BILCW07, Feb 2007, H.WeertsSlide 1 RPC-DHCAL Progress & Status H.Weerts BILCW07, Beijing, February 4 – 7, 2007 Research done as part of program of CALICE.

Slides:



Advertisements
Similar presentations
Status of DHCAL Slice Test Data Analysis Lei Xia ANL-HEP All results preliminary.
Advertisements

1 m 3 Prototype Digital Hadron Calorimeter Collaborators Argonne National Laboratory Boston University University of Chicago Fermilab University of Texas.
Bulk Micromegas Our Micromegas detectors are fabricated using the Bulk technology The fabrication consists in the lamination of a steel woven mesh and.
31 May 2007LCWS R&D Review - Overview1 WWS Calorimetry R&D Review: Overview of CALICE Paul Dauncey, Imperial College London On behalf of the CALICE Collaboration.
RPC Update José Repond Argonne National Laboratory American Working Group On Linear Collider Calorimetry 24 November 2003 What’s new since September…
28 August 2002Paul Dauncey1 Readout electronics for the CALICE ECAL and tile HCAL Paul Dauncey Imperial College, University of London, UK For the CALICE-UK.
6 June 2002UK/HCAL common issues1 Paul Dauncey Imperial College Outline: UK commitments Trigger issues DAQ issues Readout electronics issues Many more.
RPC Update José Repond Argonne National Laboratory American Working Group On Linear Collider Calorimetry 16 September 2003 What’s new since Cornell…
Mauro Raggi Status report on the new charged hodoscope for P326 Mauro Raggi for the HODO working group Perugia – Firenze 07/09/2005.
Andy White U.Texas at Arlington (for J.Yu, C.Han, J.Li, D.Jenkins, J.Smith, K.Parmer, A.Nozawa, V.Kaushik) 10/18/04 IEEE/NSS Digital Hadron Calorimetry.
Sept. 24, Status of GEM DHCAL Jae Yu For GEM-TGEM/DHCAL Group Sept. 24, 2010 CALICE Collaboration Meeting Univ. Hassan II, Casablanca Introduction.
Reports from DESY Satoru Uozumi (Staying at DESY during Nov 11 – 25) Nov-21 GLDCAL Japan-Korea meeting.
Development of Particle Flow Calorimetry José Repond Argonne National Laboratory DPF meeting, Providence, RI August 8 – 13, 2011.
DBD HCAL section report and RPC DHCAL progress Lei Xia ANL - HEP.
1 Status of GEM DHCAL Andy White For GEM-TGEM/DHCAL Group March 21, 2011 ALCPG11 Workshop Univ. of Oregon Introduction 30cmx30cm 2D readout with KPiX chip.
Towards an RPC-based HCAL Design Stephen R. Magill Argonne National Laboratory Digital HCAL for an E-Flow Calorimeter Use of RPCs for DHCAL RPC Design.
Development of a DHCAL with Resistive Plate Chambers ECFA/DESY Workshop at NIKHEF, Amsterdam, Netherlands April 1 - 4, 2003 José Repond Argonne National.
SiD R&D on PFA and Calorimetry -> IDAG guidance. -> Present PFA situation. -> Developing a timeline for PFA development. -> Calorimetry aspects.
José Repond Argonne National Laboratory Status of the DHCAL Project SiD Collaboration Week January 12 – 14, 2015 SLAC.
Digital Hadron Calorimeter (DHCAL) José Repond Argonne National Laboratory CLIC Workshop 2013 January 28 – February 1, 2013 CERN, Geneva, Switzerland.
Hadron Calorimeter Summary Andy White SiD Workshop, SLAC October 2006.
SiD Concept – R&D Needs Andy White U. Texas at Arlington SiD Concept Meeting LCWS06 Bangalore, India March 11, 2006.
Recent DHCAL Developments José Repond and Lei Xia Argonne National Laboratory Linear Collider Workshop 2013 University of Tokyo November 11 – 15, 2013.
Tests of a Digital Hadron Calorimeter José Repond Argonne National Laboratory CALICE Collaboration Meeting March 10 – 12, 2010 University of Texas at Arlington.
DHCAL Overview José Repond Argonne National Laboratory CALICE Collaboration Meeting DESY, Hamburg, Germany March 20 – 22, 2013.
SID RAL meeting; April 2008 H.Weerts DHCAL status, progress & future Based on RPC efforts in CALICE mostly by US groups H.Weerts for DHCAL group.
NUMI Off Axis NUMI Off Axis Workshop Workshop Argonne Meeting Electronics for RPCs Gary Drake, Charlie Nelson Apr. 25, 2003 p. 1.
