ESTIMATING EARTHWORK DR. Nabil Dmaidi.

Slides:



Advertisements
Similar presentations
Excavating and Lifting Part 1
Advertisements

Cross Section and Borrow Pit Methods
REVIEW - EARTH WORK Fall STEPS FOR EARTH WORK COMPUTATION Define Typical Cross Section Apply Typical Cross Section: Every Station Station at pluses.
CTC-275 Construction Methods
Earthwork Operations & Equipments
3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine.
Lecture 4 Excavating and Lifting
Chapter 3 Measuring Excavation and Sitework
Measuring Sitework, Excavation, and Piling
Earthmoving Materials and Operations
Earthwork QTO Stage 1 Preconstruction Stage 2: Procurement
Wes Marshall, P.E. University of Connecticut March 2007
ESTIMATING EARTHWORK Prof Awad S. Hanna.
ERT252/4 GEOMATICS ENGINEERING
Lecture 3 Earthmoving Materials
CTC-375 Construction Methods
Earthmoving Materials and Operations
Chapter 13 Site Plan Layout.
ENGINEERING SURVEYING & PHOTOGRAMMETRY CVE 314
Land levelling design methods - plane method
Contour and Topo map Applications Profile View (Longitudinal Sections): Roads, Canals, Pipes,… Cross-Sectional View, Roads, Canals, Pipes, Building,…
Profile elevations Sometimes the profile is too steep to illustrate on our profile sheet so we have to break the profile. This partial profile illustrates.
Estimating Waste Week 3 CTC-415. What is waste Waste is material that needs to be supplied but may not be used All material items except steel beams and.
Cross Sections CTC 440. Objectives Know what a cross section is and what is typically shown Know how to calculate areas and volumes Know how to use the.
Estimating Site work. Major Components Erosion & Sediment Control Fencing Clearing and grubbing Excavation Backfill Grading Trucking.
CE 453 Lesson 24 Earthwork and Mass Diagrams
Estimating Ahmed Elyamany, PhD, AVS. EARTHWORK AND EXCAVATION bank  Earth that is to be excavated is called bank measure. loose  Earth that is to be.
It’s more than adding and subtracting..  Before bidding, the site should be examined for the following:  Distance from the office  Site conditions.
CONSTRUCTING A FIVE CABIN LATRINE
Lecture 6 Loading and Hauling
Areas and Volumes Introduction Faculty of Applied Engineering and Urban Planning Civil Engineering Department 2 nd Semester 2008/2009 Surveying.
Compaction and Stabilization Equipment
Wes Marshall, P.E. University of Connecticut March 2007
Residential Construction Unit 2- Site Work and Concrete Mr. Todzia.
Lecture 2 Introduction to Earthmoving
Planning for Earthwork Construction
SHOVELS.
Team Assignments C D A B Clayten Greenwell Ryan Franklin Elliot Magoto
Earthwork & Volumes Spec Requirements End Areas End-area Volumes
Soil and Rock Soil and rock are the principle components of many construction projects. Knowledge of their properties, characteristics, and behavior is.
Soil And Rock General Soil Characteristics Trafficability – ability of soil to support weight of vehicles under repeated traffic –Controls traffic on unimproved.
By: Maddison Black.  Cement: binding material that, when combined with water and aggregate, forms concrete  Concrete: building material formed by combining.
How much concrete? We have a blueprint of the proposed dam, how much concrete will it take to build it?
Resource Leveling Advantages/Applications of Resource Leveling 1. Maintain the lowest uniform number of employees to perform the work. 2. Establishing.
© Awad S. Hanna, PhD, P.E.1 Estimating and Scheduling CEE 492 Lecture 5 ESTIMATING EARTHWORK.
Retaining Wall Construction Building A Block Retaining Wall Developed by: Dr. Teri Hamlin Georgia Department of Education.
Riprap Installation Construction Inspection for Field Office Activities Will use Riprap Gradation and Riprap Subgrade Problems from Class Problem Section.
DR. Nabil Dmaidi F ACTORS THAT D ETERMINE V ARIATION IN E STIMATES.
Interpreting a contour map
EXAMPLE A 400 m2 (40 x 10 m) area is to be excavated, 1 m deep, with side slopes 2:1. As the width (10 m) is less than 30 times the depth (30 x 1 m), the.
Drainage and Grading Creating stable ground surfaces
Site Grading Site Grading Civil Engineering and Architecture
Site Grading of Terrace
Calculating Cut and Fill
Site plan The plat map A plat map is the first step in development of a site plan. It delineates property lines with bearings, dimensions, streets, and.
CONSTRUCTION METHODS & TECHNOLOGY
Concrete Structures DR. Nabil Dmaidi.
Lecture 7 Excavators TSP-308 MPK Ferdinand Fassa.
FBE05 – Mathematics and Statistics
Lecture 5 Dozer TSP-308 MPK Ferdinand Fassa.
Introduction Persons engaged in surveying are often called to determine volumes of various types of material. The most common unit of volume is cubic having.
ADVANCE SURVEYING.
Introduction Persons engaged in surveying are often called to determine volumes of various types of material. The most common unit of volume is cubic having.
Section II Applications of Measurements
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Introduction Persons engaged in surveying are often called to determine volumes of various types of material. The most common unit of volume is cubic having.
Introduction Persons engaged in surveying are often called to determine volumes of various types of material. The most common unit of volume is cubic having.
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Chapter 6 Construction Quantity Measurement
Presentation transcript:

ESTIMATING EARTHWORK DR. Nabil Dmaidi

Estimating Earthwork Earthwork includes: 1. Excavation 2. Grading: Moving earth to change elevation 3. Temporary shoring 4. Back fill or fill: Adding earth to raise grade 5. Compaction: Increasing density 6. Disposal DR. Nabil Dmaidi

Productivity Factors A. Job conditions Material type Water level and moisture content Job size Length of haul Haul road condition (accessibility and load restrictions) DR. Nabil Dmaidi

Productivity Factors (cont.) B. Management conditions Equipment conditions and maintenance practices Skills of work force and management Planning, supervision and coordination of work. DR. Nabil Dmaidi

Job Efficiency Factors for Earthmoving Operations DR. Nabil Dmaidi 7

Units of Measure Cubic Yard (bank, loose, or compacted) DR. Nabil Dmaidi

1.0 CUBIC YARD IN NATURAL CONDITION (IN-PLACE YARD) 1.25 0.90 1.0 CUBIC YARD IN NATURAL CONDITION (IN-PLACE YARD) 1.25 CUBIC YARD AFTER DIGGING (LOOSE YARDS) 0.90 CUBIC YARD AFTER COMPACTED (COMPACTED YARDS) In place Compacted Loose DR. Nabil Dmaidi 6

Volume Bank: VB Loose: Vl Compacted: Vc Bank cubic yards (BCY) Density B Lb /BCY Loose: Vl Loose cubic yards (LCY) Density L Lb/LCY Compacted: Vc Compacted cubic yards (CCY) Density C LB/CCY DR. Nabil Dmaidi

Bank Volume = Loose volume x Load factor Swell: A soil increase in volume when it is excavated. Swell (%) = ( - 1) x 100 Load factor = Bank Volume = Loose volume x Load factor Bank density Loose density Loose density Bank density DR. Nabil Dmaidi

A soil decreases in volume when it is compacted Shrinkage: A soil decreases in volume when it is compacted Shrinkage (%) = (1 - ) x 100 Shrinkage factor = 1 - Shrinkage Compacted volume = Bank volume x Shrinkage factor Bank density Compacted density DR. Nabil Dmaidi

Approximate Material Characteristics Exact values will vary with grain size, moisture content, compaction, etc. Test to determine exact values for specific soils. DR. Nabil Dmaidi

Typical Soil Volume Conversion Factors DR. Nabil Dmaidi

Estimating Earth work for Trenches and Foundations Angle of Repose 2’-0” or more DR. Nabil Dmaidi

