Cat C Require testing dependent upon safety function: – Exercise full stroke Open – Exercise full stroke Close – Exercise normal flow Bi-directional (if applicable) – Leakage testing (if applicable) – PIT (if applicable)

Topic 2—General Check Valve Issues: NUREG 1482, R1, section 4.1 “The NRC staff considers check valves, and other automatic valves designed to close without operator action after an accident and for which flow is not blocked as “active” valves that would be classified as such in the IST program. Similar criteria could be applied to the opening function of a check valve.”

Topic 2—General Check Valve Issues: Bi-directional testing of CVs? – OM Code ISTC-3522 Category C CVs shall be exercised as follows: During Operation at Power

Topic 2—General Check Valve Issues: Exercised or examined in such a manner that verifies obturator travel. ISTC-5221(1)—CVs that have a safety function in both open and close directions shall be exercised by initiating flow and observing that the obturator has traveled to either the full open position or to the position required to perform its intended function and verify that on cessation or reversal of flow the obturator has traveled to the seat.

Topic 2—General Check Valve Issues: ISTC-5221(2)—CVs that have a safety function in only the open direction shall be exercised by initiating flow and observing that the obturator has traveled either the full open position or to the position required to perform its intended functions, and verify closure.

Topic 2—General Check Valve Issues: ISTC-5221(3)—CVs that have safety function in only the close direction shall be exercised by initiating flow and observing that the obturator has traveled at least the partially open position and verify that on cessation or reversal of flow the obturator has traveled to the seat. Observations shall be made by observing a direct indicator (e.g. position-indicating device) or by other positive means (e.g. changes in system pressure, flow rate, level, temperature, seat leakage testing, or NIT.

Topic 2—General Check Valve Issues: NIT for CVs Acoustics Magnetics Radiography Ultrasonics

Topic 2—General Check Valve Issues: CV Disassembly and Inspection Grouping Documented in IST Program Technically Justified Consider as a minimum – Valve Mfg. – Design – Service – Size – Materials of construction – Orientation

Topic 2—General Check Valve Issues: Maintenance and Modification history Potential Flow Instabilities Required degree of disassembly Need for tolerances or critical dimension checks During disassembly Full stroke motion of the obturator verified Full stroke motion of the obturator re-verified immediately prior to completing reassembly

Topic 2—General Check Valve Issues: At least one valve from each group DI each RFO All valves in group DI once every 8 years After Reassembly Partial Stroke (if practicable) and leak test (if applicable), before return to service.

Topic 2—General Check Valve Issues: CVs that have their obturator disturbed before full stroke motion is verified shall be examined to determine if a condition exists that could prevent full opening or reclosure of the obturator (e.g. spring loaded lift cvs or cvs with the obturator supported from the bonnet)

Topic 2—General Check Valve Issues: Condition Monitoring Rules (OM Code ISTC-5222, Appendix II) Improve Valve Performance (High Failure Rate, cannot be exercised under NOP/NOT or shutdown—i.e. DI, exhibit unusual abnormal or unexpected behavior during exercising or operation, or the owner elects to monitor for improved valve performance)

Topic 2—General Check Valve Issues: Optimize Testing/Examination/PM activities in order to maintain the continued acceptable performance of a select group of CVs (Had performance improved under CMP, cannot be exercised or are not readily exercised during NOP/NOT or shutdown, can only be DI or owner elects to optimize all of the associated activities of the valve group in a consolidated program.

Topic 2—General Check Valve Issues: Permits “cherry picking” of valves If CMP is discontinued then the requirements of ISTC-5221 shall apply. CMP Program Attributes: Groupings – Determined by Owner – Technically Justified – Based on:

Topic 2—General Check Valve Issues: The intended purpose of the CMP (e.g. improve performance or optimize testing/examination/PM activities Analysis of test results and maintenance history Design characteristics, application and service condition Owner must assess the significance to plant safety as a result of extended intervals Consider DI grouping details

Topic 2—General Check Valve Issues: Analysis Owner performs an analysis of the test and maintenance history of a valve or group of valves in order to establish the basis for specifying IST, exam, PM activities. Must include: Common failure or maintenance patterns Analyze patterns to determine their significance and to identify potential failure mechanisms Determine if certain PM activities would mitigate the failure or maintenance patterns Determine if periodic disassembly and exam activities would be effective in monitoring for these failure mechanisms Determine if changes in the valve grouping are required

Topic 2—General Check Valve Issues: CM Activities Valve obturator movement during applicable test or exam activities shall be sufficient to determine the bidirectional functionality of the moving parts A full stroke open exercise or a open test to the position required to perform its intended function is not required Performance Improvement Activities If sufficient info is not currently available to complete the analysis required in CMP:, or if the analysis is inconclusive—then the following activities shall be performed at sufficient intervals over an interim period of the next 5 years or two roes whichever is less to determine the cause of the failure or the maintenance patters