The DHCAL Data Analysis José Repond CALICE Meeting, Prague, September 10 – 12, 2007.
Calibration of a Digital Hadron Calorimeter with Muons Burak Bilki d, John Butler b, Tim Cundiff a, Gary Drake a, William Haberichter a, Eric Hazen b,
Construction and Operation of DHCAL Fermilab Test Beam Facility Lei Xia ANL_HEP.
5 February 2003Paul Dauncey - Calice Status1 CALICE Status Paul Dauncey Imperial College London For the CALICE-UK groups: Birmingham, Cambridge, Imperial,
Towards a 1m 3 Glass RPC HCAL prototype with multi-threshold readout M. Vander Donckt for the CALICE - SDHCAL group.
RPC-DHCAL Progress Report José Repond Argonne National Laboratory SiD Workshop, FNAL, April 9 – 11, 2007.
Update on DHCAL and RPC progress Lei Xia ANL - HEP.
May 31, 2007CALICE DHCAL J. Yu 1 Gas DHCAL R&D May 31, 2007 WWS CAL R&D Review, DESY Jae Yu University of Texas at Arlington For CALICE DHCAL Groups Introduction.
ILC Calorimetry Test Beam Status Lei Xia ANL HEP.
Noise and Cosmics in the DHCAL José Repond Argonne National Laboratory CALICE Collaboration Meeting University Hassan II Casablanca, Morocco September.
Lei Xia ANL – HEP. Physics prototype: proof of principle Linearity CALICE SiW ECAL.
A Hadron Calorimeter with Resistive Plate Chambers José Repond Argonne National Laboratory Presented by Andy White University of Texas at Arlington LCWS.
DHCAL Overview José Repond Argonne National Laboratory CALICE Collaboration Meeting Argonne National Laboratory March 19 – 21, 2014.
Application of Large Scale GEM for Digital Hadron Calorimetry Jae Yu For GEM DHCAL Group June 11, 2011 TIPP 2011 The Goals 30cmx30cm 2D readout with KPiX.
A Hadron Calorimeter with Resistive Plate Chambers José Repond Argonne National Laboratory CALOR 2006, Chicago, June 5 – 9, 2006.
11 October 2002Paul Dauncey - CDR Introduction1 CDR Introduction and Overview Paul Dauncey Imperial College London.
US DHCAL Status Lei Xia Argonne National Laboratory.
1 Progress from José Repond Argonne National Laboratory LCWS 2007, DESY, May 30 – June 3, 2007 Emphasis on test beam results.
European DHCAL development European DHCAL development CIEMAT,IPNL,LAL, LAPP,LLR, PROTVINO, SACLAY CIEMAT,IPNL,LAL, LAPP,LLR, PROTVINO, SACLAY Status :
Digital Hadron Calorimetry for the International Linear Collider Using Gas Electron Multiplier Technology Andy White University of Texas at Arlington (for.
José Repond Argonne National Laboratory LCWS, Vancouver, Canada, July 19 – 22, 2006 American Test Beam Plans.
Future R&D of the RPC based Digital Hadron Calorimeter (DHCAL) Lei Xia ANL_HEP.
DHCAL Jan Blaha R&D is in framework of the CALICE collaboration CLIC08 Workshop CERN, 14 – 17 October 2008.
Future DHCAL Activities José Repond Argonne National Laboratory CALICE Meeting, CERN, May 19 – 21, 2011.
SDHCAL. outline  SDHCAL concept, validation and construction  Test Beam and technological prototype performance  Perspectives and Conclusion  SDHCAL.
AHCAL Electronics. Status of Integration Mathias Reinecke for the DESY AHCAL developers AHCAL main and analysis meeting Hamburg, July 16th and 17th, 2009.
G. Drake Electronics for DHCAL R&D Oct. 13, 2005 p. 1.
DHCAL Progress Report José Repond Argonne National Laboratory SiD Meeting, SLAC, October 26, 2006.
Test Beam Request for the Semi-Digital Hadronic Calorimeter
A Digital Hadron Calorimeter Resistive Plate Chambers
Recent DHCAL Developments
SiD Calorimeter R&D Collaboration
Construction and Testing of a Digital Hadron Calorimeter Prototype
(My personal) CALICE Report
The DHCAL: an overview José Repond Argonne National Laboratory
State-of-the-art in Hadronic Calorimetry for the Lepton Collider
GEM-based Digital Hadron Calorimetry for SiD
   Calorimetry et al.    SUMMARY 12 contributions Tile HCAL
GEM-based Digital Hadron Calorimetry for SiD
GEM DHCAL Status and Plans
Tests of a Digital Hadron Calorimeter
Tests of a Digital Hadron Calorimeter
Presentation transcript:

BILCW07, Feb 2007, H.WeertsSlide 1 RPC-DHCAL Progress & Status H.Weerts BILCW07, Beijing, February 4 – 7, 2007 Research done as part of program of CALICE collaboration with main efforts from: Argonne National Lab Boston Univ. Univ. of Chicago Fermilab Univ of Iowa Univ. of Texas, Arlington

BILCW07, Feb 2007, H.WeertsSlide 2 Introduction Vertical Slice Test Test of ~8 chambers with complete electronics At MTBF in Spring 2007 Mechanical DCAL2 chip Pad and Front-end boards Data concentrators Data collectors DAQ software Beam telescope, HV, gas Prototype Section plans Measurements with complete 1m 3 section Hopefully starting in 2008 Funding Outline

BILCW07, Feb 2007, H.WeertsSlide 3 Introduction I Big Picture:There are several technologies being pursued as options for HCAL for ILC detectors. Vary from scintillator (tiles or fibers) with analog readout to gas based calorimeters with digital/multibit readout. In this talk present progress on HCAL for a PFA application: Gas calorimeter using RPC’s and a digital readout system Transverse sampling is 1 x 1 cm x cm  high channel count All these options are either new technologies or have aspects that need to be verified before they can be used for an ILC HCAL Either use PFA, which requires very fine longitudinal and transverse segmentation OR compensating calorimetry ( for all components ( EM, charged & Neutral). Precision required/aimed for jet energy demands new and novel approaches Options: Lot of efforts by many ( not coupled)

BILCW07, Feb 2007, H.WeertsSlide 4 Introduction II Try to make this work and prove feasibility for ILC Transverse sampling is 1 x 1 cm x cm  high channel count Example:A 1m 2 plane has 10,000 channels = complete tilecal of ATLAS A 1m 3 typical “module” for a testbeam consists of 40 planes  400K channels. This is a LARGE undertaking ( make stable and understood). Never done before. Approach: Build a vertical slice, with the final components and data handling and collection system that will be used for a 1m 3 test, corresponding to ~2000 channels i.e. proof of principle Goal: Verify that noise, random and coherent, is under control, that channels are stable, can be monitored and calibrated, proof stable operations, verify response to cosmics and testbeam. After “proof of principle” build the 400,000 channel system on same technology Detector choice RPC, simple, large signals, easy transverse segmentation Readout 1 x 1cm 2 sampling, using digital ( =1 bit) readout Use with RPC, but can be used for others (GEM, etc) Goal:

BILCW07, Feb 2007, H.WeertsSlide 5 Staged approach IR&D on RPCs Develop concept of digital readout system RPC Tests with cosmic rays and in particle beams IIPrototyping of RPCs for prototype section (PS) Prototyping of all components of digital readout for PS Vertical slice test in particle beam IIIConstruction of a 1m 3 Prototype Section with RPCs Detailed test program in Fermilab test beam IVFurther R&D on RPCs and electronic readout system VScalable prototype Detailed test program in test beam Done Planned for 2008 Earliest in 2009 Earliest in 2010 Planned for 2007

