Harry Carter – LCFOA Meeting 5/1/06 1 LCFOA Technical Briefings: Cryomodules H. Carter Fermilab Technical Division.

Slides:



Advertisements
Similar presentations
Interface of Plug-Compatible Cryomodule Components KEK Norihito Ohuchi 2008/3/41GDE-Sendai Meeting.
Advertisements

SRF Cryomodule Assembly Facility Plans Tug Arkan AAC, May 10-12, 2005.
1 Collaboration%20Meetings/SMTF%20Collaboration%20Meeting.
RF Unit Test Facility at NML & CM1 Test Plan Bob Kephart Fermilab IWLC-10 October 20, 2010.
An SRF Single Cavity Horizontal Test Facility Tom Peterson, Fermilab May 10, 2005.
US Cavities Status and Plan Mark Champion 01 October 2009.
Cavity Integration summary H. Hayano April 25, 2008 ILC-SCRF
ILC-BCD: Cavity Package International Linear Collider - Baseline Configuration Document: Cavity Package DESY -MPY-
Overview of the ILC and SRF Program (With an emphasis on Px) Shekhar Mishra ILC & SRF Program Fermilab.
R&D Status and Plan on The Cryostat N. Ohuchi, K. Tsuchiya, A. Terashima, H. Hisamatsu, M. Masuzawa, T. Okamura, H. Hayano 1.STF-Cryostat Design 2.Construction.
F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.
ILC R&D at Fermilab Robert Kephart. ILC Americas f Fermilab May 15-18, 2006FY06 DOE Annual Review2 Outline Fermilab ILC Goals Fermilab’s role in the GDE.
Nick Walker, Brian Foster LAL, Orsay WP2: Coordination with the GDE.
Plans for Future SRF Infrastructure Shekhar Mishra ILC Program Fermilab.
Summary of Main Linac SCRF-part H. Hayano, ILC08 at UIC.
Detail discussion of S1 Global at STF H. Hayano (KEK) GDE Mar 3-6, 2008.
STF plan overview H. Hayano, KEK LCPAC 02/25/2005.
Type IV Cryomodule Proposal (T4CM) Don Mitchell, 16 JAN 2006.
Cryomodule Design and R&D during the EDR phase Robert Kephart With input from the T4 CM Collaboration.
STF status Mar.22,2005 H. Hayano, KEK. STF Phase 1 Test Accelerator DC gun : 200kV CsTe photocathode for quick start UV(262nm) Laser (337ns spacing, 2820bunches)
ILCTA_IB1_VTS An in-ground vertical test facility for ILC SRF cavities at Fermilab Camille M. Ginsburg ILC SRF Technical Status Meeting 5.May 2006 for.
F February 27, 2006 Fermilab Budget Briefing 1 Fermilab Budget Overview International Linear Collider FY05 - FY08 Bob Kephart February 27, 2006.
D.Proch, DESY; GDE meeting Vancouver 06 Technical systems: Cavity Report Overview on costing activities for ILC –European costing method Overview industrial.
ILC/SRF R&D Robert Kephart. 9/25/2007 R.D. Kephart DOE Annual Review 2 Outline Fermilab ILC Goals Fermilab’s role in the GDE & the ILC machine design.
E. KAKO (KEK) 2010' Feb. 05 STF Meeting for S1-G Global Design Effort 1 Preparation Status at KEK for S1-Global Eiji Kako (KEK, Japan)
Harry Carter – T4CM Meeting 7/13-14/2006 Type IV Cryomodule (T4CM) Design Meeting #2 H. Carter Fermilab Technical Division.
Cryomodule Development at Fermilab Don Mitchell Representing the SRF engineering community at Fermilab April 20, 2009 Tsukuba, Japan TILC09.
Americas Main Linac Cavity and Cryomodule WBS X.9 Resource Proposal Shekhar Mishra (Hasan Padamsee, John Mammosser, Mike Kelly) For the WBS 9 Collaboration.
Parallel session summary ML/SCRF L. Lilje, H. Hayano, N. Ohuchi, S. Fukuda, C. Adolphsen (with help of Chris Nantista) TILC09,
Americas Region: T4CM Status and Plans H. Carter TD SRF Dev. Dept. July 14, 2006.
Status of U.S. Cavity & Cryomodule Industrialization Bob Kephart LCWS10/GDE Beijing, March, 2010.
R&D Expected in Cooperation with Vendors ILC Baseline Assessment Workshop Mark Champion September 09, 2010.
