Hilton Baltimore Convention Center Hotel Andrew Rhodes Spring 2007 Faculty Advisor: Dr. Bahnfleth.

Slides:



Advertisements
Similar presentations
An Introduction To Marine Steam Propulsion Plant [Source: US Navy]
Advertisements

Chapter 3. HVAC Delivery Systems
* A chiller capable of producing water temperatures of low 40s on the evaporator side and above 135° on the condenser side.
UCSD Medical Center - Hillcrest Campus Case Study Gerry White Facilities Design & Construction University of California, San Diego.
Lindbergh Field International Airport New Terminal Bill Mahoney LSW Engineers.
1 Optimizing the Efficiency of the NCAR-Wyoming Supercomputing Center Ademola Olarinde Team Member: Theophile Nsengimana Mentor: Aaron Andersen August.
Learning Outcomes Upon completion of this training one should be able to: Identify open loop and closed loop campus-type hydronic water system applications.
Denver Place North & South Towers Case Study Matt Urquhart Amerimar Realty Management Company Jack Wolpert E-Cube, Incorporated.
This tutorial is a PowerPoint ® file which includes recorded narration. Automatic slide sequencing is coupled to the sound track. For the most effective.
UTSW Thermal Energy Plants, Power Generation and Electrical System What do we do to meet the Emission Reduction, Energy usage Reduction and Electrical.
West Virginia University Alumni Center Gregory Smithmyer | Mechanical Option | Penn State University | April 15, 2009 | Advisor: Dr. Srebric.
Jacksonville, FL The Pennsylvania State University Department of Architectural Engineering Zachary Polovchik Mechanical Option Advisor – Dustin Eplee Duval.
UTSW Thermal Energy Plants, Power Generation and Electrical System What do we do to meet the Emission Reduction, Energy usage Reduction and Electrical.
Coppin State University Physical Education Complex Kaylee Damico – Mechanical Option April 12 th, 2011 Presentation Outline Project Team Project Overview.
Presentation Outline Introduction CHP Analysis Electrical Analysis Acoustical Analysis Thermal Storage Analysis System Optimization Analysis Conclusion.
Integration of Mechanical System Redesign Geothermal Heat Pump Redesign Wesley S. Lawson Architectural Engineering Mechanical Option Pennsylvania State.
…an innovative shell and tube heat exchanger with an exceptionally high heat transfer coefficient for industrial fluid cooling and air conditioning.
Steam Power Station Presented By Ashvin G. Patel Asst. Prof. (E.E.)
Building Systems Integration - Energy and Cost Analysis The Milton Hershey School New Supply Center Justin Bem AE Senior Thesis – Spring 2007 Mechanical.
Bowie State University Fine and Performing Arts Center Zachary Lippert Faculty Advisor: Dr. Stephen Treado.
Charles F. Hurley Building Case Study B.J. Mohammadipour Bureau of State Office Buildings.
CNN Center John Hester Turner Properties, Inc.. CNN Center Built in ,583,000 square feet on 18 floors Five structures joined by a common atrium.
Chilled Water Systems Total Cost of Ownership
The Edward St. John Student Center Zachary Haupt Faculty Advisor: Dr. William Bahnfleth 11 April 2011.
Gas Turbine Power Plant
Auraria Higher Education Center Case Study John Ismert & Frank Ellis Auraria Higher Education Center Facilities Management.
Important variables Water: Air: Conversion:
DEA Clandestine Laboratory Training Center Penn State University Architectural Engineering Mechanical Option David M. Potchak.
Lecture Objectives: Finish with HVAC Systems Discuss Final Project.
SENIOR THESIS PRESENTATION An Evaluation of Water-Side Economics & Emissions Sinai Hospital South Tower Vertical Expansion 2401 W. Belvedere Ave. | Baltimore,
Foothill College & Space Science Center Bill Kelly Viron Energy Services (510) ext 13,
