Legal Issues for Construction Managers ACCM 5 th Annual Conference: Building Education Facilities Against the Odds May 19, 2009 Presented By: Mark W. Kelley.

Slides:



Advertisements
Similar presentations
Organization of Primary Entities
Advertisements

Construction Contracting
Roles & Responsibilities in Construction Management
Managing Construction Risks
RFP vs. IFB A BASIC APPROACH TO THE BID PROCESS – WHEN RFPs or IFBs ARE USED 2010 AASBO Spring Pre-Conference Workshop Rosa Saenz, PGPC, Inc. Bill Munch,
Nabil dmaidi1 Miller Act H Enacted in 1935 H Federal Contracts over $25,000 H Contractor shall provide Bonds H Performance Bonds in the amount to protect.
Uniform Public Construction Cost Accounting (UPCCA) presented by: Kevin Cobb AIA/ARA, the Addington Partnership William Duncan IV, Taft College December.
Surety Bond Claims State of Colorado 05/15/2013. State of Colorado Surety Bond Overview Construction Contract Surety Bonds  Bid – Guarantees bidder will.
Working the Triple Constraint KEEPING PROJECTS UNDER BUDGET AND ON-TIME WHILE ENSURING QUALITY AND MANAGING STAKEHOLDER REQUIREMENTS Douglas Rogers, Director.
Presented By: John D. Miller
Airport Owner’s Guide to Project Delivery Systems Prepared by: The Joint Committee of ACI-NA, ACC and AGC.
CONSTRUCTION ADMINISTRATION Preconstruction Operations Dr. Alaattin Kanoğlu Spring, 2013 Professional Practice Management I.B.U. Architecture Undergraduate.
14.21 Contract Closeout Procedure Update Notice of Completion, Release of Retention and Punchlist Resolution December 8, 2005.
DPW General Conditions Articles 32 through 37. Articles Covered Today  32 Owner’s Right to Withhold Payment  33 Owner’s Right to Stop Work and Terminate.
Your Deliver Method... …Pick it Early
Resolve Business Disputes and Select and Prepare a Construction Contract Lesson Seven Cert IV - M. S. Martin March 2012.
Community Facility Loans/Grants Architect Flow Chart Owner has need for project. RD Area Office is contacted. RD visits project site and discusses project.
Construction Operations Ch 15. Opening a Project Before Contractor is allowed on site it must –Make sure contractor has all required insurance –Obtain.
PROJECT DELIVERY SYSTEMS
Conditions of the Contract for Construction
Chapter 17 Construction Bonds Vanessa S. Werden
RFP Overview Alan A. Phillips, CPPB CTPM Texas Southern University Summer 2012.
Discussion Topics Construction Contract Administration Lessons Learned Other Construction Issues Questions? / Comments (Anytime)
Project Delivery Overview June 2015 Final PD Training FMD WUSM 6/15/15 1.
U.S. Small Business Administration
SPORT MANAGEMENT 302 (a) B. FLAHERTY Questions/Comments?? Quiz next week, Chapters 1-6 Complete Chapter 7 “Funding and the Bid Process” Chapter 8 “Constructing.
Surety Basics 2013 Construction Opportunities Conference
This Presentation is a Copyrighted Property of Waller S. Poage, AIA, CSI, MAI, CVS – All Rights are Reserved Session CDT 01 – Fundamentals Lesson CDT 1.3.
Construction: Legal Issues. Legal Issues In the Bidding Process Timing of various activities has legal implications. During the bidding process: –A bid.
Introduction Time Quality Cost Project Constraints Success Introduction.
NOTICE OF CLAIM – HOW TO AVOID THE TRAP© LAW OFFICES OF MICKEY BEISMAN
Construction Contracts and Project Delivery Methods
S10 CONS5Q25 Lara Tookey. Review of estimators workings Decision on what margin to apply Bid submission details Submit your Tender.
CEM 520 Construction Contracting Dr S. Almohawis Course Content.
Compensation events and claims Presented by Prof. Khem Dallakoti.
Richard E. Thompson II, Esq.
Labor Standards Pam Truitt  September 10, Key Regulations & Statutes  Davis-Bacon Act  Copeland Act (Anti-kickback Act)  Contract Work Hours.
CVE 4070 Construction Engineering Test-2 & Review Prof. Ralph V. Locurcio, PE.
Risk Assignment in The Delivery of a Project  RISK! –Construction projects have lot of it –Contractors manage it –Owners pay for it.
January 24, …a delivery method which entails a commitment by the Construction Manager to deliver the project within a Guaranteed Maximum Price (GMP).
CONSTRUCTION ADMINISTRATION Construction Operations Dr. Alaattin Kanoğlu Spring, 2013 Professional Practice Management I.B.U. Architecture Undergraduate.
January 31, …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.
Contract Training Class I
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
You passed the Bond or secured some funds What do we do now? 2014.
FAC11 - CONSTRUCTION 101: WHERE THE RUBBER MEETS THE ROAD APRIL 3-6, 2013, LONG BEACH, CA These materials have been prepared by the CASBO Facilities Professional.
Pre-Construction Activities to include: - Provide effective overlap period and oversight of effort - Estimates during - CPM Schedule - Identify lead-time.
LACCD Building the Future THOMAS HALL Director Facilities Planning and Development.
© 2011 Orbach Huff & Suarez 1 Lease Leaseback Project Delivery Method Kimble Cook Orbach, Huff & Suarez.
CLAIMS MANAGEMENT. PRESENTATION OUTLINE INTRODUCTION TYPICAL CLAIMS AGAINST OWNER TYPICAL CLAIMS AGAINST CONTRACTOR CRITICAL PATH METHODS UTILIZATION.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
UNIVERSITY OF DAR ES SALAAM t Selection and Employment of Consultants Negotiations with Consultants; Monitoring Performance of Consultants; Resolving Disputes.
CVE 4070 Construction Engineering HW #6 review Test-2 & Review Prof. Ralph V. Locurcio, PE.
Introduction to Procurement for Public Housing Authorities Sealed Bids Unit 5.
This training is provided for educational, compliance and loss-prevention purposes only and, absent the express, prior agreement of DWK, does not create.
Measure N Modernization IMPLEMENTATION PROCESS Planning, Bidding, Construction, and Occupancy.
CONSTRUCTION MANAGEMENT AT RISK Prepared by: Nancy Fouad Carey Attorney AGC Alabama Birmingham Section Meeting November 5, 2012.
PWGSC - KOREA 2nd JCC Meeting Canadian Federal Real Property Construction Contracting Presentation by Bruce Fletcher Director General – CASMS - PWGSC November.
CHANGE ORDER/CLAIMS MANAGEMENT MODULE 9. Change Order Management.
What Small and Emerging Contractors Need to Know Understanding the Basics of Contract Surety Bonds © Copyright 2016 NASBP.
Lease-Leaseback Project Delivery Method
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
Construction Oversight
CM at Risk v. Design-Bid-Build
(Additional materials)
FIVE PROJECT PHASES 5C-3 Sun. 8:00-10:00am 21/ 2/2016.
Prime Contractor Performance
Construction Project Delivery Methods
Chapter 2 – Review ‘construction management’
Presentation transcript:

Legal Issues for Construction Managers ACCM 5 th Annual Conference: Building Education Facilities Against the Odds May 19, 2009 Presented By: Mark W. Kelley Miller Brown & Dannis Blair Shahbazian Murphy Austin Adams Schoenfeld LLP

Our Topics  Legal and practical issues with Alternate Project Delivery  What to do when the money runs out (Reprise)  Recordkeeping and documentation

Alternate Project Delivery: Legal Issues

Design-Bid-Build  Sometimes familiar and repetitive is ok; the key is to eliminate the repetitive change order and claims drill that has given this old standby a bad reputation.  Point/counterpoint: a strong prequalification plus competitive bidding is the most economical approach for most districts in today’s markets.

Lease-Leaseback  Ed. Code 17406, an old statute put to an interesting new (relatively) use.  Point/counterpoint: the best compromise between cost and control?  What is the CM’s role in LLB? Developer Developer CM CM Both? Both?

6 D-B-B vs. LLB: Structure Basically Is The Same =Owner Team Owner Construction Manager (Opt.?) Architect LLB Builder or D-B-B Contractor Subcontractors

7 Background: The 3 Contracts  Preliminary Services Agreement: Developer acts as a pre-construction consultant. Developer acts as a pre-construction consultant.  Site Lease: District leases the site to Developer. District leases the site to Developer. Terminates when Facilities Lease terminates. Terminates when Facilities Lease terminates.  Facilities Lease: Developer constructs facility per Plans and Specs. Developer constructs facility per Plans and Specs. Developer leases the facility back to the District. Developer leases the facility back to the District. Developer transfers title of the facility to the District upon final payment. Developer transfers title of the facility to the District upon final payment.