Americas Main Linac Cavity and Cryomodule WBS X.9 Resource Proposal.
SRF Processing at ANL: Progress and Plans ANL: Mike Kelly, Scott Gerbick FNAL: Dan Olis, Allan Rowe Speaker: Mike Kelly November 17, 2008.
Global design effort DOE meeting 8/10/06 Global design effort Americas 1 FY07 DOE ILC Budget recommendations G. Dugan ILC-GDE/Cornell University GDE Americas.
Meeting of the European Global Design Effort Report from INFN non EU-funded R&D Carlo Pagani University of Milano and INFN DESY, 10 May 2006.
Date 2007/Oct./25 FNAL-GDE-Meeting Global Design Effort 1 Cryomodule Report N. Ohuchi KEK 1.Cryomodule & Cryogenics KOM 2.GDE-meeting discussion I.Interface.
Summary ( Cryomodule, Plug-compatible Interface) Norihito Ohuchi.
A Satellite Meeting at IPAC-2010 SCRF Cavity Technology and Industrialization Date : May 23, 2010, a full-day meeting, prior to IPAC-2010 Place: Int. Conf.
Harry Carter – T4CM meeting CERN 1/16/06 Type IV Cryomodule (T4CM) Design Team Formation & Technical Discussions H. Carter CERN – 1/16-17/2006.
ILC Americas Cavity and Cryomodule R&D Shekhar Mishra ILC Program Fermilab Talk presented at DOE Annual Program Review Breakout Sessions – Wednesday, May.
E. KAKO (KEK) 2009' Oct. 26 ILC KEK Global Design Effort 1 Cavity Preparation for S1-Global Eiji Kako (KEK, Japan)
Medium Beta Cavities Paolo Michelato, Paolo Pierini, and Carlo Pagani INFN Milano - LASA.
Medium beta cavities Paolo Michelato, Paolo Pierini, Carlo Pagani INFN Milano - LASA.
Industrial Participation & SRF Infrastructure at Fermilab Phil Pfund with input from Harry Carter, Rich Stanek, Mike Foley, Dan Olis, and others.
30 May 2007 DESY Cryomodule Discussion 1 Type 4 Cryomodule Technical Discussion Tom Peterson Compiled from various previous meeting notes and many sources.
Proton Driver Resources & Schedule (R&D Plan) Rich Stanek May 10, 2005.
Carlo Pagani University of Milano INFN Milano-LASA & GDE ILC and XFEL Cryomodules Preliminary thoughts for convergence ILC EDR Kick-off Meeting DESY,
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
Detail plan of S1-Global H. Hayano (KEK),
S1-Global status report KEK Norihito Ohuchi 2008/11/171ILC08-GDE-Meeting-Chicago.
ILC Cryomodule Industrialization in the U.S. R. Kephart (+ H Padamsee )
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
A Proposal for FJPPL (TYL) Development of Frequency Tuners Optimization and Cryomodule Integration for 1.3 GHz SRF Cavities G. Devanz, F. Nunio, O. Napoly.
SRF Collaboration Shekhar Mishra Fermilab. Overview Charge: Does the laboratory make effective use of collaboration and existing SRF capabilities at other.
Start of S2 Milestone Work H. Padamsee. Intro At KEK S2 meeting we decided to make a list of milestones and eventually cost S2 activities I tried to start.
Thomas Jefferson National Accelerator Facility Operated by the Southeastern Universities Research Association for the U.S. Department of Energy Jefferson.
The Evolving ILC Project
Status and plans for the 3.9 GHz section of XFEL
ILC Cryogenics Work Package Status and Plans
ILC R&D Board Meeting: SRF Cavities Status and Plans
Meeting for S1-Global module design Cryomodule and Cryogenics
Evolving an ILC focused SCRF Facility from the XFEL Infrastructure
Chris Adolphsen Sergei Nagaitsev
Main Linac EDR: Cavity & Cryomodule Discussion
ILC Cavity & Cryomodule Overview
Jiyuan Zhai ( IHEP ) TTC Meeting, JLAB, 6 Nov 2012
IHEP Cryomodule Status
Nick Walker (DESY) EU GDE Meeting Oxford
Presentation transcript:

Harry Carter – LCFOA Meeting 5/1/06 1 LCFOA Technical Briefings: Cryomodules H. Carter Fermilab Technical Division

Harry Carter – LCFOA meeting 5/1/06 2 Outline Cryomodules Status Report in the Three Regions Type IV (T4CM) Cryomodule Design An RF Unit for ILCTA at FNAL

Harry Carter – LCFOA meeting 5/1/06 3 CM Status Report: European Region Assembly of Cryomodule #6 at DESY begins today  Type III+ design using cavities qualified at 35MV/m (8?)  Estimated time to complete is six weeks  European industry is involved with this effort as part of industrialization for XFEL pre-production  Assembly of a Type III+ “kit” for ILCTA at FNAL to commence upon completion of Cryomodule #6 Work well underway on a single cryomodule test stand--- scheduled for completion this summer (see next slide) R&D effort continues on EP of fine grain, large grain, and single crystal 1.3GHz niobium cavities

Harry Carter – LCFOA meeting 5/1/06 4 Module Test Stand Lutz Lilje Allows cryogenic tests and RF measurements independent from the LINAC  No beam tests  Dark current measurements will be integrated

Harry Carter – LCFOA meeting 5/1/06 5 European Region: Industrial Studies on Module Assembly (Lutz Lilje) Prepare a study by industry on the cryomodule assembly  Involve industry early  Profit of industrial experience Results of the study will be published Specification of XFEL-Cryomodule Design & Assembly for Industrial Studies

Harry Carter – LCFOA meeting 5/1/06 6 CM Status Report: Asian Region (KEK) Design of two four-cavity cryomodules has been completed (see next slide) Work underway on the STF R&D effort continues on mechanical polish (by tumbling) and EP of fine grain 1.3GHz niobium cavities (low loss design)

Harry Carter – LCFOA meeting 5/1/06 7 KEK Cryomodules N. Ohuchi KEK is constructing two cryomodules of which cross-section designs are based on the TESLA Type III. (STF-Phase-1)  The cavities between the individual cryostats have the different design of gradients of 35 MV/m and 45 MV/m.  Two cryostats are connected with a bellows tube, and the total length is mm.  Four cavities are installed into the individual cryostat.  The designed distance between the input couplers of neighboring two cavities is 1337 mm.

Harry Carter – LCFOA meeting 5/1/06 8 KEK cryomodule status - long term schedule N. Ohuchi The STF phase-1 cryomodule will be completed and tested in 2006, and the running test will be carried out in The STF phase-2 cryomodules are based on the design of the Type-4 cryomodule toward ILC, and the design will start in this year.

Harry Carter – LCFOA meeting 5/1/06 9 ILC Americas Cryomodule Status and Plans: Infrastructure Development Fermilab  ILCTA-MDB Capture Cavity #2 initial testing at 4K completed Preparations underway for 2K operation: vacuum pumping system is installed Horizontal Test System (see next slide)  ILCTA-CAF New clean room installation and commissioning has been completed  ILCTA-NML Building preparation underway Interim cryo system installation is underway (but may fall victim to FY06 funding limitations)

