1 Tim Michalski October 6, 2015 Engineering Issues in MEIC.

Slides:



Advertisements
Similar presentations
Tom Powers Practical Aspects of SRF Cavity Testing and Operations SRF Workshop 2011 Tutorial Session.
Advertisements

MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
A.KOVALENKO SUPERCONDUCTING MAGNETS for NICA BOOSTER & COLLIDER NICA ROUND TABLE DISCUSSION - 3 JINR, Dubna, November 05, 2008.
PEP-II and BaBar DND Review M. Sullivan Mar 23-24, 2009Page 1 PEP-II Overview and MMS Status Michael Sullivan SLAC National Accelerator Laboratory.
R. Ostojic, WAMSDO, 19 May 2008 LHC Insertion Region Upgrade Phase I 1.Upgrade goals and milestones 2.Review of IR systems: main findings 3.The emerging.
Crab Cavities in IR1 and IR5 Some considerations on tunnel integration What will be the situation in the tunnel after the LHC IR Phase-1 Upgrade. What.
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
MCTF Michael Lamm MUTAC 5-Year Plan Review 22 August Magnet R&D for Muon Accelerator R&D Program Goals Proposed Studies Preliminary Effort and Cost.
Page 1 Jean Delayen HyeKyoung Park Center for Accelerator Science Department of Physics, Old Dominion University and Thomas Jefferson National Accelerator.
Global Design Effort Push-pull studies How to proceed LCWS07 June 1, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi.
Hall C Meeting SHMS Magnets and Support Structure Design and Procurement Status Paul Brindza January 26, 2009.
Global Design Effort Beam Delivery System => EDR LCWS07 June 2, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi Yamamoto.
R&D, Collaborations and Closeout Fulvia Pilat MEIC Collaboration Meeting March
PEP-II Machine Advisory Committee Meeting SLAC, April 15-17, 2004 HOM Issues in LER Ring and IR. Recent measurements and calculations. Sasha Novokhatski.
PEPII Magnet Feasibility in the MEIC ECR Tommy Hiatt – MEIC Collaboration 10/07/ of 15.
4th BEPCII IMAC Meeting April , 2006 Status of BEPCII Storage Rings Ma Li April 26, 2006.
CesrTA EC Build-Up and Mitigation Program - Introduction Mark Palmer June 25, 2009.
Booster and Collider SC magnets. Design & prototyping of UHV and cryostat systems for Booster and Collider A.Smirnov JINR, Dubna, Russia NICA Machine Advisory.
Interaction Region Backgrounds M. Sullivan for the MEIC Collaboration Meeting Oct. 5-7, 2015.
BDS: 1 October 13, 2007 BDS KOM EDR planning discussion Andrei Seryi October 13, 2007.
Design Optimization of MEIC Ion Linac & Pre-Booster B. Mustapha, Z. Conway, B. Erdelyi and P. Ostroumov ANL & NIU MEIC Collaboration Meeting JLab, October.
1Matthias LiepeAugust 2, 2007 Future Options Matthias Liepe.
Project X RD&D Plan Beam Transfer Line and Recycler Injection David Johnson AAC Meeting February 3, 2009.
1 V. Kashikhin for ILC ALCPG 2007, FNAL Meeting October 23, 2007 Ring to Main Linac Magnets.
FNAL efforts on LHC Crab Cavity R&D (Proposals for R&D sub-tasks, resources and schedule) Nikolay Solyak.
LARP Collaboration Meeting, April 19, 2007Super-Ferric Fast Cycling SPS – Henryk Piekarz1 LHC Accelerator Research Program bnl-fnal-lbnl-slac - Motivation.
Low Energy RHIC e - Cooling 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity.
Overall Layout 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity.
DR Layout Description ILC DR Technical Baseline Review Frascati, July 7, 2011 Mark Palmer Cornell University.
Overall Layout 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity Booster Cavity and Gun move (next slide)
Status of MEIC Beam Synchronization V.S. Morozov on behalf of MEIC study group (summary of the results of a series of special MEIC R&D meetings) MEIC Collaboration.
Magnet R&D for Large Volume Magnetization A.V. Zlobin Fermilab Fifth IDS-NF Plenary Meeting 8-10 April 2010 at Fermilab.
Engineering for the JLEIC pre-CDR Tim Michalski JLEIC Spring Collaboration Meeting March 31, 2016.
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
November 12-13, 2007 Super-B Factory: Accelerator Costing, PEP-II Hardware and Schedule J. Seeman SLAC International Review Committee meeting November.
JLEIC SC Magnet Working Group Meeting
SLHC –PP WP6 LHC IR Upgrade - Phase I.
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
TTC Topical Workshop - CW SRF, Cornell 12th – 14th June 2013
Large Booster and Collider Ring
JLEIC R&D Review: Other R&D
Nonlinear Dynamics and Error Study of the MEIC Ion Collider Ring
The first shipment of SPEAR3 magnets (9 dipoles and 12 quadrupoles) arrived April 3. The second shipment (3 dipoles, 7 quadrupoles, and 6 sextupoles)
Collider Ring Optics & Related Issues
MEIC Cost Estimate Overview
Accelerator R&D Results from the B-factory
EIC Accelerator Collaboration Meeting
IR Magnet Layout/Design - JLEIC
Summary of Washington DOE Review
Peter McIntyre Visit Overview Slides
ERL Director’s Review Main Linac
JLEIC SC Magnets: Replace SF and High CM Energy Needs
Electron Collider Ring Magnets Preliminary Summary
MEIC Shifting Magnet Tim Michalski August 6, 2015.
Update on the JLEIC pCDR
JLEIC Engineering Status
IR Beam Transport Status
JLEIC Accelerator R&D Meeting
IR Magnet Design and Engineering Considerations
The Feasibility of Using RHIC Magnets for MEIC and Cost Impact
The MEIC electron ring as the large ion booster
Fanglei Lin, Yuhong Zhang JLEIC R&D Meeting, March 10, 2016
Status and plans for crab crossing studies at JLEIC
JLEIC Magnet R&D Tim Michalski NP Community Panel Review of the EIC
JLEIC Engineering Status
MEIC Design Update Fulvia Pilat MEIC R&D Meeting May 21, 2015.
HE-JLEIC: Do We Have a Baseline?
Crab Crossing Named #1 common technical risk (p. 6 of the report)
Model Dipole Fabrication & Testing 2016 Plan, Schedule, Budget
JLEIC SC Magnets: Replace SF and High CM Energy Needs
Presentation transcript:

1 Tim Michalski October 6, 2015 Engineering Issues in MEIC

2 MEIC Engineering R&D Focus on areas of technical risk Support R&D priorities of the MEIC Program Support MEIC collaborations, as required

3 MEIC Engineering R&D Superferric Model Dipole Magnet PEP-II Magnets FFQ / IR Magnets, other magnets SRF R&D Support Machine Layouts Synchronization – Moving Magnets Others Areas of Consideration

4 Superferric Model Dipole Magnet JLab’s Goal: Develop a solid understanding of the SF magnet technology – champion its implementation for MEIC's Ion Collider Ring and Ion Booster Ring. Collaborate with TAMU on the design and analysis of a 1.2m model dipole magnet prototype and test it to ensure performance to 3T. Develop a cryostat concept design which is cost effective and manufacturable.

5 Status of the Superferric Magnet Concept Design Review in June, 2015 – down select to CIC JLab has contracted TAMU to develop a 1.2m superferric model dipole Deliverable 1 – Concept Design – COMPLETE Deliverable 2 – Prototype Cable-In-Conduit winding – In Process, due at the end of CY’15 – more from Peter McIntyre Follow on fabrication contract is planned Test to 3T at a 3 rd party test facility SF Dipole End – With and Without Coil Supports

6 PEP-II HER and LER Magnet Evals PEP-II designs reflected against requirements for MEIC Electron Collider Ring, modeled in TOSCA – more from Tommy Hiatt Evaluated for field vs. current, multi-poles, temperature rise, etc.