BILCW07, Feb 2007, H.WeertsSlide 6 Vertical Slice Test

BILCW07, Feb 2007, H.WeertsSlide 7 Vertical Slice Test Uses the 40 DCAL ASICs from the 2 nd prototype run Equip ~8 chambers with 4 DCAL chips each 256 channels/chamber ~2000 channels total Chambers interleaved with 20 mm copper - steel absorber plates Electronic readout system (almost) identical to the one of the prototype section Tests in MTBF beam planned for Spring 2007 → Measure efficiency, pad multiplicity, rate capability of individual chambers → Measure hadronic showers and compare to simulation Validate RPC approach to finely segmented calorimetry Validate concept of electronic readout

BILCW07, Feb 2007, H.WeertsSlide 8 Mechanical: RPC chamber design New design with simplified channels 1 st chamber assembled and tested → Excellent performance Thickness ~3.5 mm Glass HV Mylar Signal Pad(s) Signal path Fishing line Channel Resistive paint 6.9 kV 7.9 kV Avalanche Plateau Material in hand for remaining chambers

BILCW07, Feb 2007, H.WeertsSlide 9 Mechanical: Stack for Vertical Slice Test Design accommodates 20 x 20 cm 2 RPCs as well as 30 x 30 cm 2 GEMs Stack is assembled

BILCW07, Feb 2007, H.WeertsSlide 10 Beam telescope, HV, and gas Beam telescope 6 counters (3 x (1 x 1 cm 2 ) + 1 x (4 x 4 cm 2 ) + 2 x (19 x 19 cm 2 ) Mounted on rigid structure Counters in hand! HV modules Need separate supplies for each chamber Modules (from FNAL pool) being tested With additional RC-filter perform similarly to our Bertan unit in analog tests (RABBIT system) Digital tests satisfactory too Gas system Need manifold for 10 chambers (in hand!) Need approval for gas tanks (safety issue)

BILCW07, Feb 2007, H.WeertsSlide 11 Electronic Readout System for Prototype Section 40 layers à 1 m 2 → 400,000 readout channels I Front-end ASIC II Pad and FE-board III Data concentrator IV Super Concentrator V VME data collection VI Trigger and timing system More than all of DØ in Run I; ATLAS tilecal HCAL is 10,000 channels; ATLAS ECAL 200,000 Some recent changes concerning role of data collector and timing/trigger module Suitable for both RPCs and GEMs

BILCW07, Feb 2007, H.WeertsSlide 12 DCAL chip Design → chip specified by Argonne → designed by Fermilab 1 st version → extensively tested with computer controlled interface → all functions performed as expected Redesign → decrease of gain by factor 20 (GEMs) and 100 (RPCs) → decoupling of clocks (readout and front-end) 2 nd version → submitted on July 22 nd → 40 chips (packaged) in hand Test board → redesign of test board (changes in pin layout etc. complete → boards fabricted → chip mounted on tes board Testing (2/40) →all software written → tets ongoing Reads 64 pads Has 1 adjustable threshold Provides Hit pattern Time stamp (100 ns) Operates in External trigger or Triggerless mode

BILCW07, Feb 2007, H.WeertsSlide 13 Spread ~20 DAC Cnts (Typically ~10-15 Cnts) DCAL2 Testing I Threshold scans… All channels OK, except Channel #31 shows some anomalies (understood, no problem) Threshold Response Tests Typical Channel (DAC=192, High-Gain) On-board Q-inj, ext. trig., pipeline enabled Noise floor 100% point (100 triggers) 50% point (100 triggers) Slope of transition region Threshold scan

BILCW07, Feb 2007, H.WeertsSlide 14 DCAL2 Testing II Error bars rms of distributions Ratio of high to low gain R h/l = 4.6 ± 0.2 (roughly as expected) Other tests - Sort out small problem with trigger (understood, can be circumvented) - External charge injection (ongoing, first results look good) - Noise floor (tests complete, results OK) For GEMs For RPCs Chip can be used for vertical slice test Small modifications still necessary for production

