Objectives To introduce software project management and to describe its distinctive characteristics To discuss project planning and the planning process.
©Ian Sommerville 2004Software Engineering, 7th edition. Chapter 5 Slide 1 Project management.
©Ian Sommerville 2004Software Engineering, 7th edition. Chapter 5 Slide 1 Project management.
Project management l Organising, planning and scheduling software projects l Objectives To introduce software project management and to describe its distinctive.
1 SW Project Management (Planning & Tracking) Dr. Atef Z Ghalwash Faculty of Computers & Information Helwan University.
Project Estimation: Metrics and Measurement
Metrics for Process and Projects
Lecturer: Sebastian Coope Ashton Building, Room G.18 COMP 201 web-page: Project.
©Ian Sommerville 2004Software Engineering, 7th edition. Chapter 1 Slide 1 Project management.
©Ian Sommerville 2006Software Engineering, 8th edition. Chapter 5 Slide 1 Project management.
1 COST ESTIMATION Basics, COCOMO, FP. 2 What is estimated? TIME MONEY TIME: –duration, chronological weeks, months, years –effort, person-month (man-month)
©Ian Sommerville 2000Software Engineering, 6th edition. Chapter 4 Slide 1 COMP201 Project Management.
©Ian Sommerville 2004Software Engineering, 7th edition. Chapter 5 Slide 1 Project management.
1 SOFTWARE PRODUCTION. 2 DEVELOPMENT Product Creation Means: Methods & Heuristics Measure of Success: Quality f(Fitness of Use) MANAGEMENT Efficient &
©Ian Sommerville 2000Software Engineering, 6th edition. Chapter 4 Slide 1 Project management l Organising, planning and scheduling software projects l.
Project Management Hoang Huu Hanh, Hue University hanh-at-hueuni.edu.vn.
Risk Management. If you don't actively attack the risks, they will actively attack you. -Tom Gilb Risk is the possibility of suffering loss, injury, disadvantage,
贾银山 Software Engineering, Chapter 5 Slide 1 Project management.
1 Software Engineering Muhammad Fahad Khan Software Engineering Muhammad Fahad Khan University Of Engineering.
©Ian Sommerville 2000Software Engineering, 7th edition. Chapter 5 Slide 1 Chapter 5 Project Management Modified by Randy K. Smith.
Project management DeSiaMore 1.
©Ian Sommerville 2000Software Engineering, 6th edition. Chapter 4 Slide 1 Concerned with activities involved in ensuring that software is delivered: on.
Estimation Why estimate? What to estimate? When to estimate?
Chapter 6 : Software Metrics
Project Management Estimation. LOC and FP Estimation –Lines of code and function points were described as basic data from which productivity metrics can.
Software Cost Estimation 1. APPROACHES Traditional: LOC estimation Modern: Functional Point Analysis 2.
1 Chapter 5 Project management. 2 Project management : Is Organizing, planning and scheduling software projects.
©Ian Sommerville 2006Software Engineering, 8th edition. Chapter 5 Slide 1 Risk management.
Engineering, 7th edition. Chapter 5 Slide 1 Project management.
Project management Lecture 10. Topics covered Management activities Project planning Project scheduling Risk management.
Requirements Engineering PROJECT MANAGEMENT Part II.
Team7 Team Assignment 2 Software Measurement and Analysis.
Object-Oriented Software Engineering
©Ian Sommerville 2000Software Engineering, 6th edition. Chapter 4 Slide 1 Project management l Organising, planning and scheduling software projects.
Lecture 4 Software Metrics
Chapter 15: Risk Management
©Ian Sommerville 2000 Slide 1 Project management l Organising, planning and scheduling software projects l Objectives To introduce software project management.
CSEM01 - wk8 - Software Planning1 Software Planning CSEM01 SE Evolution & Management Anne Comer Helen Edwards.
Project management.  To explain the main tasks undertaken by project managers  To introduce software project management and to describe its distinctive.
©Ian Sommerville 2004Software Engineering, 7th edition. Chapter 5 Slide 1 Project management.
COOP Seminar – Fall 2008 Slide 1 HOUSTON COMMUNITY COLLEGE SYSTEM SAIGONTECH SAIGON INSTITUTE OF TECHNOLOGY Software Project Management.
Project Management Yonsei University 2 nd Semester, 2012 Sanghyun Park.
Chapter 3 Project Management Chapter 3 Project Management Organising, planning and scheduling software projects.
SEG3300 A&B W2004R.L. Probert1 COCOMO Models Ognian Kabranov.
Software Engineering, 8th edition. Chapter 5 1 Courtesy: ©Ian Sommerville 2006 Oct 13 th, 2008 Lecture # 6 Project management.
Software Engineering Modern Approaches
1 Project management. 2 Topics covered Management activities Project planning Project scheduling Risk management.
Function Points Synthetic measure of program size used to estimate size early in the project Easier (than lines of code) to calculate from requirements.
Estimating “Size” of Software There are many ways to estimate the volume or size of software. ( understanding requirements is key to this activity ) –We.
Chap 4. Project Management - Organising, planning and scheduling
CSC 480 Software Engineering Lecture 5 September 3, 2004.
Project, People, Processes and Products Project management skills – schedule, monitoring, risk management, … People management skills – delegation, mentoring,
Software Engineering (CSI 321) Project Planning & Estimation 1.
©Ian Sommerville 2000Software Engineering, 6th edition. Chapter 4 Slide 1 Project management l Organising, planning and scheduling software projects.
©Ian Sommerville 2004Software Engineering, 7th edition. Chapter 5 Slide 1 Project management.
Project management 1/30/2016ICS 413 – Software Engineering1.
CSC 480 Software Engineering Project Planning. Proposal writing Project planning and scheduling Project costing Project monitoring and reviews Personnel.
©Ian Sommerville 2000Software Engineering, 6th edition. Chapter 4 Slide 1 Chapter 4: Project management l Organising, planning and scheduling software.
Project management (2) By: Zhou Chunlin School of Tourism, Conference and Exhibitions Henan University of Economics and Law.
Project management. Software project management ■It is the discipline of planning, organizing and managing resources to bring about the successful completion.
1 Project management Organising, planning and scheduling software projects.
Estimation Questions How do you estimate? What are you going to estimate? Where do you start?
©Ian Sommerville 2004Software Engineering, 7th edition. Chapter 5 Slide 1 Project management.
COMP201 Project Management.
Project management assignment, Spring 2017
Project management.
Software Engineering (CSI 321)
Management. Management What is a risk? A risk is simply a probability that some adverse circumstance will actually occur.
Chapter 5: Principles of Project Management II
Presentation transcript:

CSC 480 Software Engineering Lecture 6 September 11, 2002

CSC Software Engineering2 9/11/2002 Topics Risk Management Cost Estimation

CSC Software Engineering3 9/11/2002 Risk Management A risk is a probability that some adverse circumstance will occur.  Project risks affect schedule or resources  Product risks affect the quality or performance of the software being developed  Business risks affect the organisation developing or procuring the software

CSC Software Engineering4 9/11/2002 Software Risks

CSC Software Engineering5 9/11/2002 Risk Management Process

CSC Software Engineering6 9/11/2002 The Four Risk Activities Identification Mindset: try to continually identify risks Retirement planning Prioritization Retirement or mitigation

CSC Software Engineering7 9/11/2002 Risk Identification Technology risks People risks Organisational risks Requirements risks Estimation risks

CSC Software Engineering8 9/11/2002 Risks and Risk Types

CSC Software Engineering9 9/11/2002 Risk Analysis Assess probability and seriousness of each risk Probability may be very low, low, moderate, high or very high Risk effects might be catastrophic, serious, tolerable or insignificant

CSC Software Engineering10 9/11/2002 Risk Analysis

CSC Software Engineering11 9/11/2002 Risk Planning Consider each risk and develop a strategy to manage that risk Avoidance strategies  Reduce the probability that the risk will arise Minimisation strategies  Reduce the impact of the risk on the project Contingency plans

CSC Software Engineering12 9/11/2002 Project finish Risk Management Mindset Project start IdentificationRetirement 2. “Java skills not high enough.” 1. “May not be possible to superimpose images adequately.” 1. Retirement by conquest: Demonstrate image super- imposition Risk 1 Risk 2 Risk 1 Project finish Risk 2 2. Retirement by avoidance: Use C++ Project start