7 FFQ and IR Magnets Evaluations Understand performance parameters of the FFQs and other Specialty Magnets in the Interaction Region and Straight Segments. Perform initial assessments of stored energy, SC selection, current requirements, and design concept will be performed.

8 SRF R&D Support Perform analyses in support of SRF cavity design, prototyping, and testing. Analyzing tuning sensitivity/stiffness, pressure sensitivity, and Lorentz force detuning.

9 Machine Layouts Develop mechanical layouts of the various beamlines within MEIC to assess fit of all machine elements. 1) Develop element lists for all beamlines. 2) Create baseline layouts of the various beamlines 3) Assess regions where density requires further evaluation - straights and Interaction Region 4) Assess interface between SF Arc Half Cell cryostats

10 Synchronization Concept Evals Assess moving magnets in the Ion Collider Ring and Electron Collider Ring. 1) What is the cost of implementation for moving large, heavy magnets? 2) How much time will it take to reposition magnets for different energies? 3) Assess layout options in the tunnel - affect tunnel cross section. Preliminary assessment complete on all questions

11 Considerations for Repositioning Superferric Magnets Moving a string of magnets radially inward and outward is feasible Use slides and measurement scheme to make repeatable Rotation of magnets will be required as well Considerations for interfaces between magnets and to outside world Beamline Vacuum – bellows between adjacent beam pipe vacuum chambers Insulating Vacuum – bellows between adjacent Arc Half-Cells Power – “service loop” for conductors Cryogens – flex hoses between adjacent Arc Half- Cell cryostats Example: LHC Magnet Cryostat Interface

12 Considerations for Repositioning PEP-II Magnets Moving radially inward and outward is feasible Use slides and measurement scheme to make repeatable Rotation of magnets will be required as well – if not doing entire arc Considerations for interfaces between magnets and to outside world – no major issues Vacuum – assess capacity to expand/contract RF shielded bellows between raft and dipole

13 Other Areas of Consideration JLab Electron Cooling – ERL –Support JLab's design of an ERL for bunched beam electron cooling. RF Systems Development –LLRF development required more than HPRF. Vibration effects – tolerance of machine elements versus environment Inspect and test PEP-II magnets and RF/HPA/PS System Optimization – SF Magnets, Cryo System, DC Power, Power Distribution Costing Updates – Design Report

14 PEP-II Magnets POTENTIAL FUTURE ACTIVITY: Evaluation of reusing the HER raft assemblies and, more importantly, the Vacuum System elements. 1.Inspect magnets and vacuum elements in-situ at SLAC. 2.Select 1 each of the HER and LER magnets for de-installation and delivery to JLab for further evaluation and testing. 3.Test the HER and LER magnets for comparison to existing SLAC data. 4.Inspect the HER and LER magnets for degradation and validate assumptions on refurbishment labor and materials. 5.Inspect the HER magnet vacuum chambers for cleanability, refurbishment, and potential re-use in MEIC's Electron Collider Ring.

15 PEP-II RF/HPA/PS POTENTIAL FUTURE ACTIVITY: Evaluation the functional state of PEP-II RF/HPA/PS elements 1.Inspect the RF/HPA/PS elements in-situ at SLAC. 2.Select 1 each of the elements for de-installation and delivery to JLab for further evaluation and testing. 3.Test the RF Cavity, HPA, and PS for MEIC specs. 4.Inspect the elements for degradation and validating assumptions on refurbishment labor and materials.

16 Summary – Next Steps Summary: Continued efforts on magnets. Continued support of SRF. RF systems work coming. Next Steps: –SF Magnet Review at TAMU in December –Review of overall machine size – all elements –Update machine layouts in CAD –FFQ and IR magnets – Q2’16 –LLRF systems – Q2’16 Acknowledgements: Peter McIntyre and the team at TAMU, Tommy Hiatt, Renuka Rajput-Ghoshal, Cory Johnson, Mitch Laney, Fredrik Fors