Presentation is loading. Please wait.

Presentation is loading. Please wait.

CTC-375 Construction Methods

Similar presentations


Presentation on theme: "CTC-375 Construction Methods"— Presentation transcript:

1 CTC-375 Construction Methods
Earthwork

2 Get SUNYIT email account

3 Construction Order There is an order to all projects
What activities get done first What activities need to be done in a specific order What activities can be done at any point in time

4 Start at beginning Earthwork
Moving rock or soil from one location to another Processing it to meet location, elevation, density moisture content, etc Efficient earthwork requires: accurate estimating of work quantities and conditions, proper equipment, competent job mangement

5 Equip Selection Proper equipment has major impact on efficiency and profitablility Can equipment perform required work Also look at profitablility, other uses for equipment, return on investment, availability of parts and services, effect of downtime on other construction equip

6 Equipment planning Need to plan to effectively use equipment
Production of equipment Production = Volume per cycle/cycles per hour Cycles per hour is based on efficiency of equip Swing angle and elevation to truck bed Soil hardness and Soil type Room to manuever

7 Equipment planning Cost per production unit = equip cost per working hour/equip production per hour Table 2-1 show efficiencies

8 Soil And Rock General Soil Characteristics
Trafficability – ability of soil to support weight of vehicles under repeated traffic Controls traffic on unimproved access roads Also gives measure of how earthmoving equip will operate Primarily function of moisture conditions and soil type Loadability – how difficult to excavate and haul a soil Granular – high Compact cohesive - low

9 Soil And Rock Unit Soil Weight Pounds /cy
Depends on soil type, moisture content, degree of compaction Relation between soil weight and bearing capacity So soil weight is used as a measure of compaction Soil weight is also a factor in hauling

10 Soil And Rock Moisture Content(%) = (moist wt – dry wt)/dry wt X 100
Soil sample 120# Dry weight 100# MC = ( )/100X100 = 20%

11 Soil ID Boulders Cobbles – over 3” diameter Gravel 1/4” – 3” diameter
Sand 0.7mm (200 sieve) – ¼” diameter Silt – 0.7 mm Clay less than 0.002mm Organic Matter decaying organic matter Soils classified using these types

12 Soil Classification Systems
Unified System All material 3’’+ removed Separates soils into two main groups- Fine grained and coarse grained Table 2-2, Figure 2-1 AASHTO System 7 classes of soil Based on suitability of soil for subgrade Table 2-3 Table 2-4

13 Soil Volume Change Characteristics
Soil Conditions Bank – material in natural state before disturbance – Bank cubic yard Loose – material that has been excavated or loaded loose cubic yard Compacted – material after compaction compacted cubic yard

14 Soil Volume Change Characteristics
Swell Soil increases in volume when it is excavated Soil grains are loosened and air fills voids So 1 unit of soil in bank is smaller than the soil once it is excavated Swell(%) = ((weight/bank vol)/(weight/loose vol)-1)X100 Soil wt = 2800#/cy in bank Soil wt = 2000#/cy loose Swell = ((2800/2000)-1)X100 = 40%

15 Soil Volume Change Characteristics
Shrinkage Soil decreases in volume when it is compacted Air is forced out of soil So 1 unit of soil compacted is smaller than the soil in the bank or once it is excavated Shrinkage(%) = (1-(weight/bank vol)/(weight/compacted vol))X100 Soil wt = 2800#/cy in bank Soil wt = 3500#/cy compacted Swell = (1-(2800/3500))X100 = 20%

16 Soil Volume Change Characteristics
Load and Shrinkage Factors Need a common unit of measure for earthwork (get rid of calculations ) Can use any of the three measures Called pay measure in contract Load factor = 1/(1+swell) Shrinkage factor = 1- shrinkage Table 2-5

17 Spoil Banks Material removed from excavation
Longer than wide – spoil bank – triangular x section Conical – spoil pile To determine the size of the bank or pile need swell and angle of repose for soil Angle of repose = angle that soil on side of bank naturally form Varies with moisture content and type Table 2-6

18 Spoil Banks Spoil bank Vol = X-sect area x length
B = (4V/(L x tan R))^1/2 H = (B x tan R)/2 B – base width H height L length R angle of repose V volume

19 Example You have to store 30,000 BCY of soil in an area no wider than 80 feet How long is the spoil bank? Swell = 25%

20 Spoil Banks Spoil pile Vol = 1/3 p(D/2)^2 X H D = (7.64V/tan R)^1/3
H = D/2 x tan R D – diameter of base H height R angle of repose V volume

21 Estimating earthwork 3 types of excavations Roadways Small pit Trench
Large areas Roadways Find cut and fill using cross sections Mass diagram

22 Estimating earthwork Pit Excavations Area X average depth
Depending on size and ground may break into several geometric shapes to get volume Give bank volume

23 Estimating earthwork Trench Excavations V = x sectional area X length
Take x sections every 50 feet and compute volumes between x sections

24 Estimating earthwork Large Areas Use a grid to find volume


Download ppt "CTC-375 Construction Methods"

Similar presentations


Ads by Google