8 Minimizing Risk  Generally recommend a Validation Action once Board approves a LLB contract.  Need a strong selection process to get best Developer.  Owner’s team must closely monitor: Cost vs. estimates Cost vs. estimates Change orders, use of contingency etc. Change orders, use of contingency etc. Final cost Final cost

Disadvantages  Is the final cost of LLB projects higher?  LLB does not automatically bar change orders or claims (but less likely due to Developer’s involvement with design), particularly: Site conditions Site conditions Owner changes (“Scope creep”) Owner changes (“Scope creep”)  Often will be debates over what extra costs are charged to contingency.

CM At-Risk  CMs are responsible for the construction, not just overseeing the construction. Each trade bids separately to the school district but the CM takes over responsibility of the entire construction.  CM at risk is problematic on school projects because there is no clear statutory authority.

CM At-Risk: Legal Considerations  PCC requires award of public school construction to the low bidder.  Govt Code 4526 allows award of CM contracts based on demonstrated competence and professional qualifications--not low bid.  Govt Code defines CM services as project design review and evaluation, construction mobilization and supervision, bid evaluation, project scheduling, cost-benefit analysis, claims review and general management and administration of construction project--but not construction itself.

Ideas, Part 1  Given the potential legal challenges, CMs need to try to have the school districts tailor the CM contracts to minimize the risk that a challenge will be successful. Some suggestions include:

Ideas, Part 2  Each trade contractor needs to provide payment and performance bonds and insurance for its portion of the work.  The CM should only bond its services, not the entire construction project.  If possible, avoid having the trade contracts assigned to the CM by the District.  All documents (contracts, securities in lieu of retention, etc.) should identify the CM as the "CM" and not as the "Contractor."  The CM should not indemnify the District for the trade contractors actions.

What To Do When The Money Runs Out [Are We Really Talking About This Again?!]

Funding Issues  Key issues: Communication Communication What do the contract documents say? What do the contract documents say?  Contract suspension and termination issues How and when an Owner can suspend How and when an Owner can suspend How to minimize and mitigate losses How to minimize and mitigate losses How the team can work together to keep costs and frustration to a minimum How the team can work together to keep costs and frustration to a minimum Issues frequently encountered Issues frequently encountered

Options When Running Out of Funds  Default on the construction contract  Terminate or suspend the contract: For cause For cause For convenience For convenience  Negotiate suspension of the work  Some other ideas

Suspending or Terminating Construction Contracts  First: look at the contract documents for: Termination or suspension for cause Termination or suspension for cause Termination or suspension for convenience Termination or suspension for convenience Force Majeure Force Majeure  Second: figure out where you are on the money and on the construction

Recordkeeping And Documentation [Dull, Yes, But Important!]

Keep It Cool  Recordkeeping needs to be correct, clear, concise and impassionate--tell "what happened"--keep out personal opinions unless absolutely necessary to the factual record.  Personal comments or observations of the contractor's character or personality or similar commentary should never be included.  Solicit the input of the designer when necessary in documenting events--keep track of the designer's time of response--you will also be documenting for the owner the designer's compliance with the standard of care.

Stay On Top  Correctly and clearly document nonconforming work--do not underestimate the cost and amount of labor it will require to complete the work properly.  Timely respond to all inquiries.  Respond fully and completely when the CMm disagrees with contractor comments--especially true with scheduling issues.

Assume That Your Letter Will Be Exhibit A  Remember that everything you say or write may be reviewed by a third party at a later date and you may be deposed on same--don't let anything go unanswered or answered in an incomplete or flippant/passionate manner.

Owner Team’s Monthly Schedule Evaluation Letter from CM to the Contractor. You are currently falling behind your baseline schedule on numerous activities: --Electrical trim and lighting --Interior doors and hardware --Markerboard installation These delays are due solely to your lack of manpower.

Owner Team Identifying the Critical Path Letter from CM to the Contractor. Your letter to the District identifies Owner decisions as critical. However, the critical path is now your rework of the canopy walkways outside the classrooms.

Defining the Cause Letter from Construction Manager to Contractor. Demolition work is still incomplete. Your refusal to perform your contract work continues to severely delay the completion of this building. As discussed, it is apparent that there is a shortage of manpower to complete all the necessary activities.

Notice to Contractor Letter from Owner to Contractor. We are hereby informing you that we will enforce liquidated damages due to your delays in the library building. These delays have prevented the District from taking occupancy.

When the Contractor Keeps the Meeting Minutes There is a significant problem with slow responses to RFI’s and open items, and this has resulted in project schedule delay.

Thank you!  How to Reach Us Mark Kelley (415) Mark Kelley (415) Blair Shahbazian (916) Blair Shahbazian (916)