CSC Software Engineering13 9/11/2002 Risk Management Strategies

CSC Software Engineering14 9/11/2002 Risk Monitoring Assess each identified risks regularly to decide whether or not it is becoming less or more probable Also assess whether the effects of the risk have changed Each key risk should be discussed at management progress meetings

CSC Software Engineering15 9/11/2002 Risk Factors

CSC Software Engineering16 9/11/2002 Risk Sources Ordered by Importance Lack of top management commitment Failure to gain user commitment Misunderstanding of requirements Inadequate user involvement Failure to manage end-user expectations Changing scope and/or objectives

CSC Software Engineering17 9/11/2002 Likelihood = least likely Impact = least impact Retire- ment cost = lowest retirement cost Priority computation Resulting priority Lowest number handled first The highest priority risk 10 (most likely) 10 (most impact) 1 (lowest retiremen t cost) (11-10) *(11-10) *1 1 The lowest priority risk 1 (least likely) 1 (least impact) 10 (highest retiremen t cost) (11-1) *(11-1) * Compute Risk Priorities

CSC Software Engineering18 9/11/2002 Range of cost estimates after conceptualization phase, based on actual cost of $1 Integration/Test Design Implementation Requirements analysis $1 25c $4 $1 Conceptual- ization phase Range of cost estimates after requirements analysis phase Range of Errors in Estimating Eventual Cost

CSC Software Engineering19 9/11/2002 Cost Estimation Roadmap 1A. Use comparisons with past jobs to estimate cost & duration directly or to estimate lines of code. and / or 1B. Use function point method to estimate lines of code 1B.1 Compute un-adjusted function points. 1B.2 Apply adjustment process. 2. Use lines of code estimates to compute labor and duration using COCOMO formulas.

CSC Software Engineering20 9/11/2002 Function Point Computation Function External Inputs (EI) External Inquiries (EIN) External Outputs (EO) file External Logical Files (ELF) file Internal Logical Files (ILF)* * Internal logical grouping of user data into files Logical group of user data Logical group of user data Logical group of user data For a Single Function (IFPUG)

CSC Software Engineering21 9/11/2002 Function Point Computation Ext. inputs EI  … 3 or… 4 or... 6 = ___ Ext. outputs EO  … 4 or … 5 or... 7 = ___ PARAMETER simple complex countTotal ■ First compute unadjusted FP ■ Followed by applying adjustment process …

CSC Software Engineering22 9/11/2002 Sample FP Computation

CSC Software Engineering23 9/11/2002 General Characteristics for FP 1. Requires backup/recovery? Data communications required? Distributed processing functions? 0 Adjustment incidental average essential Case study none moderate significant

CSC Software Engineering24 9/11/2002 Computation of Adjusted FP (Adjusted) Function points = [ Unadjusted function points ]  [  ( total general characteristics ) ]

CSC Software Engineering25 9/11/2002 Constructive Cost Model (COCOMO) Can we use the estimated KLOC as an effort estimation?  KLOC / (KLOC/(man*hr)) = man * hr The answer is NO  The communication, documentation, and integration efforts increase faster than the product size grows  Effort (in man-month) is exponential in size

CSC Software Engineering26 9/11/2002 COCOMO Once we know the effort estimation in man-month, can we just divide it by the number of developers to get the duration?  Duration = Effort / (# developers) The answer is NO, again  It takes one chef five hours to cook a turkey. Can we then expect five chefs get one ready in one hour?

CSC Software Engineering27 9/11/2002 COCOMO Formulas (Boehm) Applies to design through integration & test. *“Effort” = total person-months required. (2) Duration for increasing Effort* ( y b 2.5x 0.35 ) (1) Effort* for increasing LOC ( y b 3x 1.12 ) exponent: < 1 > 1

CSC Software Engineering28 9/11/2002 Basic COCOMO Formulae Effort in Person-months = a  KLOC b Duration = c  Effort d Software Project a b c d Organic Semidetached Embedded Empirical factors due to Boehm [Bo]

CSC Software Engineering29 9/11/2002 Computing COCOMO - Case Study

CSC Software Engineering30 9/11/2002 Selected References [BO] Barry Bohem, Software Engineering Economics, Englewood Cliffs, NJ: Prentice Hall, 1981 [SPR] 12/99http:// Now with a fee ($75)