06.10.06EPPOG - LHC Machine LHC machine (and some outreach) Mike Lamont.

Slides:



Advertisements
Similar presentations
LHC Machine Protection
Advertisements

19th – 20th of September 2007Cryogenic Expert Meeting at GSI, Jan Patrick Meier1/11 Cryogenic Experts Meeting at GSI, 2007 The SIS 100 Cryogenic Jumper.
1 Commissioning ABT Equipment in the LHC Jan Uythoven ABT TCM 13/01/2015.
February 2009 Summary of Chamonix 09 Steve Myers.
Injection test? Mike Lamont For initial discussion.
Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005.
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
LHC status and commissioning plans Gianluigi Arduini, CERN, AB/ABP 10 th September 2007 Acknowledgements: R. Bailey, M. Lamont.
Prospects of SC Quadrupole Production at IHEP-Protvino The 2nd Institutes Meeting on International Construction of the FAIR Accelerator Complex Protvino,
LHC status and commissioning plans. LHC in 4 slides Lest we forget Progress to date Present schedules Consequent plan for 2008.
LTC Extended days, 03 March’08 J.M. Jimenez, AT Vacuum Group LHC Vacuum commissioning J.M. Jimenez On behalf of AT-VAC.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
1 LBDS Testing Before Operation Jan Uythoven (AB/BT) Based on the work of many people in the KSL, EC and TL sections.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
LHC status & 2009/2010 operations Mike Lamont. Contents Consolidation – brief recall Splices Operational energies Potential performance Present status.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
LHC Insertions Upgrade Working Group (LIUWG) Space available in tunnel Y. Muttoni.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
PostMortem Workshop January LHC “Post Mortem” Workshop: Introduction Initiative by Robin Lauckner, Adriaan Rijllart and myself, helped by many other.
LHC Sector Test 1 Roger Bailey, Helmut Burkhardt, Paul Collier, Brennan Goddard, Stephen Jackson, Lars Jensen, Rhodri Jones, Verena Kain, Alex.
LHC Machine Checkout & Dry Runs Strategy Acknowledgements: R.Alemany, R.Giachino M. Albert LHC Beam Operation Workshop June 2014.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
Power Converters and DC cablesSlide 1/.. LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005 Water cooled cables warm bus bars power converter.
Running scenario 2009/10 Run through components – and then synthesis.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
1 Sector Test – Preparation Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
4 December 2007Sylvain Weisz - LEMIC1 Status of LHC installation.
LHC sector test - summary 1 14/03/2008 Possible injection into part of the machine Options etc.Mike Lamont Stopping the beamStefano Redaelli Proposed Tests.
LHC Machine Status Report Mike Lamont for the LHC team Acknowledgements: Mirko Pojer, Matteo Solfaroli, Katy Foraz et al.
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
Quality Assurance Overview Ranko Ostojic 12 Nov 2012.
HL-LHC 11 T Dipole for DS Collimation 8 th to10 th December, 2014 D. Duarte Ramos, C. Mucher, L. Gentini, T. Sahner, H. Prin, R. Wawrowski, F. Savary,
AT-VAC SPC Nicolaas KOS Beam Screens for Inner Triplet Magnets LHC Upgrade Phase 1 Nicolaas KOS  LHC Upgrade phase 1  Inner triplet BS Requirements.
AEM, Sept Frank Chlebana (Fermilab) Status of the LHC and CMS Frank Chlebana (Fermilab) All Experimenter’s Meeting Sept
Preparation for Circulating Beam - Part II Collimators (40') Oliver Aberle o Breakdown of tests foreseen in preparation for beam o Equipment folder: tests.
LHC Commissioning Status Gianluigi Arduini CERN – AB Department For… 23/10/20081LHC Commissioning Status - G. Arduini.
R. van Weelderen Overview of the LHC cryogenic system.
The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar ( )
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
HL-LHC IT STRING and Series test of SC link
LHC Commissioning with Beam
Minimum Hardware Commissioning – Disclaimer
Status of LHC installation & New Installation Schedule
LHC schedule.
Feasibility and implication of installation of the string test in SM18 with a slope M. Bajko WP16.
Challenges of vacuum chambers with adjustable gap for SC undulators
LHC First Physics James Gillies, CERN 30 October 2009.
The LHC - Status Is COLD Is almost fully commissioned
Long Shutdown for the LHC: Vacuum Beam Pipes
Powering the LHC Magnets
Friday 30th September 06:00 Operator dump fill #2171, int. lumi about 75 pb-1 Previous operator dump from physics was on 14 September ! 07:00 Start of.
Powering from short circuit tests up to nominal
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
Scrubbing progress - 10/12/2012
Machine plans - CMS startup workshop
LHC status & 2009/2010 operations
LHC installation status
Brief report of the hardware commissioning activities
LHC - Week 38 Technical stop: Katy Foraz
Cryogenic management of the LHC Run 2 dynamic heat loads
Presentation transcript:

EPPOG - LHC Machine LHC machine (and some outreach) Mike Lamont

EPPOG - LHC Machine LHC - sectors

EPPOG - LHC Machine3 Magnets 5 September, the 1000th cryo-magnet was installed in the LHC tunnel in the arc between point 3 and point out of 1746 (1232 dipoles) Last one due in in March 2007

EPPOG - LHC Machine4 Interconnects Vacuum, bellows, RF contacts plus leak checksVacuum, bellows, RF contacts plus leak checks Cryogenics, thermal shield, heat exchangerCryogenics, thermal shield, heat exchanger Bus barsBus bars superconducting splices x 10,000 (induction welding) Corrector circuitCorrector circuit splices x 50,000 (ultrasonic welding) Joining everything up – 1700 times Huge, painstaking & industrialised Clearly on the critical path

EPPOG - LHC Machine5 DFBs Responsible for feeding the room temperature cables into the cold mass. DFBA - arcs DFBM - quads DFBL - links DFBX – triplets 52 total

EPPOG - LHC Machine6 Long Straight Sections

EPPOG - LHC Machine7 LSS.L8 (Injection septa)

EPPOG - LHC Machine8 XMAS 2007 NOW

EPPOG - LHC Machine is the year Installation & HWC:Installation & HWC: Huge amount to do. Potential milestones include:Potential milestones include: Cool down of first sector (7-8)Cool down of first sector (7-8) Installation of the 1232th dipole.Installation of the 1232th dipole. Installation of the last cryo-magnet (1746th)Installation of the last cryo-magnet (1746th) Powering of the first sector to nominal current (7-8)Powering of the first sector to nominal current (7-8) Completion of interconnect work - continuous vacuum.Completion of interconnect work - continuous vacuum.

EPPOG - LHC Machine10 End 2007 Calibration run (Collisions at 450GeV + ramp commissioning etc.) Dec Beam Commissioning at 450 GeV 16 days beam time estimated Machine Checkout (Access, Vacuum, Equipment Tests, Controls, Cycle (partial), Beam dump, Interlocks and INB)Nov Operations testing Oct 450 GeV HWC 450 GeV HWC ACCESS TESTS Sectors 5-6, 6-7, 1-2 & 2-3: - reduced commissioning of main circuits to 1.1 TeV

EPPOG - LHC Machine11 Calibration Run 2007 Closure of the ring for access testsClosure of the ring for access tests The hand over the machine to operations for full machine check-out, LHC prepares for beam.The hand over the machine to operations for full machine check-out, LHC prepares for beam. First beam into the machineFirst beam into the machine First circulating beamFirst circulating beam First collisions at 450 GeV.First collisions at 450 GeV. Machine development could see single beam taken up the ramp to around 1.1 TeV - new world recordMachine development could see single beam taken up the ramp to around 1.1 TeV - new world record ContingencyContingency If the challenging LHC installation schedule cannot be met in fully in 2007 then a sector test which will inject beam down TI8 and into sector 7-8 is a possibility (probably Q3 2007).

EPPOG - LHC Machine12 Who knows…

EPPOG - LHC Machine Should look something like… Hardware commissioning to 7 TeV Machine Checkout  1 month Commissioning with beam  2 months Pilot Physics  1 month Provisional MAJOR NEWS OF COURSE

EPPOG - LHC Machine14 Web

EPPOG - LHC Machine15 Interactions.org

EPPOG - LHC Machine16 Seen as an outreach conduit

EPPOG - LHC Machine17 Public Relations Lots of showing people aroundLots of showing people around TV, press, VIPs etc. etc. Usual destinationsUsual destinations SM18 CCC IP8 – near, interesting, and advanced. This usually, but not always, on request of the press office “Do you have a young, female Albanian expert on the LHC?”

EPPOG - LHC Machine18 CCC Unofficial viewing gallery upstairs (out of working hours or book it) Two big posters! Little museum has gone – no room This is cool

EPPOG - LHC Machine19 Masterclass participation c/o Michael Kobel Question: as the CMS /LHC was switched on, did you realize the sudden difference it made on the earths slight differential in its rotational and tilting effect but very slight? Ask an expert The vacuum in the LHC is comparable to outer space, if it were a car tyre with a leak, there are so few gas molecules that it would take years to go flat. FAQ

EPPOG - LHC Machine20 Conclusion Major headlines expected over the next 2 – 3 yearsMajor headlines expected over the next 2 – 3 years Coordination DSU-CO Little proactive outreachLittle proactive outreach We’re busy We rely on DSU-CO Reactive outreach supportReactive outreach support Visits, experts, video link-ups, web, FAQ, interviews etc. Going to be very little to see on the surface soonGoing to be very little to see on the surface soon Tunnel (special visitors) CCC is cool – some improvement possible