Harry Carter – LCFOA meeting 5/1/06 10 ILC Americas Cryomodule Status and Plans: Infrastructure Development Fermilab  Horizontal Test Cryostat design essentially complete Construction of vessel in progress Planned to be operational by end of summer Designed to accomodate 1.3 and 3.9GHz cavity testing  Vertical Test System Design effort is underway with civil construction planned in FY06 To be installed at TD IB1 Planned to be operational in Spring 2007 Argonne  Joint ANL/FNAL BCP Facility Installation 95% complete Safety review of ANL side underway Safety review of FNAL side will follow successful completion of ANL review  Joint ANL/FNAL EP Effort is under discussion Emphasis to be on creating a prototype system design for industrialization

Harry Carter – LCFOA meeting 5/1/06 11 ILC Americas Cryomodule Status and Plans: Cryomodules CM1  Type III+ design  To be assembled from a Kit supplied by DESY  Completion date by March 2007 CM2  Type III+ design  To be assembled from cavities procured by FNAL and processed by Cornell and JLab. Coldmass to be supplied by INFN (from Zanon) CM3  Type IV (T4CM) design effort has begun  3-D preliminary model already created  T4CM design features will be described in the next few slides

Harry Carter – LCFOA meeting 5/1/06 12 Schedule for Cryomodules at FNAL 1 st Qtr st T3CM from DESY kit 3.9GHz CM for DESY TTF nd Qtr3 rd Qtr4 th Qtr1 st Qtr2 nd Qtr3 rd Qtr4 th Qtr st Qtr 2 nd T3CM from FNAL components

Harry Carter – LCFOA meeting 5/1/06 13 Type IV (T4CM) Cryomodule Don Mitchell Presented a Conceptual T4CM 3-D Model at the CERN cryomodule meeting in January of this year

Harry Carter – LCFOA meeting 5/1/06 14 T4CM Features: The main features that distinguish the T4CM from the Type III+ CM are:  Closer cavity-to-cavity spacing due to decreased cavity overall length and a reduction in the space in the interconnecting region  Quadrupole/corrector/BPM package located in the center of the cryomodule rather than the end  Use of coaxial (blade) tuner rather than a lever-style tuner The T4CM design effort is an international effort

Harry Carter – LCFOA meeting 5/1/06 15 T4CM Proposed Cavity w/ Bladetuner from D. Mitchell presentation

Harry Carter – LCFOA meeting 5/1/06 16 T4CM Cavity Dimensions

Harry Carter – LCFOA meeting 5/1/ D Parametric Model well advanced Starting from “original” INFN CRY3 AutoCAD DWGs used for all modules fabrication Rebuilding a CRY3 with “symmetric” quasi TESLA TDR string (8) Using Unigraphics NX3 8 cavities per cryomodule Verified construction drawings from the 3D model CRY3 fabrication experience included QA/QC implemented from ZANON construction from C. Pagani’s

Harry Carter – LCFOA meeting 5/1/06 18 Arriving at a T4CM Design (Revised) 1 st Qtr 2006 Define design features Perform engineering analyses Complete drawing packages All Components in house and ready for assembly nd Qtr3 rd Qtr4 th Qtr1 st Qtr2 nd Qtr3 rd Qtr4 th Qtr Procure components st Qtr

Harry Carter – LCFOA meeting 5/1/06 19 RDR: Cryomodule Cost Studies Cost studies are being conducted in all three regions In the ILC Americas Region, two studies are planned  A study at Fermilab has begun---led by Rich Stanek  A study by U.S. industry for an RF unit is in the process of being commissioned

Harry Carter – LCFOA meeting 5/1/06 20 ILC RF unit at Fermilab (at ILCTA-NML) Fermilab is building one RF unit to be tested with Beam

Harry Carter – LCFOA meeting 5/1/06 21 Summary: I have described some of the cryomodule work going on each of the three geographical regions The T4CM design effort is an international effort and is just now beginning in earnest Cryomodule cost studies are being undertaken in all three regions in support of the RDR costing effort Thank you for your attention. Any questions?