Approximate Angle of Repose For Sloping Sides of Excavation Original Ground Line Solid Rock, Slate or Cemented Sand and Gravel (90 Deg.) Compacted Angular Gravels 1/2:1 (63 Deg.) Recommended Slope for Average Soils 1:1 (45 Deg.) Compacted Sharp Sand 1 1/2 :1 (33 Deg.) Well Rounded Loose Sand 2:1 (26 Deg.) DR. Nabil Dmaidi

Calculating Earthwork Quantities 1. End Area Method 2. Contour Line/ Grid Method DR. Nabil Dmaidi

1. End Area Method Used in sites where length is much greater than width DR. Nabil Dmaidi

CALCULATING EARTHWORK QUANTITIES 1. End Area Method a. Take cross-sections at regular intervals, typically, 100’ intervals. b. Calculate the cross-section end areas c. The volume of earthwork between sections is obtained by taking the average of the end areas at each station in square feet multiplied by the distance between sections in feet and dividing by 27 to obtain the volume in cubic yards. DR. Nabil Dmaidi

Project Site Showing 100 Stations Fill Cut 80 82 84 86 88 78 A’ B’ C’ D’ E’ F’ A B C D E F 100' 500' 300' DR. Nabil Dmaidi 2

Project Cross Sections 80 78 76 82 84 86 88 90 78.5 80.3 82.3 84.2 86.2 88.2 Sec. A’- A Sec. B’- B Sec. C’- C Sec. D’- D Sec. E’- E Project Cross Sections Sec. F’- F DR. Nabil Dmaidi 3

Cross-Section @ A’- A Section A’- A 80 79 78 77 76 79.5 78.5 76.7 Area = = 173.7 193 x 1.8 2 Area = = 53.5 107 x 1.0 DR. Nabil Dmaidi 4

Cross-Section @ B’- B Section B’- B 82 81.8 90 x 1.5 Area = = 67.5 2 80.3 80 79 210 x 1.8 76.7 Area = = 189.0 2 78 Section B’- B DR. Nabil Dmaidi 5

Table 1. Cumulative Earthwork Quantities DR. Nabil Dmaidi

2. Contour Line/ Grid Method Used for parking lots and site “leveling” Grid size from 10’x10’ to 50’x50’ the greater the terrain variance the smaller the grid DR. Nabil Dmaidi

2. CONTOUR LINE/GRID CELL METHOD(cont.) Step l Determine by visual study of the site drawing if the net total will be an import (more fill required than cut) an export (less fill required than cut) or a blend (cut and fill about equal) Step 2 Determine the pattern of calculation points or grid size. Step 3 Determine elevations at each calculation location, the corners of each grid. Step 4 Calculate the cubic yards of cut or fill required in each grid cell. Step 5 Add the individual Grid Cell quantities together to arrive at the total cut, total fill volume and the import or volume export yardage required for the job. DR. Nabil Dmaidi

No Scale A B C D E F G H J K L M N O P Q R S 88’ 89’ 90’ 91’ 92’ 93’ 87.6 88.6 89.4 90.4 91.6 93.2 G H J K L M 87.4 88.2 89.5 90.6 92.7 N O P Q R S 87.2 87.7 89.0 91.3 92.0 88.5 89.3 90.3 91.5 95.0 94.3 93.5 93.1 300’ 88’ 89’ 90’ 91’ 92’ 93’ 94’ No Scale Notes: 1. Bring the entire site to elevation 90. 2. All grids are 50’x 50’ = 2500 sq. ft. 3. Present contours DR. Nabil Dmaidi 9

Grade the entire site to grade 90’ Purpose Grade the entire site to grade 90’ Quick and Dirty Assume one grid Existing 90.50 Proposed 90.00 Cut 0.50 Total Cost = = 833CY 90' Need Fill Need Cut 150' 300' 90' 91' 90.5' 150 x 300 x 0.50 27 DR. Nabil Dmaidi

If we choose the grid size to be 50’x50’ Average elevation = = 88.08 change= 90-88.08 = 1.92 cut = = 177.77 CY and so on. 88.6 87.6 87.6+88.5+87.6+88.6 4 87.6 87.6 DR. Nabil Dmaidi