Topic 2—General Check Valve Issues: Identify interim tests (e.g. NIT) to assess the performance of the valve or the group of valves. Identify interim exams to evaluate potential degradation mechanisms Identify other types of analysis that will be performed to assess CV condition Identify which of these activities will be performed on each valve in the group Identify the interval of each activity Identify attributes that will be trended. Trending and evaluation of existing data must be used as the bases to reduce or extend the time interval between tests or exams

Topic 2—General Check Valve Issues: Complete or revise the CMP test plans to document the CV program performance improvement activities and their associated frequencies

Topic 2—General Check Valve Issues: Perform these activities at their associated intervals until: Sufficient info is obtained to permit an adequate evaluation of the specific application or Until the end of the interim period After performance, review those attributes that were selected for trending along with the results of each activity to determine if any changes to the CMP are required. If significant changes to the CMP area required the program shall be revised prior to the performance of the next activity and the applicable requirements of Grouping analysis and CMP activities shall be repeated.

Topic 2—General Check Valve Issues: Optimization of CM Activities If sufficient info is available to asses the performance adequancy of the CV or the group then: Identify applicable PM activities including their associated intervals that are required to maintain the continued acceptable performance of the cv or group of cv. Identify the applicable exams activities and associated interval s that will be use d to periodically assess the condition of each cv or group of cvs

Topic 2—General Check Valve Issues: Optimization of CM Activities Identify the applicable test activities and intervals Identify the applicable interval of each activity, interval extensions shall be limited to one fuel cycle per extension. Intervals shall not exceed the maximum intervals show below. All valves in a group sampling plan must be tested or examined again before the interval can be extended again or until the maximum interval would be exceeded. The requirements of ISTA-3120 do not apply (Traditional IST intervals (10 years).

Topic 2—General Check Valve Issues: Identify attributes that will be trended. Trending and evaluation of existing data must be used to reduce or extend the time interval between tests or examinations. Revise the test plans to document the optimized CMP activities and the associated intervals of each activity Perform the following activities at their associated intervals

Topic 2—General Check Valve Issues: After performance of the activities review the results to determine if any changes to the optimized CMP are required If changes required must revise CMP prior to performance of the next activity Changes to IST intervals must consider plant safety and be supported by trending and evaluating both generic an plant-specific performance data to ensure that the component is capable of performing tits intended functions over the entire interval.

Topic 2—General Check Valve Issues: Group Size Maximum Interval Note 1, years >/=

Topic 2—General Check Valve Issues: Note 1: The maximum interval was determined by how many interval extensions could be obtained based on an 18-month or 24-month fuel cycle. All of the valves had to be tested or examined within the maximum interval to be considered a valid extension.

Topic 2—General Check Valve Issues: Corrective Maintenance If corrective maintenance is performed on a cv the analysis used to formulate the basis of the CMP activities for that cv and the assoc valve group shall be reviewed to determine if any changes are required.

Topic 2—General Check Valve Issues: Documentation Include List of valves in the CMP List of valves in each valve group Dates valves were added/deleted to CMP and reason for inclusion/deletion

Topic 2—General Check Valve Issues: Documentation Analysis forming basis for CMP Identified failure or maintenance history pattern for each valve CMP activities including the trended attributes Methods of CV Testing/Examination, basis for associated intervals for each valve and valve group.

Topic 2—General Check Valve Issues: Methods of CV Testing/Examination Exercise with flow/dp NIT Leakage testing (Appendix J) DI PM activities

Topic 3 IST Pump Testing (in particular CPT) Group A Pumps which are operated routinely during operation, shutdown or startup. – Component Cooling Water Pumps – Service Water Pumps – Auxiliary Feedwater Pumps’ – Shutdown Cooling Water Pumps

Topic 3 IST Pump Testing (in particular CPT) Group A Testing – Frequency - Quarterly – Reference Value - +/- 20% of Design Flow or as close as practicable – Vibration Measurements Required – Hold time required (2 minutes after stabilization) – Instruments– No change from previous OM Code

Topic 3 IST Pump Testing (in particular CPT) Group B Pumps which are NOT routinely operated except for testing. – Turbine Driven Auxiliary Feedwater Pumps – High Pressure Safety Injection Pumps – Containment Spray Pumps

Topic 3 IST Pump Testing (in particular CPT) Group B Testing – Frequency - Quarterly – Reference Value - +/- 20% of Design Flow or as close as practicable – No vibration Measurements Required – No hold time required – Instruments– No change from previous OM Code

Topic 3 IST Pump Testing (in particular CPT) CPT Testing – Frequency - Biennially – Reference Value - +/- 20% of Design Flow – Vibration Measurements Required – Hold time required – Instruments Flow- +/- 2% of either FS or of reading Dp/pressure - +/- 0.5% FS or reading

Topic 3 IST Pump Testing (in particular CPT) Reference Values are established ONLY when the pump is know to be Operating acceptably—ISTB-3300(c) NUREG 1482, R1, section 5.2.1— Licensees shall only establish reference values when the pump is known to be operating acceptably