City of Hope Amini Medical Center Christopher Bratz Pennsylvania State University Architectural Engineering Mechanical Option Faculty Advisor: Dr. Jelena.
N VAV system varies the air quantity rather than temperature to each zone n Single main duct is run from AHU n Branch duct are run from this main through.
Architectural Engineering Mechanical Option Ft. Detrick Defense Medical Logistics Center Building Systems Redesign April 16, 2008 Senior Thesis Presentation.
November 2004 Low Hanging Fruit Low Cost Energy Efficiency Opportunities in Cleanrooms.
Ray & Joan Kroc Corps Community Center Mathias Kehoe | Mechanical Option April 09, 2012.
University Ridge at E ast Stroudsburg University Matthew Carr Spring 2007 Mechanical Option Faculty Advisor: Dr. Freihaut.
Hilton Hotel at BWI Airport Nathan Patrick The Pennsylvania State University Architectural Engineering – Mechanical Option.
VIMS Seawater Research Laboratory Dan DiCriscio AE Senior Thesis Mechanical Option 2007.
Bronx School for Law Government & Justice Yulien Wong Mechanical Option 2006 Senior Thesis Bronx, New York.
Tri-Valley Jr./Sr. High School Hegins, PA Senior Thesis, Spring 2004 Studying The Feasibility of a Dedicated Outdoor Air System.
Architectural Engineering Senior Thesis Mechanical System Redesign Saint Joseph Medical Center Chris Nicolais.
Lecture Objectives: Clarify issues related to eQUEST –for midterm project Learn more about various HVAC - economizer - heat recovery Discuss about the.
APPELL LIFE SCIENCES York College of Pennsylvania Joshua Martz | Dr. Srebric | April 11, 2011 Image Courtesy of RLPS, Ltd.
University of Maryland’s Gossett Field House College Park, MD Jason Borowski Architectural Engineering Mechanical Option Pennsylvania State University.
Jonathon Gridley Senior Thesis – Spring 2007 Mechanical Option Energy Efficient Mechanical System Alternatives South Jefferson High School S OUTH J EFFERSON.
Greenbriar East Elementary School Fairfax, Virginia Michelle L. Siano Mechanical Option Spring 2005 Senior Thesis.
Straumann USA 60 Minuteman Road Andover, MA Kevin Kaufman Mechanical Option The Pennsylvania State University Architectural Engineering.
Building Systems Integration - Energy and Cost Analysis The Milton Hershey School New Supply Center Justin Bem AE Senior Thesis – Spring 2007 Mechanical.
THERMAL POWER PLANT.
INOVA Fairfax Hospital South Patient Tower Falls Church, VA Senior Thesis 2012 Mike Morder Mechanical Option Advisor: Dr. William Bahnfleth.
Malory J. Faust ∙ Mechanical Option ∙ Senior Thesis 2007.
Jesse A. Fisher Mechanical Option Spring 2005 Riverpark Corporate Center, Phase 1 Salt Lake City, Utah.
The Montgomery County Conference Center and Hotel 5701 Marinelli Road, Rockville, MD.
The New Student Housing Building at The Mount St. Mary’s University Emmitsburg, Maryland Erik Shearer Mechanical Option Advisor: Dr. Srebric Spring 2007.
Copyright © 2015 Optimum Energy LLC. All Rights Reserved. Proprietary & Confidential Incorporating Energy Conservation Strategies into University Research.
NOLAN JAMES AMOS Dr. William Bahnfleth, Faculty Consultant architectural engineering senior thesis mechanical option PHOENIXVILLE EARLY LEARNING CENTER.
Manoa Elementary School Amanda Cronauer Faculty Advisor: Dr. William Bahnfleth 14 April 2010.
Harley-Davidson Museum
Energy Savings Projects
Eastern High School Baltimore, MD
By: John D. Villani, P.E., LEED AP, QCxP, CEM, GBE
Grunenwald Science and Technology Building
Eastern Pennsylvania Laboratory Facility
Biobehavioral Health Building, University Park, PA
LONGWOOD AT OAKMONT HEALTHCARE CENTER
Feasibility of Ice Storage
Senior Thesis Presentation
Virtua Replacement Hospital -Voorhees NJ
Tri-Valley Jr./Sr. High School Hegins, PA
Presentation transcript:

Hilton Baltimore Convention Center Hotel Andrew Rhodes Spring 2007 Faculty Advisor: Dr. Bahnfleth

Presentation Outline Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation

Project Background Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation Project Cost: $250 Million Groundbreaking: February 2006 Completion: August 2008 Owner: Hilton Hotels Adjacent to Oriole Park at Camden Yards and the Baltimore Convention Center

Project Background Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation East Podium Three Levels Restaurant, Starbucks, Junior Ballroom, Meeting Rooms West Podium Three Levels Main Lobby, Grand Ballroom, Lounge, Meeting Rooms, Hotel Management Guest Room Towers Levels 4 through Guest Rooms, Service Areas

Existing Mechanical System Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation Cooling Comfort Link District Chilled Water System (2) Plate and Frame Heat Exchangers 1,000 tons each District Side – 37 F to 54 F Building Side – 42 F to 56 F Two pumping zones with (2) pumps each

Existing Mechanical System Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation Heating Trigen District Steam System 150 psi steam from Trigen 50 psi steam after pressure reducing valve (2) Shell and Tube Heat Exchangers 810 gpm each Entering Water Temp – 140 F Leaving Water Temp – 180 F Kitchens served by steam directly

Existing Mechanical System Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation Air Handling (8) Air Handling Units AHUs 1-7 – VAV units with economizers AHU 8 – CAV unit with economizer (4) Makeup Air Units MAUs 1-2 – Serve Guest Room Towers MAUs 3-4 – Serve Kitchen Spaces (1) Pool Air Conditioner

Design Objective Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation Chiller Plant Optimization Study Consider numerous chiller plant design alternatives in order to quantitatively prove which alternative is the most cost-effective. A Life-Cycle Cost Analysis, based on first and yearly operating costs, will be the basis of the optimization. Lowest Life-Cycle Cost = Most Cost-Effective System

Mechanical Design Alternatives Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation Option 1: District System with Backpressure Steam Turbine Replaces Pressure Reducing Valve with a Backpressure Steam Turbine

Mechanical Design Alternatives Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation Option 2: On Site Centrifugal Chilling Replaces Comfort Link District Chilled Water System with (2) 950 ton centrifugal chillers (2) condenser water pumps along with two-celled cooling tower added Primary / Secondary pumping arrangement (2) primary pumps added All secondary pumps remain

Mechanical Design Alternatives Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation Option 3: On Site Absorption Chilling Replaces Comfort Link District Chilled Water System with (2) 950 ton double-effect absorption chillers Chillers utilize steam at 100 psi (2) condenser water pumps along with two-celled cooling tower added Primary / Secondary pumping arrangement (2) primary pumps added All secondary pumps remain

Mechanical Design Alternatives Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation Option 4: On Site Absorption Chilling with Backpressure Steam Turbine Identical to previous design alternative, but with Backpressure Steam Turbine added Extraction type Backpressure Steam Turbine required, allowing for 2 separate outlet steam pressures

Energy Analysis Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation In order to calculate the yearly operating costs of all the systems, two factors must be known… Cost of energy (Utility Rates) Amount of energy (Hourly energy usage data)

Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation Utility Rates Actual utility rates were obtained from Comfort Link, Trigen, and Baltimore Gas & Electric. Energy Analysis Electric Utility Rate District Chilled Water Rate District Steam Rate

Energy Analysis Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation Hourly Energy Usage Data eQuest 3-6 used in order to create a detailed model of the Hilton Baltimore Convention Center Hotel Once the building model was completed, only the plant information was changed Backpressure Steam Turbine modeled in Microsoft Excel using data imported from eQuest 3-6

Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation Energy Analysis The on site centrifugal chilling design alternative has the lowest yearly operating cost, while the current district system has the highest. Savings of $ 24,507 compared to next lowest yearly operating cost.

First Costs Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation The current district system has the lowest associated first cost, while absorption chilling with backpressure steam turbine has the highest. Savings of $ 21,000 compared to next lowest first cost.

Life-Cycle Cost Analysis Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation The on site centrifugal chilling design alternative has the lowest life-cycle cost, while the current district system has the highest. Savings of $ 721,161 compared to next best design alternative. Savings of $ 3,094,057 compared to current district system.

Life-Cycle Cost Analysis Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation Surprising Results… Hilton Hotels will pay $0.69 per therm of Trigen district steam, while a rate of $0.61 per therm would make absorption chilling with backpressure steam turbine worthwhile. Unit prices from Both of these rates are lower than the price of producing steam using natural gas or oil. How does Trigen produce its steam?

Electrical Breadth Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation Purpose: Provide electrical service to the equipment selected in the most cost-effective mechanical design alternative (on site centrifugal chilling). (2) Chillers wired directly to main distribution panel All other associated equipment placed on a new panelboard

Electrical Breadth Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation Switchgear F (the main distribution panel) needed to be resized in order to handle the new loads Main circuit breaker increased from 2000A to 5000A Resized Main Distribution Panel Original Main Distribution Panel

Final Recommendation Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Project Background Existing Mechanical System Design Objective Mechanical Design Alternatives Energy Analysis First Costs Life-Cycle Cost Analysis Electrical Breadth Final Recommendation Based on the design objective, it is the final recommendation of this report that on site centrifugal chilling, along with associated cooling towers and pumps, be installed at the Hilton Baltimore Convention Center Hotel.

Questions ? Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007