1 SPAFOA Capitol Hill Briefing December 2013 Harry Weerts International Linear Collider - progress & status SPAFOA meeting, Dec 11, 2013, H.Weerts.

Slides:



Advertisements
Similar presentations
Position of the Czech Republic on the European Strategy in Particle Physics Current main activities in particle physics * Plans for the future Recommendations.
Advertisements

European Strategy for Particle Physics 2013 Preparatory group->Strategy group Individual town meetings Town meeting in Krakow: september 2012 Drafting.
SUPERCONDUCTING PARTICLE ACCELERATOR FORUM OF AMERICA (SPAFOA) Update and Planned 2013 Activities April 3, 2013 MSU FRIB Ken Olsen
Discussion on EUROTeV and ILC Nick Walker (DESY) EUROTeV Kick-off Meeting DESY 1 November 2004.
LCC status Lyn Evans 1April 18, 2015PAC Orsay. ILC in Linear Collider Collaboration 2 ICFA Chair: J Mnich Program Adv. Committee PAC – Chair: N. Holtkamp.
Baseline Configuration - Highlights Barry Barish ILCSC 9-Feb-06.
View from the NSF: Later Years J. Whitmore (EPP-PNA) M. Pripstein (LHC) M. Goldberg, J. Reidy (EPP) LEPP – CLEO CESR Symposium at Cornell, May 31, 2008.
3-March-06ILCSC Technical Highights1 ILC Technical Highlights Superconducting RF Main Linac.
Review of last year: Global Design Effort Barry Barish ILC Consultations URA, Washington DC 12-May-05.
Is there synergy between ILC and SuperB? Steve Playfer University of Edinburgh.
International collaboration in high energy physics experiments  All large high energy physics experiments today are strongly international.  A necessary.
Asian View Point as ACFA Chair and Global View Point as New ILCSC Chair Shin-ichi Kurokawa KEK 2 nd ILC Workshop August 23, 2005 Snowmass, Colorado Shin-ichi.
SCRF ACCELERATOR INDUSTRY STEWARDSHIP OUTLOOK Ken Olsen SPAFOA Fermilab Meeting Nov. 13, 2012.
Status of ILC Barry Barish Caltech / GDE 17-Aug-07.
1 Albrecht Wagner, Snowmass 0805 Albrecht Wagner DESY and Hamburg University Challenges for Realising the ILC.
HEPAP and P5 Report DIET Federation Roundtable JSPS, Washington, DC; April 29, 2015 Andrew J. Lankford HEPAP Chair University of California, Irvine.
LCB/ICFA meeting at Newport News with full snow, February This is only for TB meeting Presentation and not for Distribution. ( )
ACFA Status for ILC M. Nozaki (KEK/ACFA). ACFA and AsiaHEP ACFA (accelerator science) Established in 1996 – Australia – Bangladesh – China – India – Indonesia.
LCC Linear Collider Collaboratio ILC - CFS 12 November 2013 LCWS13 Tokyo University 1 Site-specific CF design from TDR LCWS13, 12 November 2013 Atsushi.
CAPITOL HILL BRIEFING DEC 11, 2013 SUPERCONDUCTING PARTICLE ACCELERATOR FORUM OF AMERICA KENNETH O. OLSEN.
ILC, FCC and the landscape of future colliders 121 April 2015Interactions meeting Toyama.
Progress in Confinement & Heating Increasing laser energy nn Confinement Parameter & Temperature.
Message from ACFA Chair C.Zhang IHEP CCAST ILC Accelerator Workshop and First Asian ILC R&D Seminar under JSPS Core University November 5, 2007.
Round-table: Discussion on Future Machines. With the discovery of the Higgs Boson Self-consistent model (SM) accounting for all Particle Physics phenomena.
J. Mnich for Pier Oddone | ICFA Report to Lepton Photon 2013 June 28, 2013 | Page 1 ICFA Report to Lepton Photon 2013 J. Mnich (for Pier Oddone, ICFA chair)
CLIC detector & physics study “news from the ET ” Lucie Linssen L. Linssen, IB meeting, 18 April
Global Design Effort Americas Region Efforts and Resources Mike Harrison GDE.
ILC Project status Philip Burrows John Adams Institute Oxford University 1.
Status of Linear Collider Activities Rika Takahashi on behalf of the LC Communicators 104 November, 2013 Interactions US.
Hitoshi Yamamoto, 15-Mar-2013, ILC detector monthly meeting, KEK 1 Detector Introduction.
Nick Walker, Brian Foster LAL, Orsay WP2: Coordination with the GDE.
E.Elsen European LC Workshop, Cockcroft, UK, Jan 2007 Perspectives for European LC R&D.
International Linear Collider The ILC is the worldwide consensus for the next major new facility. One year ago, the choice was made between the two alternate.
Atsuto Suzuki. 1. Toward ILC Construction : Japanese Activities 1. Toward ILC Construction : Japanese Activities.