BILCW07, Feb 2007, H.WeertsSlide 15 Split old ‘Front-end board’ ‘front-end board’ highly complex and difficult blind and buried vias + large board => (almost) impossible to manufacture split into two boards to eliminate buried vias Pad boards four-layer board containing pads and transfer lines can be sized as big as necessary relatively cheap and simple vias will be filled Front-end boards eight-layer board 16 x 16 cm 2 contain transfer lines, houses DCAL chip expensive and tough to design Connections board to board with conductive glue on each pad (being tested) cables for connection to data concentrators New Concept FE board Pad board Pad- and Front-end Boards I

BILCW07, Feb 2007, H.WeertsSlide 16 4-layer Pad-board 8-layer FE-board, 16x16 cm 2 All (almost) layers shown Pad- and Front-end Boards II Design completed → submitted Any size, multiple of 16x16 cm 2 More complicated than anticipated

BILCW07, Feb 2007, H.WeertsSlide 17 Data concentrator boards Functionality defined Protocol to data collector defined Timing and trigger module Functionality (almost) defined Being designed by Argonne G Drake (ANL) Design almost completed

BILCW07, Feb 2007, H.WeertsSlide 18 E Hazen (Boston) Fabrication of prototype this month Functionality All data received as packets Timestamp (24 bits) + Address (16 bits) + Hit pattern (64 bits) Packets grouped in buffers by matching timestamps Makes buffers available for VME transfer Monitors registers (scalars) Slow control of front-end Allows read/write to DCAL chips or data concentrator boards New Design Effort Data collector boards Boston Univ

BILCW07, Feb 2007, H.WeertsSlide 19 DAQ software Particular challenge to be compatible with CALICE software CRC boards SBS620 VME-PCI bridge Driver for SBS620 Hardware Access Library (HAL) Bus Adapter Board specific read/write classes CALICE DAQ program Data collectors some VME-PCI bridge CALICE test beam DAQ Slice test/PS Driver for the bridge Data collector read/write classes Will be compatible with current CALICE test beam DAQ Use CALICE DAQ as much as possible to minimize the effort –Basically just need to supply some hardware specific I/O classes Currently focus on slice test, but will be used for 1m 3 PS as well Data format will follow existing CALICE convention

BILCW07, Feb 2007, H.WeertsSlide 20 Responsibilities and collaborators TaskResponsible institutes RPC constructionArgonne, IHEP Protvino Mechanical structure (slice test)Argonne Mechanical structure (prototype section) DESY Overall electronic designArgonne ASIC design and testingFNAL, Argonne Front-end board designArgonne Data concentrator designArgonne Data collector designBoston Timing and trigger module designArgonne DAQ SoftwareArgonne HV and gas systemIowa Beam telescopeUTA

BILCW07, Feb 2007, H.WeertsSlide 21 1 m 3 Prototype Section FUTURE

BILCW07, Feb 2007, H.WeertsSlide 22 Costs and Funding Stack ItemCostContingencyTotal RPC stack M&S607,200194,600801,800 Labor243,07599,625342,700 Total 850,275294,2251,144,500 GEM stack * M&S400,000165,000565,000 Labor280,46040,700321,160 Total 680,460205,700886,160 Both stacks M&S1007,200359, ,800 Labor523,535140,325663,860 Total 1,530,735499,9252,030,660 A) Slice test is funded by LCDRD06, LDRD06 and ANL-HEP, and Fermilab B) Prototype section not yet funded, but… Proposal for supplemental funds for $500k/year over two years submitted to DOE Help from ANL (LDRD), ANL-HEP, FNAL expected… * Reusing most of the RPC electronics

BILCW07, Feb 2007, H.WeertsSlide 23 Conclusions - Vertical slice test Funded (more or less) Concentrated effort with monthly meetings Goal: tests at MTBF in Spring Prototype section Expensive! Funding appears possible Goal: RPC stack in 2008 Finally gaining momentum!!!