1 The Design & Value Costs SRF Technology The XFEL as a Prototype Japan as a Host International Linear Collider Status Mike Harrison.
The time line Autumn 2011CERN Council initiated an update exercise to the European Strategy for Particle Physics which was approved by a special Council.
Contractor Assurance System Peer Review April Page 1 NSTAR 2011 May 16, 2011 Jefferson Lab Hugh Montgomery.
Global Design Effort - CFS TILC09 and GDE AAP Review Meeting - Tsukuba, Japan 1 GDE ACCELERATOR ADVISORY PANEL REVIEW CONVENTIONAL FACILITIES.
Date Event Global Design Effort 1 ILC UPDATE Vancouver to Valencia Ewan Paterson Personal Report to SiD Collaboration Oct 27, 2006.
ILC in Japan A 10 minute introduction H.Weerts Argonne National Lab March 24, 2014 University of Chicago.
24-Aug-11 ILCSC -Mumbai Global Design Effort 1 ILC: Future after 2012 preserving GDE assets post-TDR pre-construction program.
HEPResearchers Set-up JLCB and JLCC ~6 Cite Decision Design ILC Lab. Japan Policy Council Positive Reference from New Prime Minister.
THE INTERNATIONAL COMMITTEE FOR FUTURE ACCELERATORS (ICFA) Roy Rubinstein2nd International Conference on New Frontiers in Physics - 4 September
Status of the Project April EPOG, 12th Outreach-Meeting, CERN, Petra Folkerts, DESY 1 Report from DESY, Hamburg, Germany The Status of TESLA and.
Status Report on ILC Project in Japan Seiichi SHIMASAKI Director, Office for Particle and Nuclear Research Promotion June 19, 2015.
Office of Science U.S. Department of Energy 1 International Linear Collider In August 2004 ICFA announced their technology selection for an ILC: 1.The.
1 GUTs and Branes DESY Theory Workshop 2003 A brief introduction to the future of particle physics at DESY Albrecht Wagner Hamburg, 23 September 2003.
Status of the International Linear Collider and Importance of Industrialization B Barish Fermilab 21-Sept-05.
SiD – Beyond Snowmass Andy White University of Texas at Arlington for the SiD Concept 1/18/2013SiD Beyond Snowmass A. White.
SPAFOA OVERVIEW Kenneth O. Olsen SLAC and LBL meetings Sept 22/23, 2015.
ILC D RAFT P ROJECT S CHEDULE K LYCLUSTER 500GeV K Foraz & M Gastal ILC Mechanical & Electrical Review and CFS Baseline Technical Review Many thanks to.
1 Future Circular Collider Study Preparatory Collaboration Board Meeting September 2014 R-D Heuer Global Future Circular Collider (FCC) Study Goals and.
Industrial Participation & SRF Infrastructure at Fermilab Phil Pfund with input from Harry Carter, Rich Stanek, Mike Foley, Dan Olis, and others.
Glion Colloquium / June Accelerating Science and Innovation R.-D. Heuer, CERN HL-LHC, Aix-les-Bains, 1 Oct ECFA HL-LHC Experiments Workshop.
Hitoshi Yamamoto, 2-Oct Detector Tohoku Forum for Creativity - a Pilot Program - ‘Particle Physics and Cosmology after the Discovery of the Higgs.
CERN-US Relations and the LHC Program Rüdiger Voss Head of International Relations, CERN USLUA Annual Meeting, Argonne| November 12-14, 2014.
P5 Potential US Accelerator Collaboration with the ILC-in-Japan Mike Harrison Mike Harrison.
1 Comments concerning DESY and TESLA Albrecht Wagner Comments for the 5th meeting of the ITRP at Caltech 28 June 2004 DESY and the LC What could DESY contribute.
CPM 2012, Fermilab D. MacFarlane & N. Holtkamp The Snowmass process and SLAC plans for HEP.
ICFA J. Mnich (DESY) November 5, J. Mnich | ICFA LCWS Panel Discussion 5 November 2015 | page 2 ICFA Web Page and Mandate ICFA: International Committee.
Fermilab-India Agreements and Collaboration Shekhar Mishra Project-X, International Collaboration Coodinator Fermi National Accelerator Laboratory Batavia,
LCC L. Evans, Santander, 2nd June 2016
ICFA and the Linear Collider
Summary of WG2 :CFS for staging
ILC Decision Timeline in Japan (KEK/JAHEP) and Asian LC overview
Introduction to the Workshop
Process of the 2nd update of the European Strategy for Particle Physics FCC week, 29 May 2017, Berlin Sijbrand de Jong, President of the CERN Council (slides.
Matthias Liepe Zachary Conway CLASSE, Cornell University June 1, 2009
Yasuhiro Okada, Executive Director, KEK
Prospect of Indo-US Collaboration
Presentation transcript:

1 SPAFOA Capitol Hill Briefing December 2013 Harry Weerts International Linear Collider - progress & status SPAFOA meeting, Dec 11, 2013, H.Weerts

2 Japan – The proposal SPAFOA meeting, Dec 11, 2013, H.Weerts

3 Japan – Science Council of Japan SPAFOA meeting, Dec 11, 2013, H.Weerts

4 Japan – Science Council of Japan

Linear Collider Collaboration(LCC) working timeline Taking into account recommendations from SCJ for “time for negotiations”.

6 Japan – Site selection “ SPAFOA meeting, Dec 11, 2013, H.Weerts Completed in September 2013

Access Tunnel Access Hall (Slope <10%) Damping Ring Detector Hall Ring To Main Linac (RTML) e- Main Linac (ML) e+ ML RTML turn-around e- Source e+ Source (Slope <7%) Existing surface road Existing road ( The background photo shows a similar site image, but not the real site.) Surface Structures PM-13 PM-12 PM-10 PM-8 PM-ab PM+8 PM+10 PM+12 PM+13 (Center Campus) PX Kitakami-site cross section Site Specific Design Need to establish the IP and linac orientation Then the access points and IR infrastructure Then linac length and timing From November 2013 workshop:

The Cryomodule m (slot length) cavities (8)SC quad package Type-B module Type-A has 9 cavities and no quadrupole 8 Needed for Phase I (250GeV): CryomodulesCavities If one assumes production sites in Asia, Europe and USA, then 1/3 of this might be from USA LCLS II: 35 cryomodules

9 Global expressions of support From the EU strategy report (after operate and upgrade the LHC) “There is a strong scientific case for an electron-positron collider, complementary to the LHC, that can study the properties of the Higgs boson and other particles with unprecedented precision and whose energy can be upgraded. The Technical Design Report of the International Linear Collider (ILC) has been completed, with large European participation. The initiative from the Japanese particle physics community to host the ILC in Japan is most welcome, and European groups are eager to participate. Europe looks forward to a proposal from Japan to discuss a possible participation.” “On Sept. 3, Asia-Pacific High Energy Physics Panel (AsiaHEP) and Asian Committee for Future Accelerators (ACFA) have jointly issued a statement that the International Linear Collider (ILC) is the most promising electron positron collider to achieve the objectives of next-generation physics. “ SPAFOA meeting, Dec 11, 2013, H.Weerts

10 US – HEP strategy (P5) Just started – complete April 2014 SPAFOA meeting, Dec 11, 2013, H.Weerts

11 US – Participation The US was prominent in the global R&D program which ran from > These activities resulted in significant DOE investment in developing SRF infrastructure at Fermilab/Argonne and to a lesser extent JLAB. High gradient cavity R&D was started at the labs and from there to US industry via tech transfer A total of 60+ cavities were purchased during this time and AES was certified for ILC production US labs were active in the accelerator design as well as other hardware R&D (SLAC, JLAB, BNL, ANL, LLNL & Cornell) The R&D program was completed in 2012 and since then ILC work in the US has effectively ceased – wait and see strategy SPAFOA meeting, Dec 11, 2013, H.Weerts

12 US – Participation There is obviously no decision on the go-ahead for a construction project in Japan and whether the US will participate. Should the US decide to collaborate on a phased-ILC then it is likely that cryomodules would form a significant part of a US contribution. A 250 Gev machine would require ~900 cryomodules and since the global capacity for cryomodule production is limited then I would guess that the US would produce >200 elements. Making some assumptions about the construction schedule then production would start towards the end of this decade. This dovetails well with LCLS II. SPAFOA meeting, Dec 11, 2013, H.Weerts